Select Committee on European Scrutiny Thirtieth Report


5 PRE-ACCESSION ASSISTANCE IN 2001

(24651)
10655/03
COM(03) 329
ADD 1 
Commission general report on pre-accession assistance (PHARE
— ISPA — SAPARD) in 2001.


Legal base
Document originated4 June 2003
Deposited in Parliament 26 June 2003
DepartmentInternational Development
Basis of consideration EM of 30 June 2003
Previous Committee Report None
To be discussed in Council No date set
Committee's assessmentPolitically important.
Committee's decisionNot cleared; further information requested

Background

  5.1  This is the second annual report by the Commission on the three pre-accession aid instruments, PHARE,[14] ISPA[15] and SAPARD,[16] and their coordination.[17] It sets out the allocation of each instrument on a country-by-country basis and explains the development of the two new instruments introduced in 2000 (ISPA and SAPARD). All three programmes operate under guidelines agreed in 1999 and first implemented in 2000. To minimise the overlap between the three instruments, the areas of responsibility were agreed as follows:

  • PHARE'S main purpose should be to assist the candidate countries to adopt the acquis communautaire and to prepare them for using Structural Funds.
  • ISPA should be to assist in the implementation of EC environment policy and to build the Trans-European Transport Network; and
  • SAPARD's purpose should be to assist in the implementation of the acquis in relation to the Common Agricultural Policy and all related areas. In addition to primary agricultural production, projects to improve product processing, marketing and quality are eligible for support, as are more general rural development measures.

The Commission report

  5.2  SAPARD was established later than the other two programmes and is implemented using the Extended Decentralised Implementation System (EDIS). PHARE and ISPA are implemented using the Decentralised Implementation System in which the Commission's ex ante approval is still required for project selection, tendering and contracting by candidate countries. However, the Commission envisages all of the Accession States, at least, moving to the final stage of EDIS in the course of 2003. Each must first set up the relevant market and control systems.

  5.3  The 2001 allocation for PHARE was €1,634 million. Approximately 40% of this was allocated for institution-building, principally through twinning. The remainder was in the form of investments to assist in the adoption of the acquis. Apart from the individual allocations to the candidate countries, €168 million was allocated to the special nuclear decommissioning programme, €163 million to cross-border cooperation and €212 million to regional and horizontal programmes.

  5.4  The 2001 allocation for ISPA amounted to €1,109 million. Second tranches for projects decided in 2000 were supported, together with 94 new projects. €2.7 million was allocated to technical assistance for EDIS. With co-financing from the international financial institutions (IFIs)and beneficiary states accounting for an average of 36% per project, the total cost of the 94 new projects approved in 2001 will be € 2.3 billion. 51.92% of the ISPA budget in 2001 went to environment projects — more than half of that to sewage treatment projects. 57.5% of the transport budget was spent on road projects and approximately 40% on rail projects.

  5.5  ISPA experienced delays in tendering and contracting in its first year of operation (2000). This was due to difficulties within the candidate countries' administrations in meeting the high standards required by Community competition and public procurement rules, and also in ensuring compatibility with Community policies. In 2001, the Commission began training seminars and other measures to assist the candidate countries to increase their capacity to comply with Community policies. A total of €59.9 million was allocated between 2000 and 2001 to strengthening the project pipeline.

  5.6  All of the applicants made progress in the development of their SAPARD agencies and conferral of management to national authorities was made by the Commission to five of the ten countries. Approximately €30.5 million was transferred to the countries by the end of 2001.

  5.7  Most of the coordination between the three instruments, and between them and the IFIs, is carried out by the Enlargement Directorate General, working with the PHARE Management Committee. Most co-operation with IFIs is in connection with the ISPA programme. A co-operation agreement was signed between ISPA and the European Investment Bank (EIB) on 19 January 2000, with positive results. Good relations have also been established with the European Bank for Reconstruction and Development (EBRD), Nordic Investment Bank (NIB) and the Nordic Environment Finance Corporation (NEFCO). Within candidate countries, the EC Delegations take responsibility for co-ordination between government ministries.

