Select Committee on Culture, Media and Sport Minutes of Evidence


Examination of Witnesses (Questions 163 - 179)

WEDNESDAY 15 JANUARY 2003

MR RICHARD SUMRAY, MR TONY WINTERBOTTOM, MR MICHAEL WARD, MR JAY WALDER AND MR BARRY BROE

  Chairman: Gentlemen, thank you very much indeed for coming to see us this afternoon. We have got a very attenuated timescale for this report and we are grateful to you for co-operating in the timetable. Mr Wyatt?

Mr Wyatt

  163. Good afternoon. We have had an interesting day and a half so far. What concerns us most is transport. What can you tell us that will put us out of our misery so we can give a tick for this Olympic Games? We have been told three separate stories on Crossrail. Can we just dismiss that? If you dismiss it, are you confident the alternatives will be there? Given that London comes to a halt every day somewhere, we do not want people to miss their heats as they did in Atlanta.
  (Mr Walder) On behalf of the GLA group let me welcome the opportunity to appear before the Committee this afternoon. We understand the issues of transport, we have looked at it carefully in the initial stage. One of the great advantages here is the siting of the games. The siting of the Games in the Thames Gateway is both ideal from the interests of regeneration and transport, it is obviously one of the most deprived areas of the country and it has been highlighted in the London Plan as an opportunity area for London. It is also a very sensible location from a transport perspective. This area has good transport infrastructure and there are improvements underway right now that will make that transport infrastructure much better, such as a major increase in capacity on the Jubilee Line as part of the PPP effort and the Channel Tunnel Rail Link which are underway. What that says, along with our review of this, is that with some additional infrastructure and I think it is relatively modest in the scheme of things, and importantly, service enhancements and demand management, we believe that London's transport system can accommodate the Games. While Crossrail is a critically important project for London and the Mayor and TfL are very supportive of it and continue to plan the project, we believe that a successful London Games can be delivered without the Crossrail project. We believe that we can manage all of the issues, the planning, the building and operation, in order to be ready for the 2012 Olympic Games and we would urge to proceed on that basis. So I think the transport issues for the most part should not be a constraint within the overall scheme.

  164. Let me come on to the management of big projects. Wherever you look in London, the Eye did not open on time, Portcullis overran by two years, the British Museum has had its problems, the British Library took 17 years, the Dome was on time, but, sadly, the Jubilee Line was only open two days before when it should have been open two years before. Have we really got the skill in management in this country to manage big projects because there is not much evidence that we have?
  (Mr Winterbottom) Most of the projects that you have just referred to are projects in the public sector and a lot of those projects were projects where there perhaps was not the final definition which enabled a firm tight contract to be put together and I do agree that recent history is littered with those. However, there is also a number of projects in the country that are unsung but actually run to time and are built budget. And certainly as far as the London Development Agency is concerned, we have substantial experience of much smaller projects—I grant you, they are not as complex as the ones that you have just mentioned—where we have been able, working with the private sector particularly and making sure that we have really researched the project, to bring projects in on time and to budget. The only confidence that I can give you in relation to this project is perhaps the way that we have approached it. Contrary to any other project that I am aware of, when we first got involved with this project the Mayor insisted that we actually looked and did a pre-feasibility study as to whether or not this was something that we should go for, which is the Arup Report and I think at least that has given us a good baseline to look at the sort of complex issues that we have to deliver. We think that delivering the Games will be complex, will be difficult, but clearly it will need a very focused, very firm and very clear line of delivery with people who understand delivery and it needs to be time critical, but we do have quite a lot of time.

  165. Mark Bostock yesterday said kept saying it was a specimen contract. Is the difference of opinion between the Government and the Arup Report the fact that this is not fully a costing of the actual Games, this is a sort of model of what could be the Games? If it is actually the Games then why are they called specimen costings?
  (Mr Winterbottom) This is where I would like to go into your first question also. It is very important we get the stages of this bidding process correct. We have not spent a great deal of money on the Arup Report, but what it has done is it gives us that specimen, these are the issues that have to be tackled, this is what we think those issues will cost. There is another piece of work that needs to be done and that needs to be done relatively quickly. If London and the Government decide that we should bid for those Games then the important thing is that each of those items need to be thoroughly investigated as part of the bidding process so that we are very clear as we go forward that we understand the issues, the costs, the difficulties, the challenges and in each sub-component of that bid we understand what the end date is, when we have to deliver it, what it is going to cost, who is going to deliver it and who is going to be responsible. That is the reason that we have gone down this route of getting a pre-feasibility piece of work.

