Select Committee on Environmental Audit Minutes of Evidence


Supplementary memorandum from the CBI

  At the request of the House of Commons Environment Audit Committee, this memorandum supplements the CBI's original submission to the inquiry Winning the War on Waste by providing an overview of the potential consequences that could arise from power station ash being classified as a waste. The information contained within this report has been compiled with the assistance of members of the CBI, including the Electricity Industry.

1.  PULVERISED FUEL ASH

  Pulverised Fuel Ash (PFA) is produced from the combustion of powdered coal at high temperatures in order to general electricity. PFA has physical and chemical properties which make it suitable and desirable for a wide range of applications without requiring further processing prior to use.

2.  INDUSTRIAL USE OF PFA

  The electricity generating industry has sold PFA for around 50 years in cement products, concrete, building blocks and as a fill material to make road foundations and flyovers. The graph below provides a more detailed breakdown of industrial use for 2001. Since 1994, the industry has worked under a Department for the Environment Guidance Note (11/94), which permits PFA destined for use to be sold as a by-product free of waste regulation. At present more than 50% of PFA is sold for use. The remainder is landfilled, but a significant proportion of this is used to restore worked out gravel pits, a purpose for which it is ideally suited.

3.  RECENT DEVELOPMENTS

  The Environment Agency (EA) has not reported any environmental problems with the use of PFA to industry, but at a meeting around 18 months ago, the EA suggested that PFA should be classed as waste, based on their interpretation of case law. The industry has had several meetings with the EA since and has produced a report indicating the commercial damage that would be caused by classification of PFA as waste. Key findings of this report are contained within the additional memorandum.

4.  IMPLICATIONS OF CLASSIFYING PFA AS WASTE

  While it is impossible to quantify precisely the effects of designating PFA as waste, it is anticipated that the civil engineering fill and grout market would be the worst affected initially. The effects on other sectors would depend on the market situation at the time and the ability to absorb the additional costs associated with the handling of waste. Generally the value of the product is likely to decline as consumers pay less for what they deem an inferior product, due to its new classification. The effects of complete loss of the current market for PFA have been estimated and the results summarised in Table 1 below. Overall in the UK, it is possible that the future loss of market could be in the order of 3.5 million tonnes per annum.

Table 1—Summary of Additional Impacts for Replacement of 3.5 million tonnes p.a.
IssueEffects of Replacement of Ash
Quarrying & Dredging of Primary Aggregates Increase in quarrying (allowing for the higher density of replacements for PFA and the additional material required for cement production) the total additional quarrying could be around 5 million tonnes per annum.
LandfillAn increase in landfill usage equivalent to 3.5 million tonnes of PFA per annum. Reducing available landfill capacity by around 2.2 million cubic metres per year.
Carbon Dioxide
Emissions
This is the most difficult to quantify however it is possible to point to substantial increases in emissions due to:

  —  Greater emissions from the manufacture or processing of raw materials where PFA could have been used directly. These emissions result from grinding materials or production processes such as cement kilns. Approximately 12.5% of PFA is used as a cement replacement, the loss of this market alone will cause an increase of 70,000 tonnes per annum of CO2. There will also be greater emissions from block manufacture because the raw materials will require grinding and more cement will be used due to the loss of the cementitious effects of PFA.

  —  Additional: road transportation to disposal sites. A recent assessment of the impacts of transporting PFA to a site within 10 miles of the power station indicated a minimum of 1. 64 Tonnes of CO2 is emitted per 1000 tonnes PFA transported.

CostThis is very difficult to estimate but as a first estimate the total cost will be of the order of £50 million per annum.

  —  £5 million additional landfill tax assuming around one third of disposal is exempt from tax.

  —  Establishment of additional landfill capacity p.a., increased transport to more distant sites could add £5 million to costs.

  —  £16 million in replacement cement in both cement manufacture and concrete.

  —  Use of more expensive materials to replace PFA in a variety of applications could be a further £5 to £10 million.

  —  Importation and distribution of 700,000 tonnes of pumice say £10 million.

Other Impacts—  Importation of pumice adds to balance of payments deficit.

—  Increased traffic emissions and road vehicle noise and nuisance.


  Further implications are outlined overleaf.

5.1  Product Stigmatisation

  The most significant effect of categorising PFA as waste is the stigma associated with an accepted construction product being designated as waste. This implies a connotation of being "discarded" and second rate. The public perception may well be that the designation implies that the material is unfit, substandard and potentially dangerous. It has proved very difficult to inform public opinion and would be extremely challenging to convey the technical issues involved. The public would rely on the simple designation implied by the word waste.

  The designation as waste makes it necessary to obtain exemptions for every engineering fill project. Not only does this have a cost and cause delay but also it accentuates the stigma issue highlighted above. If there is to be a blanket exemption, then the designation as waste achieves no additional control but causes a reduction in use due to the stigma.

5.2  Administrative Implications

  If PFA destined for use is designated as waste then the industry's customers will be required to comply with the full range of waste management regulations. All PFA processing plants will have to apply for waste management licences even though existing legislation generally requires them to have permits as minerals processing plants, or for other reasons. This would increase costs and double regulate the same plants. These processes are frequently low margin operations. The increased costs of licences and additional staff with WAMITAB qualifications etc are sufficient to add £0.50 to £1 per tonne processed or more. This additional cost will make such ventures less attractive and may render some uneconomic.

5.3  Storage Implications

  If PFA is designated as waste then storage sites may require licensing under the Landfill/Pollution Prevention Control Regulations if the period of storage prior to recovery or treatment is greater than three years, "as a general rule". It is not clear at this stage how this would be applied to PFA storage. Since the storage of PFA as a material for sale is currently regulated under IPC authorisations there would be no benefit in improved control resulting from a change in designation.

6.  INCONSISTENCY WITH EU CATEGORISATION OF PFA

  The industry has taken legal advice that confirms that there is no requirement for the EA to classify PFA as waste provided it is to be used beneficially and the use of the product is certain. This has been reinforced by the Palin Granit (April 2002) judgement from the European Court. This is the latest interpretation of the by-product argument. The judgement indicates that a by-product is not waste if its beneficial use is certain without further treatment of the material. This applies to PFA that has many beneficial uses. Its use is certain if it has been purchased under a sales contract.

  PFA used as a by-product is not treated as a waste in EU countries with coal-fired generation eg Holland, Germany, Spain, and Portugal. The European Commission has not objected to the PFA sales arrangements in these countries. The UK industry cannot understand why PFA sales are not encouraged by the EA in accordance with several Government policies. The current arrangements cause no environmental problems, reuses materials, prevents the use of mined aggregates and reduces the need for scarce landfill resource.

7.  THE WAY FORWARD

  The potential classification of PFA as waste is just one example of the difficulties business faces over this issue. Other examples extend to a wider range of sectors including manufacturing (eg steel), chemical, automotive, telecommunications and indeed other examples which the CBI referred to both in our written and oral evidence. The legal uncertainties, the inappropriate interpretations and applications of the definition of waste currently inhibit business ability to further waste reduction, increased re-use, recycling etc need addressing.

  It is becoming increasingly important for government to take a more holistic approach to waste management. The CBI continues to ask government to provide business with clarity on the definition of what is and what is not a waste. When considering the classification of materials as "waste", a full evaluation of the costs/benefits should be completed. Government must establish a proper dialogue with business to resolve this matter.

February 2003


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 22 April 2003