Timescales |
|
1.Determination of Application/consultation of stakeholders
| 4 months>6 months |
2.Baseline operation | 2 months1 2 months
|
3.Commissioning/optimisation | 2 months2>4 months
|
4.Trialing the fuel at the selected replacement rate
| 2 months 2 months |
At the end of the trial use of the fuel must discontinue until permanent authorisation is achieved. Environmental gains achieved during the trialing period are immediately reversed and the plant returns to higher emission levels.
|
5.Trial report preparation3/application for permanent use
| 3 months 3 months |
6.Agency determination4 | 4 months>6 months
|
|