Future competition
20. Another factor in rejecting the BAE Systems unsolicited
proposal was the value of retaining the potential for warship
competition between UK shipyards in the future. The Department
considers that the new arrangements for the Type-45 give it a
strategy which looked "a good way of keeping two companies
in the warship building business."[31]
The previous plan of a head-to-head competition between Vosper
Thornycroft and BAE Systems Marine for the fourth and subsequent
ships had the potential of the loser going out of warship building,[32]
as the loser would be faced with building one of the three vessels
in each batch at the price offered by the winning bidder.[33]
Instead, CDP told us, "if you allow competition to kill off
one of two effective companies, then you have no competition for
ever. The Type-45 strategy retains an element of competition,
a needle if you like, between two yards, each of whom are trying
to perform better than the other, without putting them into a
head-to-head, winner-takes-all, loser-disappears situation. I
think it is quite constructive."[34]
The RAND consultants acknowledged that the solution now settled
upon by the MoD "helps ensure that both shipbuilders will
remain viable and able to compete on future MoD programmes",[35]
but were cautious about the nature and extent of that future competitive
capability
For future programmes such as the [Future Surface
Combatant] and [the Future Carrier], Vosper Thornycroft's continued
presence increases the chance of Vosper Thornycroft being in the
market to compete for these programmes. Sole-source and, to some
degree, the directed buy of blocks may not allow Vosper Thornycroft
to maintain its warship construction capabilities, leading to
future programmes facing a monopoly in warship construction ...
Keeping Vosper Thornycroft active in building warships will be
positive for future MoD programmes. A caveat must be stated for
the option of a directed buy of blocks, however: Once that paradigm
is chosen, it may be difficult to choose another paradigm for
future programmes.[36]
21. The RAND analysis also underlines a wider concern,
about the availability of competition for future warship programmes
within the UK. Their report noted the risks, had Vosper Thornycroft
withdrawn from warship building, of BAE Systems Marine securing
a monopoly position[37]
(since it is government policy that only UK shipyards should be
allowed to build warships). They noted widespread concern within
industry about the prime contractorBAE Systems for
the Type-45 and Astute submarines, and possibly for the Future
Carrier, also controlling three shipyards involved in those same
programmes.[38] In the
short term at least, demand for warship building work would remain
low, and as the industry consolidated there would be less impetus
for innovation.[39] The
RAND study identified a clear market trend over the next 15 years.
Demand for blue-collar workers is set to decline slightly between
now and 2006, after which demand will increase rapidly with work
on the Type-45s and Future Carriers to a peak of nearly 7,000
'direct' workers in 2010almost double the level in 2005.
Consequently, RAND identified a risk for the MoD's future warship
building programme in being able to maintain and expand the labour
force in the next several years while managing a small dip in
demand.[40] In his evidence
to us, Sir Robert Walmsley too highlighted the need to retain
shipyards with their special warship building skills.[41]
He distinguished, however, the need for the MoD to help maintain
shipbuilding capacity needed for warship construction
where the yards building the Type-45 destroyers would be sufficient
and for its non-warfighting ships where many other yards
were available and provided competition without MoD intervention.[42]
22. Maintaining sufficient warship construction capability
in the UK remains essential not just for political reasons. There
is no international reciprocity in the shipbuilding industry,
and the relatively low design content of warships in terms of
their total cost reduces the impetus (compared with aircraft programmes,
for example) for international collaboration to share the non-recurring
costs.[43] To maintain
UK shipbuilding capacity until the expected rise in demand, Sir
Robert considered that industry too had a part to play by improving
its export performance
For as long as I can remember, we have been dealing
with over-capacity in shipyards. The problem has not been shortage
of labour; the problem has been shortage of orders to sustain
the shipyards.[44]
We should be doing better in terms of securing warship
export business. The Type-45 gives a platform and both companies
can look for a certain future from the Ministry of Defence over
a long period. Of course there will be some uncertainty about
it but the Type-45 should be enough to help launch some export
programmes.[45]
If we do not use as a nation the opportunity presented
by our warship building programme over the next ten years, in
order to present designs that are attractive to other countries,
we will only have ourselves to blame for what happens to the warship
building industry in the next decade after that.[46]
23. Shrinking demand in a market with surplus
capacity appears to be the backdrop for many areas of the defence
industry, and perhaps it can be said to be a more intractable
problem for the warship construction industry (it also affects
the ship repair industry as we shall see later in this report).
It is clear to us that in the Type-45 programme the MoD has sought
to weave a strategy through often conflicting pressures, not just
for minimising costs and maximising competition (when it can be
effective), but also balancing what might be best in the long-term
as well as the near-term. And, with the complexities of warship
procurement, the MoD appears at least to have made reasonable
choices, backed by expert advice. There are clearly dangers still
in the approach adopted. There is uncertainty about the prospects
for genuine competition for future programmes, like the Future
Surface Combatant, from shipyards which may only by then have
experience of fabricating 'blocks' rather than assembling ships.
The MoD will have to determine how to support warship building
capacity for the lean short-term to ensure that it is available
when needed in nearly a decade's time. And even the smooth passage
of ship work at Barrow's Devonshire Dock Hall will have to be
monitored carefully.
