SUCCESS OF UORS
178. Lessons for the Future states that the
'majority of UORs were very successful in rapidly delivering enhanced
capability.'[259] It
highlighted successes such as the dust mitigation modifications
made to the Challenger 2 main battle tank, the Minimi light machine
gun, and the new Shallow Water Influence Mine-Sweeping equipment
which was leased. The National Audit Office (NAO) concluded that
'overall, the enhancements worked very well'.[260]
During our visits, the Armed Forces personnel we met told us that
they were particularly impressed with the Minimi light machine
gun.
179. There were, however, drawbacks in using the
UOR process. First Reflections acknowledges that 'the UOR
process inevitably involves the risk that not all requirements
will be met in time.[261]
Lessons for the Future[262]
accepts that it 'may be necessary to review the constraints on
earlier industrial engagement to minimise procurement delays in
future' and that 'delivery of equipment was also complicated by
some deployment dates being advanced once the date for the likely
timing of the operation became clearer.' Some equipment had to
be 'delivered direct to theatre', and that 'while delivery was
still achievable in most cases some equipment was not able to
be fitted prior to operations as a result'. Lessons for the
Future[263]
also states that 'personnel did not always have time fully
to train or become familiar with new equipment' and that 'in some
cases, where training occurred only in theatre, this delayed the
achievement of full operational capability'. The complaint that
they had insufficient time to familiarise and train with UOR equipment
was raised with us on a number of occasions by Armed Forces personnel
we met.
180. MoD recognises that 'other capability shortfalls
(e.g. those involving more complex systems such as warships and
aircraft) were not filled by UORs because of the long lead times
involved. We need therefore to consider key war fighting capabilities
and review the Equipment Programme to ensure that we can deliver
them within planning timescales'.[264]
181. Much of the equipment procured as UORs made
a significant contribution to the success of the campaign and,
in most cases, industry supplied equipment at very short notice.
However UORs are not the solution in every case. MoD needs to
be better informed of which types of equipment and capabilities
can be delivered in UOR timescalesthere were a number of
cases where equipment was not delivered by the time required or
where users did not have a full complement. We do not consider
that MoD planning properly recognised that the delivery date for
a piece of equipment and the date by which a capability is achieved
are not the same. If personnel are to be confident and fully efficient
with their equipment there must be adequate time for familiarisation,
training and integration. Furthermore, given the desire stated
in the White Paper to be able to intervene anywhere in the world
at short notice, we believe that the risks of relying on UORs,
instead of holding adequate stocks, are not sufficiently well
analysed or understood in MoD's risk assessment processes.
182. We asked what lessons could be learned from
the UOR process to improve MoD's normal equipment acquisition
arrangements. General Fulton told us that 'one of the key issues
about a UOR is that it has to be available to be bought off the
shelf
One of the reasons why a number of UORs did not succeed
was because there was complex integration involved'.[265]
We heard evidence that the UOR process was becoming part of the
informal procurement process due to the frequency of recent operations.
183. There are likely to be positive lessons from
the UOR process which have applicability to MoD's normal equipment
acquisition processes: for example, where UORs were used to accelerate
existing programmes. We expect MoD to identify and implement these
and reflect on the appropriateness of UOR procurement becoming
institutionalised.
RETENTION OF UOR EQUIPMENT
184. The NAO reported that 'Urgent Operational Requirements
fitted for warfighting may be removed, even sold, if long-term
funding is unavailable or there is no identified requirement to
retain them for the long term. In one case, that of "All
Terrain Mobility Platforms", vehicles that had been disposed
of were repurchased from a company at a cost of £1.1 million'.[266]
MoD is 'now considering which of the equipment bought specifically
for this operation it would be beneficial to retain for future
use'.[267] Sir Kevin
Tebbit told us that some UORs 'will have a continuing bill attached
to them
. We would rather not have simply to destroy them
for want of resources to sustain them in our force structure'.