  5.8  In September 2000, the centralised PHARE Monitoring and Assessment System was replaced by a Decentralised Monitoring System and an Interim Evaluation Scheme. Candidate countries assumed responsibility for monitoring progress, while the Commission kept responsibility for assessing progress through regular sectoral Interim Evaluations carried out by independent evaluators. To facilitate coordination of project monitoring, Joint Monitoring Committees and Sectoral Monitoring Sub-Committees were set up in each candidate country. After July 2001, the interim evaluations were carried out by a new contractor. Over the course of the year, 42 Monitoring and Assessment reports were issued, based on the old monitoring and assessment scheme, and 25 sectoral Interim Evaluations reports were produced, based on sectoral monitoring reports. The new guidelines were being followed fairly well, with the majority of projects in line with the Accession Partnerships, Regular Reports and Action Plans. However, the ECA found that

    "an appreciable number are poorly designed or prepared, with vague aims, imprecise indicators, poor take-up of lessons learnt, and no feasibility studies. The evaluators' view is that PHARE's achievements owe more to the ability of those implementing the programme 'to get something done' than to good project design. The evaluators also note that while projects' administrative capacity has improved, financial and time management remain weak, and specialists are difficult to recruit and retain".

  5.9  The Commission says that the Interim Evaluation system was adapted further in 2002 to help to ensure the sound financial management of PHARE.

  5.10  A Commission staff working paper is annexed which reports on the ten candidate countries individually.

The Government's view

  5.11  The Secretary of State for International Development (Baroness Amos) says that, despite monitoring reports now coming on stream, it is still too early to assess the impact of spending and the relative efficiency of the co-ordination between the instruments. She then comments:

    "One of the benefits of the decentralisation of the pre-accession instruments is the development of the candidate countries' administrative structure that this entails. This will act as important preparation for the implementation of the Structural Funds. All of the candidate countries acceding next year are expected to receive EDIS accreditation before the date of accession. Both Bulgaria and Romania have emphasised administrative capacity-building and preparation for Structural Funds in their 2003 PHARE programmes and in the plan for multi-annual programming for Romania. Bulgaria is expected to move to multi-annual programming in 2004. Past experience of the candidate countries shows that this early preparation is sensible.

    "DFID is happy with the direction that the PHARE programme is taking in moving to multi-annual programming, which allows for a more strategic approach, and with the priorities set.

    "ISPA has not been very efficient in contracting and disbursing funds but the work that the Commission has done in assisting the candidate countries in developing their capacity appears to be making progress. SAPARD's performance, on the whole, has been very disappointing. The decision to implement it by EDIS from the outset may have been too ambitious, given the administrative deficiencies of the candidate countries.

    "The structures it has set up and the experience of implementing the programme will however prove helpful in the administration of the European Agricultural Guidance and Guarantee fund, with which it will merge as stated in Article 33 of the Accession Treaty."

Conclusion

  5.12  This report should be read in conjunction with the two Special Reports from the European Court of Auditors on which we are also reporting.[18] They relate mainly to aspects of implementing PHARE and ISPA. It is disappointing to learn from the Minister that the more recently established programme, SAPARD, has not been very efficient in contracting and disbursing funds. Once again, it appears that the administrative deficiencies of the candidate countries were under-estimated. Just as disappointing is to read that as recently as 2001 PHARE projects were evaluated as poorly designed and prepared.

  5.13  In view of her indication that the Government contributes 19% to these assistance programmes, we ask the Minister to tell us when she considers that it will be possible to make a sound assessment of their value.

  5.14  Meanwhile, we do not clear this document.



14   The Phare programme supports economic restructuring and democratic reform in the states of Central and Eastern Europe, the Baltic States and in Albania, FYROM, and Bosnia and Herzegovina.  Back

15   Instrument for Structural Policies for Pre-Accession. Back

16   Special Accession Programme for Agriculture and Rural Development. Back

17   (24225) 5585/03;see HC 63-xv (2002-03), paragraph 15 (19 March 2003). Back

18   (24623) - and (24660) -; see paragraphs 4 and 6 of this Report. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 24 July 2003