24. But at least the problems of this industry
are starting to be addressed. It is clear to us that the sort
of work commissioned from RAND provides a valuable and timely
analysis of the state of the warship construction market in the
UK. From their examination of the procurement options available
to the MoD, it is evident that a clear strategy is now needed
for warship procurement. The RAND analysis would be a useful starting
point.
The construction of the Future
Carrier
25. Like the Type-45 programme, the Future Carrier's
development programme has been revised following representations
from the bidders (BAE Systems and Thales). In this case, the firms
had sought a longer 'assessment' phase to reduce risk in the designs.
In response, the MoD introduced a new phase-3 to the assessment
studies. The plan now is to down-select to a preferred bidder
at the end of a shorter phase-2 in November 2002, with a Demonstration
and Manufacture contract to be awarded in early 2004.[47]
In the current phase-2 work, the two contractors are working up
designs able to take either a 'short take-off and vertical landing'
(STOVL) or a conventional 'Carrier Variant' aircraft,[48]
pending the selection of the particular variant of Joint Strike
Fighter later this year (paragraph 85).
26. There have been recent reports[49]
suggesting a possible smaller than previously planned order for
the STOVL version from the aircraft's US customers, which could
increase the unit cost of a STOVL aircraft for the UK if it chose
to adopt that variant (paragraph 86). In terms of the external
size and shape of the Future Carrier, however, we were told that
there will be little difference between STOVL and Carrier Variant
versions of the ship.[50]
27. Nevertheless, there will still be challenges
for building a 50,000 tonne carrier in the UK for the first time
in half a century.[51]
Shipyard capacity is such now that the Future Carrier cannot be
built at one location. The Type-45 programme, however, is providing
a model for its construction. Shipyards will have to cooperate
to build modules in different locations and then assemble them
elsewhere. RAND highlighted how the 'hook-up' of the blocks will
be a greater challenge with the Future Carrier than with the Type-45,[52]
and in that light CDP saw the experience with the Type-45 and
the Alternative Landing Ship Logistic (ALSL) as particularly valuable.
The ALSL is being constructed on the Clyde to a Swan Hunter design,[53]
and that requires co-operation between two yards "who do
not instinctively cooperatethis is practising at it."[54]
Sir Robert saw in these developments the beginning of a "network"
of shipyards that could co-operate to build ships.[55]
28. As we have discussed above, the construction
of the Future Carrier and Future Surface Combatant (the successor
to the frigate force) will require extra shipyard capacity beyond
about 2009. This was mainly a question, CDP told us, of securing
sufficient labour capacity in the shipyards at that time: "It
will not be a question of building some huge crane in some lonely
dry-dock somewhere. There are very few issues relating to facilities,
other than modernising."[56]
To assemble a modular Future Carrier, CDP identified three likely
candidates with an infrastructure large enough for its final assembly
Harland & Wolff in Belfast, Inch Green on the Clyde
and Cammell Laird in Birkenhead.[57]
We understand that Swan Hunter are also developing a large dry-dock
which will be able to accommodate the vessel, and that Rosyth
are working on similar plans.
11 RAND's consultancy report, The Royal Navy's New-Generation
Type-45 Destroyer: Acquisition Options and Implications, has
been placed in the Library of the House (HC Deb, 2 July 2002,
c233w). Back
12
Ev 103 Back
13
Eighth Report, Session 1998-99, op cit Back
14
Ev 99, para 8 Back
15
Ev 99, para 11 Back
16
Q 2 Back
17
QQ 2, 17 Back
18
Ev 99, para 13 Back
19
Mean of 7%, but a range median of 11% Back
20
RAND Report, op cit, page 52; Q7 Back
21
Q 8 Back
22
RAND Report, op cit, p 64; Q 8 Back
23
Q 17 Back
24
RAND Report, op cit, p 56 Back
25
RAND Report, op cit, p 58 Back
26
Q 17 Back
27
RAND Report, op cit, p 62 Back
28
RAND Report, op cit, p 66 Back
29
QQ 19-21 Back
30
Fourth Special Report, 1999-2000, HC 223, para 16 Back
31
Q 9 Back
32
Q 8 Back
33
RAND Report, op cit, p 47 Back
34
Q 16 Back
35
RAND Report, op cit, pp 64-65 Back
36
RAND Report, op cit, pp 60-61 Back
37
RAND Report, op cit, p 85 Back
38
RAND Report, op cit, p 73 Back
39
RAND Report, op cit, p 75 Back
40
RAND Report, op cit, p 70 Back
41
Q 10 Back
42
QQ 14-15 Back
43
Q 11 Back
44
Q 25 Back
45
Q 15 Back
46
Q 26 Back
47
Ev 92, para 14 Back
48
Ev 106, para 4 Back
49
see Aviation Week, 1 April 2002 Back
50
QQ 37-39 Back
51
The last such carrier, the previous HMS Ark Royal, was completed
in 1955. Back
52
Q 32 Back
53
Strictly speaking, a design put together by Swan Hunter and Royal
Schelde, its Dutch strategic partner, according to MoD evidence
submitted to the Scottish Affairs Committee's inquiry into Employment
in Shipbuilding on the Clyde (Fifth Report, Session 2001-02,
HC 865). Back
54
Q 28 Back
55
ibid Back
56
Q 24 Back
57
QQ40-43 Back