Select Committee on Culture, Media and Sport Appendices to the Minutes of Evidence


APPENDIX 2

Memorandum submitted by Arup

1. The Clerk of the Culture, Media and Sport Select Committee asked for information from Arup, supplementary to the evidence given by Mark Bostock, Sam Higginson and Nick Banks on 14 January 2003.

Question: Can you explain the rationale for using a discounted cashflow approach?

2. Discounting is recommended by the Treasury (see the Treasury Green Book for more details) as the most appropriate way to appraise investment in a particular project. The rationale for using a discount rate approach is something called 'social time preference' i.e. Government would prefer to have its goods and services sooner rather than later so that costs and revenue flows in the distant future are valued less than costs and revenue flows in the near future. A discount rate of six per cent was the standard recommended Treasury discount rate when we did our work (May 2002). This week a new discount rate of 3.5 per cent in the revised Green Book has been introduced.

Question: Was your work based upon an exempler Games?

3. Our work was based upon a 'specimen' or 'exempler' Games for London. As you know, the Arup Summary Report concluded that there was a considerable potential to improve the financial profile of the 'specimen' proposal through further development.

Question: Were your costs a 'high' estimate as they were based upon Sydney outturn prices?

4. Our land and infrastructure cost and revenue projections were based upon current experience of the costs of construction of facilities in the UK, supported on land costs and revenues by the real estate market knowledge of Insignia Richard Ellis. Our staging cost and revenue estimates drew upon a range of sources including recent previous bids from European cities such as Paris for 2008 and the outturn cost and revenues from the Sydney 2000 Olympics. Where appropriate we based our staging cost and revenue projections upon Sydney. The advantage of using the Sydney cost and revenue profiles is that they are outturn costs rather than bid cost and revenue profiles which may be over optimistic. Overall our costs and revenues were our best professional estimates given the time (16 weeks in early 2002) and the resources available.

Question: If cost estimates are inflated to 2012 prices must revenues and benefits also be inflated?

5. A consistent methodology and approach to the appraisal of the project is required. If costs are inflated to 2012 prices, revenues and benefits must also be inflated.

Question: Are benefits which can't be and/or weren't captured by (i) your particular study, and (ii) cost/benefit methodologies in general (needing other appraisal techniques)?

6. There are benefits which it has not been possible to quantify and incorporate into the analysis. Examples of such benefits would include the 'feel good factor' a boost to 'image' of the country, or an increase in sports participation amongst the general population. It is fair to say that there could also be potential unquantifable risks for example a badly run Games could have a negative effect on 'image'. Currently it is not possible to quantify or monetarise these impacts. We have placed significant importance on the need to identify the benefits at the outset, because of their importance in off­setting the financial deficit that we have concluded will be incurred.

Question: There seems to be some debate over apportionment—the scope of the Government's term 'public subsidy' which may cover costs not within the scope of your study (i.e. wider security for London, accelerating or guaranteeing planned infrastructure projects to meet the Olympic timetable (bidding as well as staging), or even customs and immigration in 2012) i.e. there is debate over the recipe as well as the likely size of the resulting cake.

7. There is not only a debate over the recipe as well as the size of the cake but also the attribution of costs and benefits. An example is government agencies claim that additional capital works will be required at Stratford station. We would accept this but argue that not all of these costs are necessarily attributable to the Olympics. If they are included as costs, the benefit of such provision needs to be incorporated in the revenue/benefit assessment.

Question: What work Sydney/Athens did or didn't do and how their process compared to the work undertaken by Arup and subsequently the Government and PwC?

8. I'm afraid we don't have any information on this. As far as we are aware no other study of the type we did is available in the public domain. Certainly, previous recent British efforts were promoted by cities/local authorities/individuals, without a full analysis of the overall costs and benefits of going for a bid/staging.

Summary Question: Why is the Government's estimate different from Arup's?

9. The first point we must emphasise is that our commission was a high­level cost­benefit analysis of a possible 2012 London bid. It was not a formal budget, nor did it represent a bid document.

10. In the Arup Summary Report, which went into the public domain in November 2002, we presented the case for a Mill Meads Olympic Village and an athletics legacy for the stadium. Most of the Government evaluation has been based upon a Mill Meads Olympic Village with a football legacy—this means that there are some small discrepancies amongst the totals (athletics gives you a better financial result because of the smaller footprint required for the legacy stadium allowing more post Games development on adjacent sites). For consistency we have focused upon Mill Meads with a football legacy in the figures below.

11. The best place to start is where we started which is to establish the cost and revenues line items in 2002 prices.

  • costs in 2002 prices were estimated to be: £2,820 million, revenues: £1,998 million, balance: £822 million;

  • if you discount these figures using a 6 per cent discount rate you get costs £1,808 million, revenues: £1,260 million, balance: £548 million;

  • if you inflate these figures you get costs £3,443 million, revenues £2,450 million, balance: £983 million.

12. If you then look at the table submitted in the DCMS written evidence you will see an Arup base case and a DCMS case of £3,558 million in costs (we would argue that there is a small discrepancy in methodology here and it should be £3,443 million).

13. Government has then factored in a number of additional cost items equivalent to £1,090 million in inflated prices. They have also included a revenue risk allowance of £400 million. This should give you a result of—£2,483 million.

14. Whichever methodology is adopted a full appraisal of the project also requires an allowance to be made for wider quantifiable economic benefits. To produce an initial estimate in inflated prices we have taken the Arup case tourism assumed benefits as well as the Arup base case fiscal and employment benefits and inflated these figures. We have also assumed, a boost to exports after the Games of £0.5 billion in 2002 prices. Finally we have assumed that investment in tourism would be zero. Wider benefits in inflated prices using this initial analysis indicate a figure of £2.24 billion.

15. An overall position in inflated prices is set out in the table below (we have assumed a similar level of anticipated wider benefits in the DCMS case as we have projected in the Arup case).

Table 1

SUMMARY ARUP AND DCMS FINANCIAL AND ECONOMIC PROJECTIONS USING INFLATED PRICES

  
Arup £ billion inflated prices
DCMS £ billion inflated prices
Costs
Revenues
3.44
2.45
4.53
2.05
Financial balance
Wider benefits
-0.99
2.24
-2.48
2.24
Economic balance
1.25
-0.24


Summary Question: Why did Sydney and Athens get it wrong by 100 per cent and what is the likelihood we won't?

16. We are not able to comment in detail upon the Sydney and Athens experience from bid to outturn. We stated it in our report and reiterated during our oral evidence that if this experience is not to be repeated in London any Olympic Games will require effective co­ordination and project management. We contend that a concordat between the key stakeholders must be agreed upon before any bid is submitted (ie to cover both bidding and staging). Our emphasis is a strong project managed delivery, incorporating private sector skills to deliver this major event and establishing a legacy thereafter.

20 January 2003  



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 23 January 2003