Select Committee on Defence Written Evidence


Supplementary memorandum from the Ministry of Defence (7 July 2003)

Nimrod/Astute

  The Committee's first two questions dealt with the basis for the calculation of MoD's additional contribution to the two programmes, and on the cost of buying-in help from General Dynamics on CAD for Astute. It should be noted that the exact details of the agreements required to establish formally the new financial structures and the revised in-service dates for both programmes have yet to be agreed. The Department is not, therefore, in a position to give further cost details to the Committee at this stage, beyond those set out in the memoranda. We would, of course, be happy to provide these in due course.

  Turning to Nimrod MRA4, it was evident by summer 2002 that there would be further delay and cost increase on the programme. Delays in the development programme had increased significantly the overlap with production, and introduced further risks. The Agreement introduced a break in production until development work had sufficiently de-risked the programme. At the same time, and as a result of operational experience, the MoD identified a need for improved surveillance and reconnaissance and land attack capability. Accordingly, we are investigating the potential for converting Nimrod into an adaptable aircraft, and it was against this background that we arrived at the Agreement. Our intention was that the company should bear responsibility for the additional costs arising from their conduct of the programme (while recognising some MoD responsibility for the cost overrrun) together with the cost of an Assessment Phase study to examine the potential of Nimrod MRA4 to meet the adaptable aircraft requirement. In line with this, BAE Systems agreed to make the larger provision—£500 million in 2002—in addition to a provision of £300 million in 2000, with MoD increasing funding by around £270 million. The Agreement has also introduced an incentive on the company to minimise costs for the development phase and has set a cost aim for the production of aircraft 4-18.

  In respect of Astute, the contract included the full use of computer aided design (CAD) for the first time in UK submarine building. It was assumed by both parties that there would be significant efficiencies, and lower costs were agreed for design, development, First of Class and the following two submarines (AO2 and AO3). In the event, the introduction of CAD was considerably more troublesome than had been expected by both parties; in particular, the confined space in a submarine presented difficulties not experienced with surface vessels. The Department now knows, but could not have known at the time, that the US Navy was having similar difficulties with the design of their Sea Wolf Class submarines.

  The Agreement with BAE Systems therefore focuses on design and production of the First of Class, and takes account of the experience of US submarine builder Electric Boat in introducing and using CAD systems. It incentivises the company to drive down costs, and links profit on the design work to the production timetable and costs for AO2 and AO3. It has also reduced the overlap between development and production. The sharing of the cost overrun—the Government agreed to increase its funding by around £430 million, against an increased contribution by the company of around £250 million—reflected the relative responsibilities of the two parties. The costs associated with the involvement of General Dynamic's Electric Boat Division, *** are subsumed within the revised pricing arrangements.

US ITAR

  The Committee's third question dealt with the procedure and likely timescales for Parliament to consider the US ITAR Agreement.

  The ITAR Waiver Agreement will be laid before Parliament in a similar manner to a treaty. This will occur post-signature, but at least 21 sitting days before any actions, such as mutual notification of completion of procedures or ratification, can be effected. The Committee will wish to note that this process will not include the Memoranda of Understanding associated with the Agreement, copies of which have been passed to the Committee on an informal basis.

  The laying before Parliament will be effected by means of a Command Paper, and accompanied by an Explanatory Memorandum drawing attention to the main features of the Agreement. We would expect this to happen either towards the end of 2003, or early in 2004.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 23 July 2003