Select Committee on Environmental Audit Minutes of Evidence


Memorandum from English Nature

SUMMARY

  1.  AMP4 is of major importance for the protection of statutory nature conservation sites. Schemes proposed by English Nature and the Environment Agency are based on a robust assessment process using best available information and expert judgement. We have advised the Government that the majority of these schemes are necessary to achieve compliance with the EU Habitats and Birds Directives and the Countryside and Rights of Way (CRoW) Act 2000, by protecting European sites known as Natura 2000 and Sites of Special Scientific Interest (SSSIs).

  2.  Under AMP 3, 90 schemes received funding to protect wildlife on 45 SSSIs. We have advised that AMP4 should include schemes to address water quality on 63 SSSIs and Natura 2000 sites, and water resources schemes on 46 sites, as well as over 120 investigations which may lead to the need for further schemes by 2010. The Habitats Directive and the Government's Public Service Agreement (PSA) target that 95% of SSSIs (by area) should be in favourable condition by 2010 require these schemes to be implemented by 2010, and therefore funded under PR04. Another 43 schemes have been proposed to contribute towards Government commitments to restore priority habitats under the UK Biodiversity Action Plan (UK BAP).

  3.  In 1998, the Environment Agency and English Nature began a joint Review of Consents process to identify all consents, including water company discharges and abstractions, affecting Natura 2000 sites. This review of over 60,000 consents affecting water quality or water resources will be completed in three phases from 2004, 2006 and 2008, and the Agency must affirm, modify or revoke damaging consents within two years of the completed investigations (ie all within the AMP4 period 2005-10). There is no scope for delaying implementation beyond 2010. Any attempt to do so will pose infraction risks for late or non-compliance with EU Directives, and risks failure to achieve the PSA target for SSSI condition.

  4.  We have advised the Government that additional schemes are likely to be identified during the AMP4 timetable as the Review of Consents process is completed. These will require funding under logging up or interim determination orders. It is essential therefore that the present impediments to logging up are addressed.

  5.  Despite a rigorous assessment process by the Environment Agency and English Nature, and robust scrutiny, Ofwat has proposed a constrained environmental programme which we believe would reduce the scope and number of nature conservation schemes below that required to achieve statutory obligations. This would lead to infraction risks, achieve only a minimal reduction in the average overall size of the bill increase and will probably have to be reversed within the AMP4 period to achieve compliance.

1.   Introduction

  English Nature is the statutory body that champions the conservation and enhancement of the wildlife and geological features of England. We work for wildlife in partnership with others, by:

    —  advising—Government, other agencies, local authorities, interest groups, business, communities, individuals on nature conservation in England;

    —  regulating—activities affecting the special nature conservation sites in England;

    —  enabling—others to manage land for nature conservation, through grants, projects and information;

    —  enthusing—and advocating nature conservation for all and biodiversity as a key test of sustainable development.

  We have statutory responsibilities for nationally important nature conservation sites: SSSIs, the most important of which are managed as National Nature Reserves.

  Through the Joint Nature Conservation Committee, English Nature works with sister organisations in Scotland Wales and Northern Ireland to advise Government on UK and international nature conservation issues.

2.   English Nature's role in the PR04 Process

  2.1  English Nature's role in the periodic review is to advise the Secretary of State on the nature conservation component of the environmental programme in England, including both water quality and water resources aspects, in conjunction with the Environment Agency. English Nature is a member of the regulators group for the PR04 process, and was a member of the working group that designed and commissioned surveys of customer opinions in 2003 and 2004.

3.   Nature conservation components of the environmental programme

  3.1  Initial Ministerial Guidance (January 2003) identified three key legislative and policy drivers for nature conservation schemes in PR04: the EU Habitats and Birds Directives, the CRoW Act 2000, and UK BAP. Schemes proposed under the Habitats and Birds Directives are needed to comply with the Government's legal obligations to protect European sites known as Natura 2000, to ensure the achievement or maintenance of favourable conservation status for habitats and species protected at such sites.

  3.2  Initial Ministerial Guidance required that where schemes under the Habitats and Birds Directives and CRoW Act drivers are identified at a high level of certainty, action must be taken to cease or modify discharges, and that funding must be made available where abstraction licences need to be varied or revoked to ensure favourable conservation status. Work to affirm, modify or revoke consents under the Environment Agency's Review of Consents affecting Natura 2000 sites will be completed by 2006, 2008 and 2010 for high, medium and low priority sites respectively (see para 4.2 below). We advise that there is no scope for delaying implementation beyond 2010, the review programme already fully exploits the time allowable for implementation and any further delay will pose infraction risks.

  3.3  Failure to include schemes identified under the CRoW Act driver will place at risk the Government's PSA target that 95% of SSSIs (by area) should be in favourable condition by 2010, and will make it difficult to convince others to play their part. It would also undermine the statutory duty (s28G of the CRoW Act) placed on public bodies, including the Environment Agency, Ofwat and the water companies, to conserve and enhance SSSIs in carrying out their functions.

  3.4  Around 43 nature conservation schemes which are not linked to statutorily protected sites have been proposed, which would contribute to meeting UK BAP targets to restore specific priority freshwater habitats. These have been subject to cost benefit analysis. Although falling into the category of schemes for which choices can be made, we believe they offer significant gains with a very small impact on prices. To exclude BAP schemes would delay the achievement of the UK BAP targets and desired outcomes of the England Biodiversity Strategy (October 2002). It would also reflect poorly on Government's regard for the commitments it made with others: (a) at the World Summit on sustainable development in Johannesburg in 2002 to reduce the rate of biodiversity loss by 2010; and (b) to halt biodiversity loss in the EU within the same timescale.

