Select Committee on Defence Written Evidence


Annex A (continued)

METEOR

  Meteor is an all-weather, beyond visual range air-to-air missile to equip Eurofighter (now Typhoon), which is being procured from MBDA UK Ltd (formerly Matra BAe Dynamics) in collaboration with Germany, Italy and Spain (our Typhoon partner nations), France (for Rafale) and Sweden (for Gripen). It was selected in May 2000, following a competition between MBDA and Raytheon Systems Ltd. The combined design, development, production and support contract was placed on 23 December 2002 following approval and signature of the Meteor Memorandum of Understanding (MOU) by all partner nations. It is forecast that Meteor will enter service, on Typhoon in 2012.

Operational Requirement

  The requirement is for a medium range air-to-air missile for the Typhoon. Initial planning assumptions were based on the ability of the AIM-120B Advanced Medium Range Air-to-Air Missile (AMRAAM) to meet the longer-term threat, but changes in the operational environment led to the issue of a revised Staff Requirement in 1995. It underlined the need for the fighter to achieve a large "no escape zone" against manoeuvring targets during beyond visual range air-to-air combat, and to maximise the number of firing opportunities. The Staff Requirement also employed the principle of "performance objectives" as opposed to "essential criteria". This was designed to prompt bidders to propose innovative solutions and as wide a range of options as possible.

Trade-offs

  It should be possible to upgrade major missile sub-systems to incorporate more cost-effective technology and to match the evolving threat. The Staff Requirement sought to encourage the designers to share the risk by matching and trading the performance requirements to a realisable and affordable design solution.

Numbers

  ***

Strategic Defence Review

  The BVRAAM programme was considered during the Strategic Defence Review, when the difficulties of achieving the in-service date were assessed. It was concluded that BVRAAM remained a key capability.

Military Capability

  Meteor will be the primary air-to-air weapon for Typhoon. It will provide a key capability in achieving and maintaining air superiority wherever Typhoon is deployed. Meteor will allow Typhoon to engage multiple and manoeuvring targets simultaneously, at greater range than before, in all weathers, day or night, and with greater survivability.

Equipment to be Replaced and In-Service Date

  Meteor will not specifically replace any other programme. Instead, it represents a new generation of weapon designed to equip a new generation of fighter.

  A 90% confidence ISD of August 2012 was approved for Meteor at Main Gate; the approval noted a 50% confidence date of September 2011. Until Meteor comes into service, Typhoon will, for its Medium Range capability, be armed with the Advanced Medium-Range Air-to-Air Missile (AMRAAM), manufactured by Raytheon. An interim buy of AMRAAM missiles would have been required whichever BVRAAM solution was chosen.

Acquisition Approach

  Competition was maintained throughout the pre-Main Gate phase, both at prime and sub-contractor levels, to ensure best value for money. Bidders were required to submit firm prices for an initial five-year period from award of contract and fixed prices thereafter.

  A Request for Information was issued in 1994 to a wide range of national and foreign government agencies, potential prime contractors, and major equipment suppliers. Responses received by the MoD in late 1994 suggested that a project was technically feasible and capable of completion within an acceptable timescale. Four potential partner nations, Germany, Italy, Spain, and Sweden, agreed in principle in 1995 that the UK BVRAAM specification broadly met their baseline missile requirements for Typhoon and, in the case of Sweden, JAS 39 Gripen. These nations were invited to assess the bids jointly with the UK, with a view to agreeing on a common solution. In July 1999 France joined the programme, having identified that the BVRAAM specification broadly met their capability requirements for Rafale.

  An invitation to tender was issued in 1995, requesting bids for the full capability missile, as well as proposals for a staged capability (ie an interim capability missile with the potential for upgrade). Two companies, Raytheon Systems Ltd (formerly Hughes) and Matra BAe Dynamics (now MBDA), submitted bids. Raytheon submitted proposals for a Future Medium Range Air-to-Air Missile (FMRAAM), a full capability missile, and the Extended Range Air-to-Air Missile (ERAAM), with a proposed growth path to full capability. MBDA proposed only a full capability missile, Meteor.

