Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 60 - 79)

WEDNESDAY 31 JANUARY 2001

MR ROBIN YOUNG, MR GUY WILSON AND MR CHRISTOPHER O'BOYLE

  60. You mentioned catering and we are led to believe from correspondence which the Committee has seen that they also had experience in running car parks, which, given the position you have arrived at is the full circle, is it not, because that is essentially what you are doing, is it not?

  (Mr O'Boyle) We are running a corporate operation; by corporate we must not assume it is purely catering or silver service. The Armouries is actually a very important asset for the region. It is used by a lot of organisations for inward investment. We have a growing band of corporate/government events, organisations which use the Armouries and we are very proud of the service we offer.

  61. The point I am making is that the dream your company had and the role you had has been significantly cut back. We are told in the report that it is an important job but it is catering and car parks.

  (Mr O'Boyle) It is, and that was part of the deal we had to face up to as part of the restructuring of 1999. What I would say to you is that we were able to recruit the best people from the leisure industry to join us for the launch, indeed I am pleased to say that our first operations director has gone on to a very senior post in the tourism industry. Her deputy, whom we recruited from Tussaud's is actually now a senior figure in another leisure organisation.

  62. It struck me, and the Chairman's opening question alluded to it as well, that it is a bit like the Dome to some extent in that some of the seeds of the problem were sown at quite an early stage. I was struck by the report which is really, as far as I can see, a catalogue of neglect and failure. Let us look at paragraph 4. This is a high risk project which failed to attract more than one seriously interested party from the outset. Should warning lights not have been flashing?

  (Mr Young) The answer to that is yes. Under current guidance for PFI projects, if there is not sufficient interest from the private sector we are urged to reconsider or alter the offer so as to attract more private sector interest.

  63. In paragraph 1.23 we are told that Tussaud's were interested originally. They have enormous experience of visitor attractions, they said that the visitor projections for the Armouries were too optimistic. Was their view not seriously listened to?

  (Mr Young) We should have reconsidered and the current guidance would have obliged us to reconsider the offer we are putting to the market. The answer is yes. So, I repeat, we should either have altered the offer so as to attract more interest, or put some conditions to it, for example a minimum level of visitors being achieved, so as to attract more people. The current guidance, as the report rightly points out, would oblige us to do just that.

  64. What was their visit projection?

  (Mr Young) I do not know, I am afraid.

  (Mr O'Boyle) In the discussions they were talking around about the high 500,000 to 600,000-ish. Warwick Castle was their benchmark. At the time that was getting about 625,000; it is now getting over 800,000. That fell within our downside sensitivities which we put together.

  65. Warwick Castle has been around for a long time. It has a history footfall. It is not a new high risk venture, is it? One of the aims of this project was part of a process of making heritage bodies more self-sufficient, was it not?

  (Mr Young) Yes.

  66. There was as the stick at the end of it all a real threat that the public purse would not be there to pick up the bill any longer. So there must have been pressure to push on with this PFI from the outset.

  (Mr Young) As the report makes clear, this was one of the very earliest PFIs and lessons which we now take for granted had not yet been learned. The report rightly points out and compares current guidance on PFI projects and the Government Department's behaviour in this one. You put your finger on two of them: we ought to reconsider if there is not sufficient market interest; we should look askance if a well-known organisation like Tussaud's walks away because of difficulty in the offer we are making. We should have altered the offer. We should have been alerted by the lack of private sector interest to it. That is what the report says and current guidance would oblige us to do just that.

  67. Why was no public sector comparator sought?

  (Mr Young) Because the open explicit objective laid out on page 12 was to obtain maximum private sector funding.

  68. In other words, you did not have to.

  (Mr Young) We did not have to. That was the explicit open statement of policy.

  69. You were getting advice from Schroders at the time who were quite keen on the project going ahead. They had been involved from the start. Who else was giving you advice at that point? Who was providing a perhaps more objective and fresh pair of eyes?

  (Mr Wilson) At that time on the financial side Schroders were the only advisers.