  166. The Chancellor is looking at this. That means that on the 30 January the Government is going to go okay, we have the full figures, it looks like £5 billion, we do not know but we will do it.
  (Mr Sumray) What all the parties were agreed to, and this was a stakeholders group in which the Government and other parties were involved, was to get this cost benefit work done and in order to do that, as Arup expressed yesterday here, they developed the specimen proposal. The specimen proposal is not going to be exactly what the end result is and in fact if you look at the history of bids the end result is never quite what is even bid for. It is pretty well there or thereabouts and we believe that what Arup has come up with is actually sustainable and robust, but Arup have done this independently. The Government have had an independent review of that and there are discussions going on between Arup and the Government about this. That is right and proper and it is right and proper that as much work as possible can be done around costs. I think the other thing is that in our knowledge and certainly I think this has also been expressed here, no other event of this kind has ever had such detailed work done on it before any announcement has been made about whether or not to make a bid. We think that is absolutely right and proper given the history we have had of some of the projects that have gone wrong, but it will never be exact at this stage, it cannot be. What you can get is a scenario, and I know the Government are developing this, around the probability and risk and I think that is what one has to go with in the end.

  167. The thing about the World Athletics Championship is nobody claimed it for London, no one owns it physically, no one claimed "This is ours". People were attached to it but nobody owned it. Manchester City worked for the Commonwealth Games. Even if they got the figures wrong initially, they owned it and bullied it and it won. Here we are being asked as a Government to trust the GLA, a relatively new body, to work across four boroughs that are stretched at the moment to run their boroughs. Do you think that this should be run by a Minister being chairman of this so that there is a Minister inside the Cabinet Office, do you think it should be run in the Mayor's office with somebody full time there? Do you think the BOA should be chairman of running this from Wandsworth? What is your view of taking this forward?
  (Mr Ward) First of all, it needs clear ministerial ownership. In a sense the start point is that no national bid can succeed without proper support from international government and that does mean the ministerial champion. The World Athletics Championship did not have an effective sponsor in London because we were in the period of no London government at that time, we relied on Government office and less formal structures. We now have a wide range of structures. While the GLA is a new organisation, Transport for London draws upon 70 years experience of London transport as an organisation. The London Development Agency draws upon the very substantial project management experience of English Partnerships which in turn draws on the experience of London Docklands Development Corporation as major players in East London. I took my colleagues to talk to people in Manchester who had worked both on the Commonwealth Games and on the Olympic bid earlier this year. The Manchester experience is it needs to be very firmly rooted in the local authority. There they had an organisation to run the Commonwealth Games but the local authority itself procuring the stadium as a capital project. We think, and there is more work to do on the detail, you will need at least one special delivery vehicle to do the Olympics and that will need to be sponsored both by Government and by ourselves. You will probably need an organisation to run and market the Games. You will certainly need an organisation to build the stadium. Some of the international experience suggests you need a dedicated authority with transport and highways powers.

Chairman

  168. Mr Ward, you have just offered a recipe which if it had been followed in Manchester would have led to a disastrous Commonwealth Games. Although Mr Wyatt is absolutely right in saying that Manchester owned the Commonwealth Games, Manchester City Council very wisely and readily accepted that they had to be under a Minister and that the Minister had to create the structure, control the structure and take responsibility for it. This is not a question of Government support. In New South Wales the Minister for Sport was in control both of organising the Games and organising the transport. Anything else and we are headed for, in my view, a catastrophe. A Minister in charge as in Manchester is a huge success. In a moment I would like you to respond to that, but I want to put a couple of other points consequent upon what Mr Wyatt has been asking. Firstly, Mr Walder said he is confident that the Jubilee Line will be able to cope. I do not know if Mr Walder was on the Jubilee Line this morning—I was. The Jubilee Line was practically inoperable. There were two separate signal break downs in two separate places, hundreds of people were fighting to get on the trains at every station when these trains actually arrived. The argument is that after the botch of the way in which the signalling system was originally produced for the Jubilee Line Extension the whole signalling system needs to be replaced. How after day after day experience when I travel on the Jubilee Line Mr Walder can be confident that in eight and a half years it will be ready, I fail to understand and I would be grateful for clarification. Thirdly, I heard no answer to the question put by Mr Wyatt about Crossrail. Transport for London sends us in a document which says we are not factoring in Crossrail. Okay, that creates problems about getting to the new stadium, but nevertheless that is clear. The Secretary of State yesterday says no factoring in of Crossrail. In a statement published in the Evening Standard yesterday the Mayor says Crossrail will be running by 2011 and will be a great boost to getting to the Olympic Games stadium. Arup says the delivery date for Crossrail is by 2016 but some of it should be in place in time for the Games. I really would like to know which, if any, of these statements is accurate.
  (Mr Walder) If I can take each in turn. I shared the use of the Jubilee Line this morning and I do use it on a regular basis. You are correct to say that there are very serious signalling difficulties on the Jubilee Line as it stands right now. You are correct to say that the Jubilee Line needs an entirely new signalling system on that line, I have no argument with either of those two statements. The point I was making was that that is actually contracted for now. In the contract that the Government let in December of last year for the JNP portion of the PPP the specification includes a complete new signal system on the Jubilee Line by 2009, so it is fair to accept that the situation as it sits today would not be adequate to do it, but I think the project is both funded and moving forward and in place to be able to do it well before 2012. That enhancement to the Jubilee Line is quite significant. In terms of the trains, it would add a seventh carriage to the train which is an increase of 15% on each train that goes through. In addition, it would increase the peak capacity of the system from about 22 trains an hour running currently to about 30 trains per hour as it would run with the new signal system. In aggregate you would get about a 45% increase in capacity on the Jubilee Line which is the equivalent of a very major enhancement as a result of that. In regard to Crossrail, the Crossrail project is proceeding. It is the expectation, with Government support, that Crossrail would come as part of a hybrid Bill before Parliament later this year, but the most optimistic schedule for Crossrail has the project being completed around the end of 2011. This is a project of a magnitude greater than the projects that you identified before. It is a project that at this point is only in the preliminary design stage. We have not gone through achieving Parliamentary powers, we have not gone through the process of bidding out and structuring the project and completing that work. You would be hard pressed as we sit here today to say that the largest public works project that has been undertaken will be brought in spot on from a schedule developed before preliminary design is completed. It would be inappropriate to plan on that basis.