  Assessment highlighted areas of major technical risk in each bid, and it was decided not to award an immediate Development and Production contract. Instead, contracts for a Project Definition and Risk Reduction phase were placed with the two bidders in August 1997. Revised bids to meet the requirement were received in May 1998, and these were followed by an additional, unsolicited offer of Raytheon's ERAAM+ under the umbrella of a joint UK/US collaboration. Best and Final Offers were received from both companies in September 1999 and, following Ministerial consideration, a decision to buy Meteor was announced on 16 May 2000.

  Contractual negotiations with MBDA, involving a number of complex technical and commercial issues, were fully concluded in early 2002. Importantly, lessons learned from the Advanced Short-Range Air-to-Air Missile (ASRAAM) programme were applied, particularly in ensuring that both ourselves and MBDA were in full agreement on the requirement and the means by which this would be demonstrated. Signature of the contract was however further delayed until German Bundestag approval was received in December 2002.

Alternative Acquisition Options

  No suitable "off-the-shelf" missile was assessed as being able to meet the BVRAAM requirement. Options considered in the early stages, but deemed not to have the required performance, were the Matra MICA, the Alenia Aspide, and the British Aerospace Dynamics Active Skyflash.

Collaboration

  Meteor is a collaborative project with Germany, Italy, Spain, France, and Sweden. The UK is leading the programme, with industry having defined work-share based on technical excellence, manageable risk, and best value for money, rather than any predetermined formula. The collaborative Meteor contract placed by the DPA is under UK contracting law. The contract incorporates production options for partner nations, which enables them to commit to production quantities at any stage of the development programme. The UK is presently the only nation to commit to production. An MOU, setting out the contractual, financial, and management arrangements for the programme, has been signed by all partner nations. The UK, France and Sweden signed the MOU in June 2001; Italy signed in September 2001; Spain signed in December 2001 and Germany in December 2002. The final signature of the MOU allowed the UK to place the contract with MBDA.

  Missile requirements and in-service dates (ISDs) for the other nations have yet to be advised. An International Joint Project Office (IJPO) has been established within the MoD Defence Procurement Agency under the UK's BVRAAM Integrated Project Team Leader. The salary costs of partner nations' representatives are being borne by their governments.

Export Potential

  Meteor has good prospects for sales, particularly as part of an integrated package on Typhoon. The opportunities for overseas sales could be widened through sales of Gripen and Rafale, by Sweden and France respectively.

Industrial Factors

  Industrial factors were taken into account in the assessment of bids. Meteor offered particular advantages to the UK in terms of the quality and sustainability of the jobs involved. MBDA stated that a total of 2,400 jobs would be created or sustained in Europe; 1,200 in the UK.

Smart Acquisition

  The Meteor programme embodies a number of Smart Acquisition principles. Whole life costs formed an integral part of the decision process. The IPT has also entered into a partnering agreement with the Prime Contractor, that formally details how the relationship between the company and the IPT will be managed. Emphasis is being placed on continued delivery of value for money, and gain-sharing potential will be kept under continuous review. Importantly, the contractor has agreed to a series of four key technological milestones, to demonstrate successful progress during the development phase. If the company fails to achieve any of these milestones, against clearly measurable acceptable criteria, termination of the contract can be initiated, with all money being returned to the partner nations.

Acquisition Phases

  Key acquisition phases are shown in the table below:

Phase
Date
Activity
Prime contractor selectionMay 2000 Contract negotiation. Drafting of Memorandum of Understanding.
Demonstration and Manufacture PhasesDecember 2002 Contract placed for Design, Development, Production and Support of Meteor.


Milestones and Costs

  Expenditure up to 31 March 2003 was £77 million (on a resource basis at outturn prices). The total approved (90%) acquisition resource costs at Main Gate in May 2000 is £1,437 million, including the purchase on interim AMRAAM missiles. The current forecast (50%) cost is £1,403 million. The years of peak expenditure are likely to be 2010-11 and 2011-12.

