APPENDIX 1

TRACK AND SIGNALLING INCREMENTAL OUTPUTS FOR THE NORTH OF ENGLAND


IOS Infrastructure SchemeMain Output Key RequirementExpected Completion

Manchester Piccadilly- New Mills Central Journey Timeimprove journey times 2002
Rochdale-Manchester Victoria-Wigan Wallgate-Southport (via Allerton) Journey Timeimprove journey times 2002
Manchester Airport-Nottingham via Stoke-on-Trent Capacityregular interval service, running earlier and later 2002
Manchester Piccadilly-MarpleJourney Time reduced journey time2002
Blackburn-ManchesterCapacity Sunday service2002
Manchester Victoria-BlackburnJourney Time reduced journey time2002
Olive Mount ChordOperational Flexibility Re-open for freight traffic2002-03
James Street, LiverpoolOperational Flexibility provide additional turnback facilities for use during disruption 2003
Nottingham-SheffieldCapacity 2 trains per hour at regular intervals 2003-04
Hazel Grove-Furness ValeCapacity Additional trains to Furness Vale2004-05
Sunderland-MiddlesbroughCapacity fast service achieved by extension of existing Hartlepool service to Middlesbroughy 2005-06
Wigan WallgateOperational Flexibility Ability to turn back trains from Manchester direction without shunting 2005-06
Carnforth-BarrowJourney Time higher line speeds, giving improved journey times 2005-06
Sheffield-YorkOperational Flexibility upgrade the Monkhill Goods line to passenger status, allowing new through services 2005-06
Crewe-NottinghamJourney Time reduced journey time2006-07
Newcastle-CarlisleCapacity provision of a new turnback and bay platform at Hexham, and associated works to allow additional services 2006-07





 