  169. Could you or Mr Sumray explain why the Mayor yesterday said it will be ready for use in time for the Commonwealth Games in 2012?
  (Mr Sumray) It is a question for the Mayor. I think the point that Tessa Jowell made to you this morning to you is right, that the Olympic Games can be delivered without Crossrail being there and at this stage I think, as she put it, it is a risk in relation to being completed in time. The key thing is, and this was dealt with in the Arup Report, can it be delivered without Crossrail. The Arup Report indicated and Transport for London are in agreement that it can be delivered without Crossrail. Even more to the point, talking about breakdowns, Sydney in its Olympic Games relied upon one particular loop in the railway system to get 70% of the spectators to it. Had that broken down during the Olympic Games there would have been real problems and it did break down when that system was first launched about 18 months beforehand. It did not, but in fact in the London context here we have many more routes into East London than Sydney actually had so there is less risk with the London situation than there was with the Sydney situation.
  (Mr Walder) The other major significant infrastructure investment that would be made on the transport side is the Channel Tunnel Rail Link. That project is scheduled for completion by 2007. In both the case of the Jubilee Line and the case of CTRL you are not putting yourself in a position where you are backed up against the wall in terms of completing those projects on time to be ready for the Olympic Games. The site that has been selected benefits from four tube lines, two national rail lines and the Docklands Light Railway. That is a very very significant transport capacity. Overall, when you look at the entire system, the Olympic Games would add about 1% to the daily transport flows that we deal with in London, a range, as you point out this morning, that the system has to accommodate on a fairly regular basis. The real issue in terms of transport is not the delivery of these major projects, the real issue is the concentration of activity in a very small area. That will likely necessitate some improvements, like station improvements at Stratford station, but that is nowhere near the complexity of the other items that you have mentioned.

  170. Okay. What you say, Mr Ward, is very persuasive, but I would still like to hear from Mr Sumray, who is here as the Mayor's representative, why the Mayor is quoted within quotation marks in yesterday's Evening Standard as saying that Crossrail should be running by 2011 and will be a great boost to transport in time for the Olympic Games.
  (Mr Sumray) That is the timetable that is there at the moment. It is desirable, the Mayor has expressed it in this way, for it to be completed in time.

  171. He did not say desirable, he said it would be there.
  (Mr Sumray) That is the plan at the moment. If it was there it would be a significant boost to the Games.

  172. He did not say that, he did not hypothesise. He said that provided Government approval is given, which he expects shortly, Crossrail will be in operation by 2011 and will be a great boost to the Olympic Games.
  (Mr Sumray) The last part of that is absolutely right. The first part is the Mayor working on the expectations under the current plans that it would be, but the fact is that, as we know with any of these really major projects, there are risks and the point about this particular risk is that in relation to the Olympic Games, it is not one that we should be taking about its deliverability. We do not absolutely need Crossrail for the Olympic Games. As the Arup Report put it and I am sure the Mayor would agree with this, it would be a significant boost to the Olympic Games but it is not an absolute necessity for it.