In-Service Support

  The aim of the Meteor Integrated Logistic Support strategy is to minimise the support costs whilst maintaining weapons availability. The weapon is being designed under an "all up round" principle (ie a complete munition that requires no assembly or maintenance immediately prior to loading) to reduce through life logistic support. MBDA will be responsible for the first 10 years of logistics support. Very little maintenance will be required on the Meteor system in service. Missiles and support equipment will be returned for repair to MBDA once any fault has been confirmed. Contracts after the initial ten-year period will be subject to negotiation.

  Discussions between the UK, MBDA, and our partner nations on support are now complete. All partner nations have indicated that they would like to pursue a collaborative logistic support contract for Meteor with the benefit of greatly reducing each partner nation's support costs. The draft 10-year logistic support contract has been worded to enable any partner nation to join in this combined support contract as they commit to production.

  Provision of initial operator and maintainer instructor training and the associated training package are the responsibility of MBDA. Future continuation training will be undertaken with in-service resources. A number of ground-handling training missiles, telemetered operational missiles and explosive ordnance disposal training missiles will be procured. Technical publications will be produced in full electronic format.

Front Line, Storage and Reserve Numbers

  Current plans for operational missiles require *** to be placed in storage and *** to be allocated to Main Operating Bases. This includes telemetered rounds.

Interoperability

  The BVRAAM programme was conceived exclusively for Typhoon, where the main carriage method is semi-recesssed under the fuselage—a key design driver. Meteor will be integrated on Gripen (for Sweden) and Rafale (for France) and will therefore be interoperable with these nations in addition to our Typhoon partners. Whilst the extant UK requirement provides only for integration on Typhoon, integration issues with respect to the Joint Strike Fighter variant selected as the UK's Future Carrier Borne Aircraft will also be assessed.

In-Service Life

  Meteor has a required 25-year design life.

Development Potential

  Through-life development of the missile will be considered as the project progresses.

ADVANCED SHORT RANGE AIR-TO-AIR MISSILE (ASRAAM)

  The Advanced Short Range Air-to-Air Missile (ASRAAM) is a highly agile, passively guided advanced-air weapon, manufactured by MBDA (formerly Matra BAe Dynamics). It is being deployed on the Tornado F3 to replace the Sidewinder AIM-9L missile and it will also be fitted to Eurofighter (now Typhoon). ASRAAM entered service at an interim standard in January 2002 and became available for operational deployment in summer 2002. Incremental improvements will lead to a full operational capability for ASRAAM, which we aim to achieve by the end of 2003.

Operational Requirement

  The requirement for a highly agile missile with good infra-red countermeasures resistance was driven by the need for short-range air superiority in visual combat. Such a missile was to provide Typhoon with a substantial advantage against the forecast threat at the turn of the century, and would be complementary to Skyflash and Meteor (see separate memorandum). The missile would, additionally, be an important factor in the overall capability of the Tornado F3.

  Initially, the UK sought to meet the national requirement for a short-range air-to-air missile through participation in a collaborative development for a family of weapons. In accordance with a Memorandum of Understanding between the UK, the US, and Germany, signed in 1980, a tri-national Staff Requirement was agreed in October 1984. Subsequent budgetary pressures, technical and management problems, and changes to US requirements caused our partners to withdraw from the project. The Staff Requirement was re-endorsed as a UK national programme in 1990 without any significant changes since the original approval.

Trade-offs

  We have accepted that, for a short period of time, the missile will be beneath the exacting performance standard we specified. We have agreed to this only after having established a clear and robust route map towards achieving the missile's full operational capability. There is no additional cost to the Department for the work that MBDA will have to do to achieve this. Notwithstanding this, the missile that has entered service is the best in its class.

Numbers

  ***

Strategic Defence Review

  The Strategic Defence Review (SDR) and SDR New Chapter did not affect the requirement or existing orders.

Military Capability

  ASRAAM will provide a significant contribution to achieving and maintaining air superiority, as well as providing critical self-defence capability for a variety of current and future UK air assets. It will be employed in the full spectrum of air operations from air policing to peace support through to high intensity conflict.

