Select Committee on Transport, Local Government and the Regions Appendices to the Minutes of Evidence


Memorandum from the Highways Agency (59A)

  Thank you for your letter of 18 February. I offer the following clarification on the points raised.

NEW APPROACH TO APPRAISAL

  Schemes are subject to the New Approach to Appraisal (or NATA) throughout their development, whenever a significant decision stage is reached.

  They are subject to assessment prior to entering our Targeted Programme of Improvements. For example, our original Targeted Programme of Improvements (TPI) of 37 schemes emerged from the application of NATA to 67 candidate schemes during 1998. Schemes that have entered the TPI since have all been subjected to NATA, and schemes currently being considered within multi-modal and road-based studies are all equally subject to the same appraisal method.

  The current appraisal process we follow is as set out in "Guidance on the Methodology for Multi Modal Studies" which can be viewed at www.dtlr.gov.uk/itwp/mms/index.htm.

  Once in the TPI, scheme appraisals under NATA should be updated at the key decision stages— public consultation, at preferred route announcement, order publication and at any subsequent public inquiry.

5 PER CENT REDUCTION IN CONGESTION—EFFECT ON TRAVEL TIMES.

  You have asked for details of the effect a 5 per cent reduction in congestion would have on travel times on our network. The modelling for the 10 Year Plan is the responsibility of the central department—and it would be more appropriate for them to answer these detailed questions. We have passed your questions to them and have asked them to reply directly to you.

  I can confirm the HA were asked to provide the indicative pricing for the mixture of illustrative schemes in the published 10 year plan.

  The illustrative scenarios of constant motoring costs and trunk road charging were assessed by DTLR using the same programme of illustrative schemes from us.

  Details of the underlying assumptions made in DTLR's (then DETR's) modelling were published with the 10 Year Plan in a document entitled "Transport 2010-The Background Analysis". This can be viewed at www.detr.gov.uk/trans2010/index.htm.

BYPASSES IDENTIFIED AS AT THE END OF 2001.

  The table below lists the 25 bypass schemes identified and placed in the Targeted Programme of Improvements (TPI) by the end of 2001. The original (July 1998) list of 19 included a scheme on the A23 in Coulsden, which has since passed to the Greater London Authority. The scheme on the A11 at Attleborough was originally classified as a congestion-relieving scheme, but is now counted as a bypass (which means we still have 19 bypass-schemes from July 1998).

Tim Matthews

Road and scheme name
Date scheme entered TPI
1  A27 Polegate Bypass
July 1998
2  A43 Silverstone Bypass
July 1998
3  A6 Great Glen Bypass
July 1998
4  A11 R'ham H'th-Attleborough Imp (now Attleborough Bypass)
July 1998
5  A66 Stainburn and Great Clifton Bypass
July 1998
6  A6 Clapham Bypass
July 1998
7  A500 Basford, Hough, Shavington Bypass
July 1998
8  A650 Bingley Relief Road
July 1998
9  A120 Stanstead-Braintree Improvement
July 1998
10  A41 Aston Clifton Bypass
July 1998
11  A63 Selby Bypass
July 1998
12  A5 Nesscliffe Bypass
July 1998
13  A6 Rothwell-Desborough Bypass
July 1998
14  A6 Rushden and Higham Ferrers Bypass
July 1998
15  A6 Alvaston
July 1998
16  A10 Wadesmill-Colliers End
July 1998
17  A21 Lamberhurst Bypass
July 1998
18  A421 Great Barford Bypass
July 1998
19  A5 Weeford-Fazely Improvement
July 1998
20  A47 Thorney Bypass
March 2000
21  A38 Dobwalls Bypass
March 2001
22  A3 Hindhead Improvement
March 2001
23  A595 Parton-Lillyhall
March 2001
24  A14 Haughley New Street-Stowmarket Improvement
March 2001
25  A483 Pant-Llanymynech Bypass
August 2001





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2002
Prepared 27 May 2002