Select Committee on Public Accounts Thirty-Fifth Report


1  GREATER CERTAINTY FROM THE PFI

1. The National Audit Office (NAO) carried out a census of all 38 central government PFI projects where the construction phase was due to have been completed by Summer 2002. The results showed that departments were experiencing greater certainty in project delivery under the PFI. The proportions of projects which were not delivered on time, or which cost the public sector more than had been expected at contract letting, were much smaller under the PFI than under previous government building procurement (Figure 1).[2]

2. The OGC considered that the more timely delivery of PFI projects reflected a genuine improvement in building times from the PFI's more disciplined approach and was not due to soft timetables being negotiated. The OGC placed emphasis on the benefits which departments would derive from the greater certainty over when an asset will be available and that the asset will be kept in good order for the whole of its life. Where departments had experienced price increases this had mainly related to additional work which had not been part of the original specification.[3] Figure 1: Improved project delivery under the PFI

  
PFI experience
(2002 NAO census)
Previous experience
(1999 Government survey)
Price exceeds that agreed at contract
22%
73%
Built asset delivered late to public sector
24%
70%
Over 2 months late
8%
  

Sources: PFI experience: NAO census of central government & building projects due to be completed summer 2002. Previous experience based on a government building survey 1999

3. It is encouraging that greater certainty for the public sector is being achieved under the PFI. This certainty may carry a price, however, particularly as the private sector will be charging for the risk of maintaining the built asset throughout the PFI contract period. The CIC told us that the PFI gives the private sector greater incentive to focus from the outset on the whole life costs of the contract. The construction industry had found that PFI produced cost improvements of 5 to 10%, both on construction and subsequent operations or facilities management. The PFI contract is also supposed to give the private sector less scope to escalate the price after contract award. More evidence is needed, however, to show whether these cost reductions have fed through into lower prices compared with conventional procurement. And the CIC's calculations of cost reductions were before any changes to staff costs that may arise if steps are taken to address the two tier workforce issue, where the pay and conditions of former public sector staff transferring to a private sector contractor are different than those of other employees of he contractor.[4]

4. As well as the consideration of project delivery and price, it is important that there is a full evaluation of the wider benefits from PFI projects compared with other forms of procurement. It was disappointing that formal user surveys had only been undertaken in four of the 37 PFI projects surveyed by the NAO. For example, in hospitals the views of doctors, nurses and patients are essential to building up a picture of how well the built asset is serving its intended purpose. The OGC said it would be giving greater prominence to the need for user surveys. It also expected that the design quality indicators developed by the Commission for Architecture and the Built Environment (CABE) would help in assessing public buildings.[5]

5. Because a PFI consortium is not paid until the built asset is operational, contractors might tend to use working methods which deliver the asset quickly without necessarily encouraging new ideas in design and construction. The CIC said that the PFI process should encourage innovation because contractors should be considering methods which minimise the costs of maintaining the built asset over the life of a PFI contract. There was a need to improve on the extent of innovation in PFI projects, however, though there were sometimes constraints in practice. In particular, funders tended to prefer tried and tested solutions as the risks could be more easily predicted.[6]


2   C&AG's Report, Figure 1, p3 and paras 5, 2.3-2.5, 2.17-2.25 Back

3   Qq 1, 11-12, 20, 39-42, 57-63, 92-93, 165-168  Back

4   Qq 11-12, 22-24, 43-48, 92-94, 106-107, 115-117, 135-136, 146-151, 186; Ev 18-19; Qq 146-151 Back

5   C&AG's Report, para 2.29; Qq 4-6, 170-178 Back

6   C&AG's Report, para 1.20; Qq 13, 18-19, 22-24, 112-114, 133-134 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 16 July 2003