Equipment Replaced and In-Service Date

  ASRAAM will replace Sidewinder AIM-9L on Tornado F3 in a delivery programme that started in January 2002 and is the planned short-range air-to-air weapon for Typhoon. In addition, following the announcement, in September 2002 of the Joint Strike Fighter (JSF) as the Future Joint Combat Aircraft platform ASRAAM will provide the same capability on JSF. ASRAAM is no longer planned for Harrier GR9 or Sea Harrier FA2 following the new investment strategy for Joint Force Harrier announced in February 2002.

  The ISD set at ASRAAM's Main Gate equivalent was December 1998; following re-approval in August 1999 this was reset to April 2001. ASRAAM entered service in January 2002, 37 months late against the Main Gate approval. The achievement of ISD marked the successful resolution of a contractual dispute between MoD and MBDA. Prior to this, the missile had been offered for acceptance by MBDA but we were unable to accept it as a number of specified performance standards had not been met. The performance shortfalls were in the areas of lethality, target acquisition, tracking, and resistance to countermeasures. The Department worked closely with MBDA to agree a clear and robust route map to full operational capability which enabled the missile to enter service in January 2002.

  The incremental route to full operational capability comprises a number of stages. The missiles accepted in January 2002 were at an interim standard that is higher than that offered by MBDA for the ISD of April 2001. Even though improvements over and above this standard are required, the missile's level of performance at ISD was far superior to that of AIM-9L and it is the best short-range air-to-air missile available. The first incremental upgrade standard (FOC1) involves both hardware and software improvements, and deliveries at this standard of missile began in late 2002. The ASRAAM development programme will continue with further software upgrades that will lead to full operational capability, (FOC2) by late 2003. Any improvements identified as being required beyond this will be incorporated into an FOC3 standard for which additional funding will have to be found. The delay has had no impact on Typhoon's operational capability.

Acquisition Approach

  Under the provisions of the 1980 MoU, the US was to develop an advanced medium range air-to-air missile, and the UK and Germany, along with Norway and Canada, who had subsequently joined the programme, were to develop the advanced short-range system. The European programme was managed by a joint project office, with Bodenseewerk Geratetechnik GmbH and British Aerospace Dynamics Ltd as the principal contractors. Difficulties with the programme, including problems with missile configuration and the establishment of effective collaborative arrangements, led to the withdrawal of Germany from the programme in 1989 and the US, Norway, and Canada in 1990.

  Once ASRAAM had been re-endorsed as a UK national programme, an invitation to tender was issued in 1991. It called for a package deal, covering development, production, and associated logistic support of the missile and its associated training variants. We also stipulated the minimum use of Government Furnished Facilities and Equipment, and the earliest possible ISD.

  A number of candidate weapons were considered. British Aerospace Defence Ltd; Raytheon; a consortium of GEC, Marconi, and Matra; Bodenseewerk Geratetechnik GmbH, (BGT); and Loral Aeronutronic all expressed an interest in the competition. In the event, Raytheon and Loral did not respond to the ITT. The BAe bid of ASRAAM, the GEC Marconi/Matra bid of MICA ASRAAM, and the BGT AIM9L IRIS were considered as options in early 1992. Other weapons, including a further BGT bid, the AIM 9LI (an improvement over the standard AIM9L) and a number of US options either in service or in development were also considered, but were not assessed as capable of meeting the UK requirement.

  The BAe bid met the Staff Requirement and offered a number of advantages over the BGT and GEC Marconi/Matra bids. BAe Defence Ltd (now MBDA) was awarded a fixed price contract in 1992.

Export Potential

  ASRAAM won its first export order in December 1998 when it was selected for the Royal Australian Air Force, with whom we are working closely. Australia has had similar concerns to us with respect to performance, however they are now reasonably confident that their requirements will be met and enable Service Release of the Full Operational Capability ASRAAM in December 2003. There is also interest from a number of other nations, including Canada, Oman, Singapore, Spain, Finland and Saudi Arabia. The main competition to ASRAAM is from missiles being built in the USA, Germany, Russia, Israel, France, and South Africa.

Industrial Factors

   The decision on the main development and production contracts took account of the employment implications for the UK. MBDA has estimated that more than 80% of the work in total would be in the UK, securing some 7,000 jobs. The GEC Marconi/Matra bid offered only 50% of work in the UK, although they estimated that this would rise to 70% if potential sales were achieved.

