SCHEMES WHICH HAVE BEEN/MAY BE AFFECTED BY PIPS RULING

  It seems to be generally accepted that the EC view that PIP was an illegal state aid effectively ruled out any project in which the private sector sought public sector funding directly (and possibly indirectly).

  The draft SEZ IDPs states that the establishment of a simple and straightforward gap funding mechanism is a "critical success factor" for the management of the Objective 1 Programme—"The success of the Programme depends on the substantial involvement of private sector developers".

EMPLOYMENT SITE PROJECTS (HISTORIC/ONGOING)

Site/project Comment
Sash Productscompleted prior to PIP ruling.
J36 SRB infrastructure£1.2 million off site infrastructure project funded by SRB. Committed prior to PIPs decision. Scheme directly benefits three private sector developers and it may not now be possible to do similar schemes.
Dunlop Slazengeragreed prior to PIP ruling but ability to transfer premises development to another user is uncertain.
Land reclamation schemesfor hard afteruse—see briefing note on LRP implications.
Priority Sitesjoint venture (English Partnerships and Royal Bank of Scotland). Have a generic floorspace approval which was agreed prior to PIPs ruling. We are negotiating to secure PS development in Barnsley. Agreement ends in c two years.


POTENTIAL EMPLOYMENT SITE PROJECTS AT RISK

  Many of our main employment sites are owned by the private sector. Any public sector/Objective 1 assistance in terms of site preparation or floorspace will be difficult. Many projects we are discussing with SEZ IDP consultants include:

SiteComment
Junction 37Sterling Capitol require gap funding and Objective 1 support for site preparation.
Junction 36Potential PIP and/or Objective 1 funding required.
Claycliffe sitesPotential PIP and/or Objective 1 funding required.
Goldthorpe Industrial EstatePotential PIP and/or Objective 1 funding required.
Houghton MainPotential PIP and/or Objective 1 funding required.
GrimethorpePotential PIP and/or Objective 1 funding required.
Thurnscoe BPPotential PIP and/or Objective 1 funding required.
Barnsley Miller PartnershipAny infrastructure or floorspace development at Fields End, Grimethorpe or elsewhere.


TOWN CENTRE PROJECTS (HISTORIC)

SiteComment
George Yard/ArcadeAround £350K PIP to fund the restoration of the Beehive/Linen warehouses to commercial use.


POTENTIAL URBAN CENTRE (OBJECTIVE 1 IDP) PROJECTS AT RISK

SiteComment
Stocks Lane Mixed Use AreaPotential PIP and/or Objective 1 funding required.
Old Mill Lane development sitePotential PIP and/or Objective 1 funding required.
Former Gas Depot, Old Mill LanePotential PIP and/or Objective 1 funding required.
Former Van Leauven Tubes redevelopment site Potential PIP and/or Objective 1 funding required.
Dunlop/Slazenger, Doncaster Road, Barnsley Potential PIP and/or Objective 1 funding required.
Former Canister Co sitePotential PIP and/or Objective 1 funding required.
Peel Street PFSPotential PIP and/or Objective 1 funding required.
Markets Mixed-use redevelopment sitePotential PIP and/or Objective 1 funding required.
Interchange Mixed-use redevelopment site Potential PIP and/or Objective 1 funding required.
Design 2001Potential PIP and/or Objective 1 funding required.
Regent Street/Royal StreetPotential PIP and/or Objective 1 funding required.
  
Jerry Youle and Peter Willows
Planning & Transportation  

18 January 2001




 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2002
Prepared 25 February 2002