Mr Flook

  173. It is now not much more than about a year since the fiasco of the bid for the World Athletics Championship. Do you each in turn believe the Government will back this bid when they look at it at the end of this month?
  (Mr Sumray) I do not know whether the Government will back it at the moment and indeed the Secretary of State—

  174. Mr Winterbottom?
  (Mr Sumray) Just to say, if the Government do back it, I think the point that others have made which we need to reiterate is that there has to be wholehearted and absolute support from all government departments to make sure that it works, it requires that, otherwise there is no point in bidding. All the stakeholders say it has to have full and unequivocal support. It cannot work with half-hearted support and we saw that in the sense of what happened at Picketts Lock. It has to have full support from the Government in order to make it work.

  175. Mr Sumray, you may not have had the chance yet to read the transcript of Tessa Jowell's words in the House of Commons yesterday, but did you get the sense that there was that full backing from what she was saying?
  (Mr Sumray) I was there yesterday so I heard the speech. What I think that she was doing, which is what she said this morning, was creating a balance sheet and that balance sheet was to say this is actually what is required in order to make a bid. We have to understand what the costs are. I think there has been a little bit too much concentration on the costs and potentially not enough concentration on some of the benefits that accrue in making a bid. I think the benefits as far as regeneration is concerned, the benefits for the local community, the legacy done properly, all of those things are huge benefits plus the factors which cannot be costed, the feel good factors and all of those things are significant benefits. It is also not just about costs and benefits, it is also about a range of other things which in a way cannot be costed. What I got from her yesterday was the need, an understandable need, from the Treasury and other government departments to try and provide what the worst-case scenario is. I hope at the end of the day that she and other ministers will support it. We cannot be sure that obviously will be the case.
  (Mr Winterbottom) I think we will bid.
  (Mr Ward) I think we should, but they must take the proper decision on all the facts and the investigations they are doing, what any government must do.

  176. Do you think the Treasury are doing their own analysis in the way that Arup have done it?
  (Mr Ward) They must do, they must do, and I think that most of what we see in the papers are different versions of different documents which are circulating in government departments, some giving an upside, some giving a downside, and that must be part of the process of taking a decision.
  (Mr Walder) I believe the Government will bid, I hope the Government does bid. One point I would make about it is that we are talking about it as a London bid and if it is a bid here, if it is a London bid, that is a UK bid and it has to be thought of as a UK bid.
  (Mr Broe) I think the Government should bid.

  177. The reason for asking all that is that losing the IAAF Games really meant no athletics stadium. What will not happen if we do not bid? If there is no bid, what will not happen in the way that you all want it to happen?
  (Mr Sumray) The opportunity for very significant developments, regeneration opportunities, particularly for the people of that part of East London, but actually opportunities for the country as a whole, and I agree wholeheartedly with the point being made that it is the country that will benefit as a whole, not just London and not just that part of London. The boroughs described yesterday, and I think absolutely appropriately, what the nature is of that population of that part of East London. It is a very young population with a high ethnic minority proportion there, very deprived, and there will be real opportunities missed to support that population, to get them involved, to get them engaged and really to get them engaged in sport and other things and to improve people's health. All of those sorts of issues are things which would be missed if the Games was not bid for, and the speeded-up regeneration of that part of London is very important. Legacy in sport is again something which would not happen in the same way. I have figures here about swimming pools and it was raised yesterday where Amsterdam has three 50-metre swimming pools, Barcelona six, Berlin 19, Paris 18—

  178. To save you reading the report, there are more in the basin of Paris than there are in the whole of the United Kingdom.
  (Mr Sumray) Precisely, and I think here we have opportunities which quite frankly would not occur if we did not have the bid.

  179. What will happen transport-wise or what would not happen?
  (Mr Walder) Transport is actually interesting in this regard. For the most part, we are not relying on new infrastructure to be able to accommodate the Games, so you are not able to point to a piece of infrastructure, for the most part, which would not be there. On the other hand, I think there is experience from similar situations that residents change their travel behaviour during times of major events for a large part because demand management measures have to be put in place because people see it as no choice, but it also exposes them to other travel patterns than the ones they have been accustomed to. Interestingly, some of the experience is that when people are actually exposed to different travel patterns, they sometimes retain those travel patterns. The use of public transportation rises, people who use public transportation move to walking, cycling, other modes of travel, and that actually is a legacy benefit that you do not often think of from games of this nature. It gives an opportunity to try things in terms of demand management regarding our streets and the like that perhaps the day-to-day experience in London does not provide. That is really an opportunity.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 23 January 2003