Smart Acquisition

  MBDA proposed in September 1998 a number of Smart Acquisition "gain sharing" initiatives. These included the introduction of a more powerful processor into the missile, enhancing the potential for future performance upgrades and eliminating an obsolescence problem at no cost to the MoD, and better alignment of missile production deliveries with candidate aircraft platforms. A contract amendment was agreed in September 1999. The subsequent contractual dispute between MoD and MBDA was eventually resolved in 2002 and the outcome, an incremental route map to full operational capability, follows Smart Acquisition principles. Lessons from our experience of the ASRAAM programme are informing our acquisition from MBDA of the Meteor beyond-visual-range air-to-air missile. (See separate Meteor memorandum).

Acquisition Phases

  Details of the current acquisition phase are shown in the table below:

Phase
Date
Activity
Development & ProductionMarch 1992 Full development and production of ASRAAM starts


Milestones and Costs

  Expenditure to 31 March 2003 (on a resource basis at outturn prices) is expected to total £777 million, comprising £72 million on Feasibility and £705 million on Development and Production. Total approved costs are £866 million. The expected final cost is £857 million (ie £72 million on Feasibility and £785 million on Development and Production). The delay in achieving ISD resulted in the Department incurring approximately £7 million additional costs. These include extra intramural expenditure and costs arising from the need to maintain Sidewinder missiles in service.

  Delays to the programme have triggered liquidated damages. The majority of these have already been collected totalling some £19 million. The amended contract makes provision for further liquidated damages up to a maximum of 6% (approximately £23 million) of the value of deliverable items. The MoD will continue to claim any liquidated damages that fall due. We have, however, accepted the company's claim that some of the programme delay has been caused by the need to dedicate significant resources to the MoD/company contractual dispute. Accordingly as part of the overall agreement to bring ASRAAM into service, a period of grace has been allowed in the schedule determining liquidated damages. But any further delays by MBDA could negate the benefit the company derives from this period of grace.

In-Service Support

  ASRAAM is an industry-supported missile, with maintenance being undertaken by the prime contractor. A five year Support contract, based on delivering an agreed level of availability, was awarded to MBDA on 1 March 2003.

  Most of the support equipment and handling procedures for ASRAAM will be the same as for the current AIM-9L weapon. However, as the design has been completed under the "all up round" principle (ie a complete missile, ready for use, stored in its own container), there will be a substantial reduction in routine servicing requirements and all major servicing will be undertaken by industry. Having identified potential storage difficulties (the result of ASRAAM stocks building up without equivalent reductions in AIM-9L stocks), we undertook a Weapon Loading and Storage Study. The recommendations are now being implemented and we are confident that no significant problems will arise. Since the operational and training missiles both have classified software, unlike the current air-to-air weapons, of which only the operational weapons are classified, modified security procedures have been put in place.

Front Line, Storage and Reserves Numbers

  The Air Force will operate a dual inventory policy where the majority of the stock will be held in store and the remainder held forward for first line use.

Interoperability

  ASRAAM has demonstrated its compatibility with earlier AIM-9L launch equipment and interfaces. It is capable of being carried and fired, with minimum modification, by all UK and other allied air forces' aircraft that can carry and employ AIM-9L. The system is compatible with the rail launchers on Typhoon. It is also designed to be employed using multiple sensors, such as the infra-red search and track systems and helmet-mounted sights planned for Typhoon, as well as radar.

Disposal of Equipment Replaced

  Surplus Sidewinders may have potential for re-sale. Missiles that cannot be sold will have no operational use and will be scrapped.

In-Service Life

  The current life required from ASRAAM is 10 years. However this will need to be extended to at least 25 years in order to match the Service life of Typhoon and JSF. A strategy to do this will be developed over the course of this year.

Development Potential

  We continue to work, in partnership with Australia, to establish a programme of through-life development. The programme is primarily to ensure a useful service life of 25 years and could involve the acquisition of emerging technology on an incremental basis.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 23 July 2003