Select Committee on Public Accounts Thirty-Second Report


1. Delivery of the maintenance programme

1. The condition of the network has improved since the late 1980s, and the Agency has sustained this improvement since it was established in 1994. The proportion of the network that is at the end of its life, where the asphalt surface no longer fully protects the road base, has more than halved since the Committee last reported on the road maintenance programme in 1991 (Figure 1). This improvement partly reflects the emergence of 'long life' roads, due to successive surfacing of roads creating a surface layer so thick that roads' structural bases are protected from damage indefinitely. The Agency estimates that 60% of motorways and 25% of trunk roads are now long life.[3]

Figure 1: The trend in the condition of the network, 1985-2001


Notes

1.  The figures for 2000 and 2001 are not strictly comparable with those of earlier years because of a change in the Agency's method of estimating residual life.

2.  A lower percentage of motorways than of trunk roads have a zero residual life because the Agency gives motorway maintenance a higher priority.

Source: National Audit Office

2. The condition of the network does, however, vary significantly between regions. At March 2002, the South West for example had just over 5% of roads requiring maintenance compared to 9% of roads in the North West. The East Midlands and East of England also exceeded the Agency's target range of seven to 8% of the network needing maintenance. The Agency acknowledged that it had only recently started to consider road condition on a regional rather than national basis. It had introduced indicative regional allocations for the part two years which had reduced the degree of variation.[4]

3. The Agency does not directly assess whether the network is in a good, fair or poor condition but uses the proportion of the network requiring maintenance in the following year as a proxy. The Agency recognised that a more robust indicator of network condition was required and had planned to introduce a direct measure of condition in April 2003. However, it was not yet in a position to do so and would retain the current indicator for the current year.[5]

4. The Agency's measures of network condition, and its assessment of the optimal level of maintenance on the network, do not take account of perceptions of road users. The Agency was considering whether and how far users' perceptions should be taken into account more explicitly. Nevertheless, the Agency listened to road users, particularly their views on road surface condition, which was why maintenance was considered so important by the Agency.[6]

5. National data on road surface condition was called for by our predecessors in 1991 but much of the data has only been available since 1998 and data on roadside assets remain incomplete. Our predecessors were also assured by the Department that there would be centrally collected data on the maintenance history of roads from April 1992, but in practice such information has only been recorded for some recent major schemes. The Agency attributed the delays in acting upon previous recommendations to difficulties with the hardware solutions. The Ten Year Plan now included a target on data on road surface condition. The Agency also acknowledged that it had not collected information on the maintenance history of roads systematically or robustly.[7]

6. To assess the technical and economic merits of all major capital schemes over £100,000, agents use Value Management Workshops to score proposals against six criteria of which safety is the most important. Agents then submit their proposals to the Agency and the scores may be revised in discussion. These techniques should allow for projects to be assessed systematically and consistently, but agents' proposals often lack supporting evidence about the benefits that schemes offer, particularly safety benefits which are not quantified. Lower priority projects might therefore go forward at the expense of higher priority work. The Agency acknowledged these weaknesses but was now addressing the problem by putting in place more rigorous systems to measure safety and other benefits.[8]

7. Until recently, the Agency relied on a system of Technical Audits to monitor agents' adherence to contractual requirements and provide assurance about the standard of work undertaken. These audits had revealed deficiencies in the quality of agents' inspections. The Agency is, however, replacing them with Performance Review Improvement Delivery (PRIDe) inspections which audit agents' own quality control systems and their basic competencies, as well as the quality of work. The Agency had extended the length of agents' appointments from three to four years to encourage contractors to invest more fully in the training and development of their staff.[9]

8. The National Audit Office had found that seven out of a sample of nine of the Agency's regional areas had overspent against projects' lifetime budgets by 27% or £21 million in total. Additionally, all three of the projects forecast to cost more than £10 million in 2001-02 were expected to overspend against tender price by between 12 and 27%. The Agency acknowledged that it had focused too much on in-year cost control at the expense of controlling costs over the lifetime of projects. Poor lifetime cost control had resulted in delays to new projects to fund cost over runs on projects not yet finished. Overruns on resurfacing schemes, however, often arose due to unforeseen problems with the structure. The Agency had introduced a new process for managing costs from April 2003.[10]

