Select Committee on Foreign Affairs Written Evidence


Further memorandum submitted by the Foreign and Commonwealth Office

FCO SERVICE DELIVERY AGREEMENT

Letter to the Parliamentary Relations and Devolution Department, Foreign and Commonwealth Office, from the Clerk of the Committee, 3 March 2003

  In its Report on the FCO Annual Report 2002[5], the Foreign Affairs Committee asked the Government to set out what progress the FCO has made towards identifying areas in which its 2.5% efficiency savings per annum target for 2004-06 can be made, and how the target will be met in full if the areas identified do not produce the required efficiency savings.

  In its response[6], the Government gave some examples from "a wide range of ideas" but did not provide a full list of the areas of expenditure in which the savings are expected to be achieved. Neither did it answer the Committee's question about how the target will be met in full. This information does not appear to be available elsewhere: the FCO Autumn Performance Report 2002, published at the end of last week, deals with Public Service Agreements (PSAs) but not with Service Delivery Agreements (SDAs); the FCO website appears to have no scorecards for this SDA.

  I would be grateful to receive, not later than 24 March, a fuller statement on exactly where and how the FCO intends to achieve its 2.5% efficiency savings per annum target over the period 2004 to 2006, and what plans it has to meet the target in the event that the areas identified for those savings do not produce them.

Clerk of the Committee

March 2003


Letter to the Clerk of the Committee from the Parliamentary Relations and Devolution Department, Foreign and Commonwealth Office, 2 April 2003

  Thank you for your letter of 3 March asking for a fuller explanation of how the FCO intends to achieve its annual efficiency target of 2.5% over the period 2004-06, and what plans we will put in place to meet the target if efficiencies are not realised.

  The 2002 Spending Review provided funding for new FCO priorities but did not include an uplift to compensate for annual increases in UK inflation. This is mirrored in our internal resource allocation: Directorates are given funds to meet new requirements and challenges but are expected to manage without compensation for inflation. This means that, in effect, the 2.5% efficiency savings are budgeted in—Directorates will need to achieve annual efficiency savings of about 2.5% if their budgets are not to be eroded in real terms by rising prices.

  It is therefore for each Directorate to decide how best to achieve 2.5% efficiency savings each year. Directorates have produced efficiency plans which show how they plan to meet the target. Some of the measures proposed include:

    —  Streamlining overseas entry clearance operations thereby allowing more entry clearance applications to be processed within existing resources;

    —  Leasing cheaper properties and using them more efficiently;

    —  Refocusing of publications and TV products on strategic messages;

    —  Telephony installation costs to be contained within budget—no uplift for inflation;

    —  Reduction in the use of agency staff through more efficient deployment of existing staff;

    —  Surrender of staff slots for redeployment elsewhere following the introduction of new IT equipment.

  Because the efficiency savings are already budgeted in, the savings are, for the most part, sure to be fulfilled—the only question is whether they are met through efficiencies or through cutting activity. The aim, of course, should be the former; and efficiency plans will be monitored to encourage Directorates to achieve savings while maintaining or increasing outputs. The outputs themselves will be monitored through our performance management system, the results of which are reported routinely to the Treasury and to Parliament in the Departmental and Autumn Reports.

  The centrally held UK pay budget reflects activity levels in the Directorates, which are, as explained above, already subject to efficiency targets. Application of separate Efficiency Targets to the pay budget would therefore be double counting and would mean that we would be unable either to meet the demand for new activities, which remains high, or fund the 2002 pay settlement, which was agreed with the Treasury and was necessary for FCO remuneration to remain competitive.

  Over the next three years the FCO will also undertake a rolling programme of efficiency studies to identify further potential savings across the organisation. Examples include savings on residential accommodation overseas, procurement and ICT working methods. FCO Services (the support arm of the FCO) is also in the midst of a comprehensive business transformation programme which should improve performance and achieve efficiency savings.

Parliamentary Relations & Devolution Department,

Foreign and Commonwealth Office

April 2003







5   Twelfth Report from the Foreign Affairs Committee, Session 2001-02, Foreign and Commonwealth Office Annual Report 2002, HC 826. Back

6   Government Response to the Twelfth Report of the Foreign Affairs Committee, Session 2001-02, Foreign and Commonwealth Office Annual Report 2002, CM 5712. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 4 December 2003