[268] General
Fulton told us that:
After this operation, we have been very careful
to make sure that we look very critically at what equipment can
and should be retained in service, because by nature of an Urgent
Operational Requirement, it does not come with support funding;
you buy it and that is it. So the first issue is whether we can
afford to take it into the normal equipment programme and provide
it with sufficient support funding so that it can then be sustained
through life
. So there are a number of questions that we
have to ask ourselves, but ultimately, what it comes down to is
the affordability of retaining that capability in-service, and
that is when you have to come back round the loop and ask what
its wider applicability is
. There is a fine balance, and
that is why we are going through it as part of the normal long-term
equipment planning process at the moment, to assess how many of
those 190 we can afford to keep and how many we cannot. Then the
issue is, if there are some that we cannot afford to keep, the
Chief of Defence Logistics would be very keen that we take them
out of service, so that we do not have unsupportable equipment
in the inventory that he cannot then maintain.[269]
We expect MoD to evaluate fully the performance
of the equipment procured as UORs and the specific enhancements
they provided to the UK's military capabilities. This evaluation
must also take full account of the views of those members of the
Armed Forces who used the equipment in action. Disposing of useful
equipment cannot represent good value for money if it then has
to be re-acquired in the future.
218 Ministry of Defence, Operations in Iraq-First
Reflections (July 2003), pp 41-42. Back
219
Q 1 Back
220
Ministry of Defence, Operations in Iraq-First Reflections (July
2003), para 2.13. Back
221
Ministry of Defence, Operations in Iraq-First Reflections (July
2003), para 4.22. Back
222
Ministry of Defence, Operations in Iraq-First Reflections (July
2003), box on p 12. Back
223
Ministry of Defence, Operations in Iraq-First Reflections (July
2003), para 4.22. Back
224
Q 42 Back
225
Committee of Public Accounts, Evidence Session 21 January 2004,
Ministry of Defence: Operation Telic-United Kingdom Military
Operations in Iraq, Q 147 Back
226
Ministry of Defence, Operations in Iraq-First Reflections (July
2003), p 27. Back
227
Ev 387 Back
228
Ev 387 Back
229
Q 1030 Back
230
Q 1037 Back
231
Ev 411 Back
232
HC Deb, 9 February 2004, c1178W Back
233
Ev 452-5 Back
234
Q 1039 Back
235
Q 1039 Back
236
Q 1041 Back
237
Ev 411 Back
238
Q 1031 Back
239
Q 1043 Back
240
Ev 387 Back
241
Q 1984 Back
242
National Audit Office, Ministry of Defence: Major Projects
Report 2003 (HC 195 Session 2003-2004: 23 January 2004), pp
45-50. Back
243
Ministry of Defence, Operations in Iraq-Lessons for the Future
(December 2003), para 2.7. Back
244
Defence Committee, Lessons of Kosovo, Fourteenth Report,
HC347-I (1999-2000), para 287. Back
245
Q 946 Back
246
Q 1018 Back
247
Ev 416 Back
248
Ev 416 Back
249
HC Deb, 25 November 2002, col 128 Back
250
Committee of Public Accounts, Evidence Session 21 January 2004,
Ministry of Defence: Operation Telic-United Kingdom Military
Operations in Iraq, Q 2 Back
251
Committee of Public Accounts, Evidence Session 21 January 2004,
Ministry of Defence: Operation Telic-United Kingdom Military
Operations in Iraq, Q 3 Back
252
Committee of Public Accounts, Evidence Session 21 January 2004,
Ministry of Defence: Operation Telic-United Kingdom Military
Operations in Iraq, Q 4 Back
253
Committee of Public Accounts, Evidence Session 21 January 2004,
Ministry of Defence: Operation Telic-United Kingdom Military
Operations in Iraq, Q 130 Back
254
Q 2262 Back
255
Q 1771 Back
256
Q 1923 Back
257
Q 1939 Back
258
Q 1940 Back
259
Ministry of Defence, Operations in Iraq-Lessons for the Future
(December 2003), para 2.10. Back
260
National Audit Office, Ministry of Defence: Operation TELIC-United
Kingdom Operations in Iraq (HC 60 Session 2003-04: 11 December
2003), para 2.7. Back
261
Ministry of Defence, Operations in Iraq-First Reflections
(July 2003), para 4.4. Back
262
Ministry of Defence, Operations in Iraq-Lessons for the Future
(December 2003), para 2.6. Back
263
Ministry of Defence, Operations in Iraq-Lessons for the Future
(December 2003), para 2.9. Back
264
Ministry of Defence, Operations in Iraq-Lessons for the Future
(December 2003), para 2.7. Back
265
Q 1942 Back
266
National Audit Office, Ministry of Defence: Operation TELIC-United
Kingdom Operations in Iraq (HC 60 Session 2003-04: 11 December
2003), para 2.8 e (iii). Back
267
Ministry of Defence, Operations in Iraq-Lessons for the Future
(December 2003) , para 2.10. Back
268
Q 1772 Back
269
Q 1935 Back