9. Maintenance work undertaken often differs from that planned, frequently reflecting insufficient design work at the project proposal stage. Costs are estimated before detailed design work has taken place or before the precise nature of the problem is known. Variations after contracts are placed weaken the Agency's ability to negotiate the price of additional work. The Agency acknowledged the deficiencies in its budgeting, and was now making resources available to carry out more detailed assessments, particularly surveys of the structure of the roads, to achieve more accurate specifications at an early stage.[11]

10. Materials known as 'thin surfacings' are now normally used on major repairs. These materials offer greater resistance to rutting, use fewer materials and result in lower noise levels for motorists and nearby residents when compared with conventional surfacings. The Agency acknowledged that it did not have data on the life expectancy of the new surfaces but, based on current evidence, considered that they were good value and wearable. The Agency had a target as part of the Ten Year Transport plan to cover all concrete parts of the network with low-noise surfacing and 60% of all the network.[12]

11. The Agency's annual allocation of monies to smaller capital projects costing no more than £100,000 should be improved. The Agency tells agents what percentage of each category of work, such as drainage or barrier repairs, is 'urgent' on a national basis, based on historical spending patterns. The Agency then funds these sums in full with a lump sum budget. No evidence of urgency or need is sought from agents and there is no prioritisation of bids. The Agency also funds, as a matter of policy, half of the total bid received from Agents for non urgent work, again without any assessment of need. There are therefore no controls to prevent individual agents from over-bidding for this work. The Agency acknowledged that its scrutiny and management of agents' bids for small capital works had not been as strong or as systematic as it should have been, but it had now put in place stricter control and monitoring of smaller schemes.[13]

12. The Agency has transferred 3,200 kilometres of roads not considered to be of strategic importance to local authorities and has also introduced new contracts with agents which are intended to improve efficiency. These changes might have been expected to reduce the Agency's maintenance and administrative costs. The Agency could not, however, quantify the savings, and cost trends suggest that no reduction in the Agency's administration costs has arisen as the workload has reduced (Figure 2). The Agency envisaged that its administrative costs and staffing complement would remain broadly constant for the foreseeable future, as resources were needed to implement the Government's Ten Year Plan for Transport. Staff were being redeployed from managing maintenance work to overseeing the construction of major new road schemes, and to making better use of the existing network. The Agency was, nevertheless, negotiating with local authorities about the transfer of resources.[14]

Figure 2: Highways Agency spending in real terms, 1994-95 to 2001-02


Notes:

1.  All amounts are adjusted to 2001-02 prices and show spending on roads, bridges and other structures.

2.  Payments to DBFO operators are payments made under contracts with consortia of private sector firms to design, build, finance and operate roads. There are currently eight DBFO roads, covering 7% of the Agency's network.

Source: National Audit Office

13. Unit costs of maintenance work have risen in real terms over recent years, from £34 per square metre in 1997-98 to £42 per square metre in 2000-01, an increase of 24% in real terms (Figure 3). Costs look set to continue to rise in future years. The Agency noted that in recent years it had contracted for quality, rather than for lowest cost, to improve delivery and service, and to provide greater certainty of cost.[15]

Figure 3: Unit costs of maintenance work, 1997-98 to 2001-02


Note:

Unit costs are the total costs of all capital maintenance, including Agents' fees, at 2001-02 prices, divided by the number of square metres of road affected.

Source: National Audit Office

14. Motorists involved in accidents may damage crash barriers and safety fences. The Agency has a poor record of recovering the repair costs of such damage, losing over £6 million a year. The Agency noted that in many accidents the culprit could not be identified, especially if the vehicle had been removed before the Agency's contractors became aware of the incident. In other cases, the culprit was known but the Agency had decided not to continue with a claim, often because there was insufficient proof of liability or it was not cost effective to pursue the case through the courts.[16]


3   C&AG's Report, para 2.4 Back

4   ibid, para 2.10, Figure 6; Qq 9-11, 29-36, 48-54 Back

5   Qq 37-38  Back

6   Q 92 Back

7   C&AG's Report, paras 2.5, 5.6; Qq 59-63 Back

8   Qq 75 -78; C&AG's Report, paras 3.4 -3.6 Back

9   Qq 23-24; C&AG's Report, para 4.17 Back

10   Q 18; C&AG's Report, paras 4.8, 4.10 Back

11   Qq 79-80, 82-86 Back

12   Qq 64 -70; C&AG's Report, paras 5.13-5.15 Back

13   Qq 39, 44; C&AG's Report, para 3.12 Back

14   Qq 26-27, 96-103  Back

15   Qq 5, 17; C&AG's Report, para 4.2 Back

16   Qq 13-14, 55-56 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 11 July 2003