  70. According to paragraph 1.11, Schroders said that there would be a net revenue of somewhere in the region of £4.2 million a year. It is pie in the sky, is it not? We are also told that when the visitor figure reached more than 1.3 million, the taxpayer would start to benefit from that and get some money back. Which consultant advised you, of all the ones you chose, that you would get more than 1.3 million?

  (Mr Wilson) No-one said more than 1.3 million.

  71. Nobody did?

  (Mr Wilson) No.

  72. Not one of them did, yet that was the point chosen at which the taxpayer would begin to get some of the benefit from this. Not one set of advisers had suggested that that was possible.

  (Mr Wilson) Correct.

  73. When was PFI guidance introduced?

  (Mr Glicksman) About 1995.

  74. Paragraph 19 says that had there been guidance then the Armouries would have been better placed to deal with some of the problems which came along later.

  (Mr Glicksman) That is correct.

  75. Figure 6 says that it is the joint responsibility of the parties involved to agree performance requirements so that if things did go wrong, people would know what had been expected of them and hopefully things could be put right. Why were those performance requirements not ever produced?

  (Mr Young) Because the parties could never agree and it was not a prior condition before things started that the agreement should be in place, which it would be now. You are rightly underlining another difference between current PFI guidance, which says that this sort of agreement should be entered into by agreement between both sides before the thing starts, whereas in 1993 the opposite happened. The project got under way with the obligation on them to try to agree and they never did.

  76. Paragraph 1.61 is another one. Failure to agree access to financial records. When things go wrong you are then groping around in the dark, are you not, and the clock is ticking.

  (Mr Young) That is correct. Current PFI guidance obliges transparency which was not the case in 1993.

  77. Failure to secure access to assets in the event of the termination of the contract. The possibility of having to wait two years before the taxpayer could see what was left for them.

  (Mr Young) All of which we have sorted in the revised deal. In the deal which was done in 1999 all of those conditions, in line with current guidance, are met. There is now transparency, there is an agreement between them and everything you have mentioned so far has been sorted in the revised deal. It was not there in 1993; it just was not there.

  78. As you well know, and as is often said in this Committee, the benefit of hindsight and experience is a wonderful thing. That is not what I am getting at in these questions. What I am getting at is that even without the benefit of hindsight, why is it that the planning appears to have been so lax, that something was missing here? You are talking about people who should know better and yet what appears to be very basic precautions have not been taken.

  (Mr Young) I can only say that the specific objective was to maximise private sector contributions. The private sector would not have agreed—ask Mr O'Boyle—but, if that was thought at the time that we could not load in other things. This was the best deal available at the time with the knowledge and experience of PFI deals which we then had.

  79. Whatever the cost to the taxpayer, what we now have is a revised deal which is not a PFI and we have the company which was set up to deliver it—which takes me back to the point I was making earlier—doing the catering and dealing with the car parks. It really does not represent good value for taxpayers' money and actually does a disservice to people who were looking for a very, very good museum in the north of England.

  (Mr Young) Perhaps I could say two things. If you look at table 7 on page 14, this shows that the total cost of this was £42.6 million, of which about one third was paid for by the private sector. As the rest of the report makes clear, the private company, Mr O'Boyle's company, has built up debts of £21 million which are not public sector debts. The private sector has paid for one third of the project. It has debts of £21 million, for which the public sector is not liable, so it has not been a risk free thing for the private sector. The public sector has gained to that extent that we have had one third of the project financed by the private sector and the debts arising from the disappointing first few years are not with the public sector. In that sense we have not done badly. In fact what we have done is put too much of the risk in the private sector so that the project is not sustainable. In order to maximise the private sector contribution, we have given them obligations they could not fulfil, with the result that the deal had to be renegotiated. I would argue that the re-balanced deal which was done in 1999 is wholly in line with current PFI guidance and does give a good deal to the taxpayer. It also sustains what is a world class excellent museum in Leeds.

  Mr Campbell: It is a pity it was not done earlier.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2001
Prepared 30 July 2001