Select Committee on European Scrutiny Thirty-Third Report


29 Environmental projects in the candidate countries

(24623)

Special Report No. 5/2003

European Court of Auditors' Special Report No.5/2003 (pursuant to Article 248(4), second subparagraph, EC) concerning PHARE and ISPA Funding of Environmental Projects in the Candidate Countries together with the Commission's replies.

Legal base
DepartmentInternational Development
Basis of considerationMinister's letter of 20 September 2003
Previous Committee ReportHC 63-xxx (2002-03), paragraph 4 (16 July 2003)
To be discussed in CouncilNo date set
Committee's assessmentPolitically important
Committee's decisionCleared, but further information requested

Background

29.1 The objective of the audit which is the subject of this Special Report from the European Court of Auditors (ECA) was to assess the effectiveness of assistance given under the PHARE[60] and ISPA[61] programmes to the environment sector in the ten candidate countries of Central and Eastern Europe[62] between 1995 and 2000.

29.2 When we considered the document on 16 July 2003, we asked the Minister to provide a short summary of the Commission's replies to the European Court of Auditors and to comment on them. We also asked her to comment on whether any of the lessons to which the ECA drew attention had already been learnt by the Commission, whether the Court's recommendations were being acted upon and whether the lessons learnt had wider relevance. We asked if the Minister was content that steps had been taken to improve any structural deficiencies within the Commission or to review any constraints within which it operated.

The Minister's letter

29.3 The then Secretary of State (Baroness Amos) replied as follows:

    "The Court's recommendations fell into three broad categories: the need for more institution building, the need to have more effective targeting of grant financing and the need to improve the absorption capacity of the candidate countries.

    "The Commission pointed out that the report concerns only the first year of ISPA programming and PHARE under its new guidelines introduced in 2000. As such many of the concerns raised by the report have already been addressed or are being addressed and the lessons to which the report draws attention are being learned. In addition wider structural problems within the Commission are being addressed, in line with the Commission's general move towards reform of their external assistance programmes. Examples of these reforms are deconcentration to local delegations,[63] moves towards multi-annual programming and more linkages to recipient-government owned strategies.

    "The Commission has already begun to address the need for more institution building. They have introduced the Transition Facility, to begin in 2004, to provide further assistance for institution building in the post-accession period. As institution building in the candidate countries has been a priority for DFID, we welcome the introduction of this facility and will continue to work to ensure that the funds allocated are used in the most effective way possible.

    "The report recommendations raise the question of effective targeting [of] grants in ISPA. The Commission felt that there was little room for reducing grant levels in ISPA. This was due to a number of factors, including the income levels of the candidate countries (far below that of the current EU15) and access to co-financing with International Financial Institutions, such as the European Investment Bank (EIB). DFID agree with the Commission that care would need to be taken in reducing the ISPA grant levels particularly if the financial burden that this would cause would fall disproportionately on those with the lowest incomes.

    "The report recommends that the need to strengthen the absorption capacity of the candidate countries has to be addressed in a more significant way. The Commission agrees that absorption capacity is an issue and has made it a priority in the lead up to accession. They have provided technical assistance through the ISPA programme to strengthen project preparation and tendering procedures. The PHARE programme has also invested considerable funds in improving absorption capacity, particularly in the preparation for EDIS (Extended Decentralised Implementation System) whereby the PHARE programme will be fully decentralised to the country level. Absorption capacity has been a priority for DFID and of great concern to us in the entire pre-accession period. We approve of the move to EDIS as a preparation for the Structural Funds, as well as a vehicle to aid in the absorption of PHARE funds. Furthermore, our experience is that the measures taken by the Commission to strengthen administrative capacity in ISPA have had an appreciable impact.

    "It is the case that many of the lessons learnt from the pre-accession assistance programmes have wider relevance, particularly to the CARDS[64] and TACIS[65] programmes. Many of the lessons regarding institution building and absorption capacity are already being fed through to these programmes and DFID continues to work with the Commission in identifying further lessons to be learnt. We have, for example, recently requested that the Commission holds a seminar on evaluation of the PHARE programme, to identify lessons from the PHARE programme that would be of use to other assistance programmes and in the development of the New Neighbourhood Initiative, which will encompass aid in the Wider Europe area."

Conclusion

29.4 As indicated above, the UK recently asked the Commission to hold a seminar on evaluation of the PHARE programme. We ask the present Secretary of State to let us know when this seminar is to take place, as we may wish to ask him to give evidence to us after that event on the Commission's arrangements for monitoring and evaluation, as well as its performance in drawing up its programmes.

29.5 We now clear this document.


60   Named, initially, the Poland and Hungary Assistance for Reconstruction programme, PHARE was later extended to all the countries of Central and Eastern Europe. Back

61   Instrument for Structural Policies for Pre-Accession. Back

62   Bulgaria, Czech Republic, Estonia, Hungary, Latvia, Lithuania, Poland, Romania, Slovakia and Slovenia. Of these, eight are now referred to as the Accession States. Back

63   Devolution of the planning and management of programmes to the EC's staff in the country concerned. Back

64   CARDS is the EU programme of assistance for Albania, Bosnia and Herzegovina, Croatia, the Federal Republic of Yugoslavia and the former Yugoslav Republic of Macedonia. Back

65   TACIS is the EC's programme of technical assistance to the Commonwealth of Independent States and Mongolia. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 30 October 2003