  3.5  Three water companies have proposed schemes which should help to tackle some water quality issues at catchment level through land management actions, such as reducing livestock density and blocking moorland gripping, that could be funded through the PR04 process. The majority of these land management actions are directed at water companies' SSSI landholdings and will make a significant contribution to the achievement of favourable condition for these sites. We support these proposals both as schemes or investigations for funding under AMP4, and as an objective for future AMP rounds as part of a more integrated and sustainable approach to managing inputs.

4.   Process for providing advice on the size and scope of the nature conservation programme

  4.1  Schemes needed to address problems with water quality or water resources in Natura 2000 sites and SSSIs were determined in close collaboration with the Environment Agency. Joint guidance was developed to determine the need for schemes (at a given level of certainty, from LoC 1—high, to LoC 6—low certainty, see Box 1 below) or investigations. The level of certainty with which schemes were proposed for specific sites was determined jointly with Environment Agency, based on jointly agreed criteria for: (a) degree of risk to or impact on a site; and (b) strength of association with water company activity.

  4.2  The basis for considering individual sites under this process, depended on present scientific understanding of the association between water quality or water resources/flows, and ecological response within a given water or wetland habitat. In the case of Natura 2000 sites, a programme of research and assessment to inform the Environment Agency Review of Consents process was begun in 1998. Following an initial phase of risk assessment, sites were categorised as high, medium and low priority for completion of the review, with completion dates for the assessment of consents (alone or in combination ) by 2004, 2006 and 2008 respectively. Any necessary revocations or variations in permits must be identified and planned within two years of these dates. The selection process for relevant schemes under AMP4 is therefore underpinned by a programme of several years of investigation. Implementation of schemes will take place only when each site assessment is complete and the roles of all other permissions assessed.

Box 1

EXPLANATION OF LEVELS OF CERTAINTY USED IN RECOMMENDING NATURE CONSERVATION SCHEMES
Level 1There is a proven link between a water company abstraction or discharge and damage to the ecological integrity of the site, or failure to meet relevant Environmental Quality Standards (EQS)
Level 2Signs of deterioration in, or risks to, the ecological integrity of the site are apparent and/or EQS are breached. The current understanding of the site is that there is a high risk that the problem is caused by a water company discharge or abstraction. Investigation work has not established this with sufficient confidence but we expect that such work can resolve the issue.
Level 3A link between a water company abstraction or discharge and potentially detrimental impact on the hydrology or water quality of a site has been demonstrated sufficiently. Ecological damage may not be readily observable, however, there may be initial signs of the site condition deteriorating.
Level As Level 2 however, there is no established link with water company abstractions or discharges. The site will be showing signs of deterioration in ecological integrity or EQS failure but the risk of this being caused by authorised water company activities is viewed as moderate.
Level 5The site is showing signs of deterioration in ecological integrity or EQS failure but there is a low risk that this is due to authorised water company activities. There are other factors in evidence, which could have caused the ecological integrity of the site to deteriorate or failure of the EQS.
Level 6There are no signs of damage to the ecological integrity of the site and that the risk posed by water company abstractions and discharges is low




  4.3  For AMP4 planning purposes, our joint advice with the Environment Agency is that all schemes at LoC 1-3 should be included for funding within final business plans (or for funding options appraisal where the precise scheme is uncertain for water resources schemes). Once the assessment process for sites under the Review of Consents is completed, we anticipate that a number of schemes currently at lower levels of certainty are likely to require to be brought into the programme, and there may be some movement of scheme certainty in the opposite direction.

  4.4  Ofwat has proposed a constrained programme under which only those schemes at LoC 1 should be included. We have advised that schemes at LoC 2 and 3 are not optional—there is a high probability that these schemes will be confirmed once the Review of Consents process has been completed. Limiting funding to schemes at LoC 1 will lead to infraction risks and misrepresents the costs to water companies of the programme required to achieve compliance. These costs will have to be passed on to customers and funded by Ofwat through logging up or interim determinations. Excluding them now will not achieve real cost savings and will potentially mislead customers about future bill increases.

  4.5  Some schemes have been challenged (before or during the development of draft business plans) on the basis of high relative or absolute costs. These have been reviewed with the Environment Agency, and in a limited number of cases where we have agreed that there is uncertainty over the outcome of a proposed scheme, further investigation has been required rather than a costed scheme at this stage.

5.   Nature conservation achievements under AMP3

Achievements under AMP3

  5.1  PR99 was the first in which substantive consideration had been given to schemes for the protection of nature conservation sites. Included in AMP3 are schemes and investigations on 72 SSSIs. This constitutes a capital investment of £100 million. £40 million is being spent on phosphorus or nitrogen removal at 72 sewage treatment works on 29 SSSIs. £60 million is being spent on schemes to combat over-abstraction on 18 SSSIs and investigations into water resources problems on 27 SSSIs. The AMP3 investment period (covering 2000-05) is not yet complete, and the majority of nature conservation schemes are scheduled for completion towards the end of that period. At the last full reporting period in March 2003, 10 SSSIs had completed investigations and nine SSSIs had completed schemes.

  5.2  Examples of schemes under AMP3 include:

    —  restoration of flow levels to parts of the River Eden, Cumbria, a Site of Special Scientific Interest (SSSI) and Special Area of Conservation (SAC) under the EU Habitats Directive, which has enabled fish to migrate through one of the major tributaries;

    —  restoration of water levels in parts of North Dartmoor SAC and SSSI which have improved habitats for brown trout and valley mire vegetation;

    —  removal of phosphates for sewage treatment works discharging into Bure Broads SSSI and SAC in Norfolk, Woodwalton Fen in Cambridgeshire, and Loe Pool lagoon SSSI in Cornwall;

    —  investigation of the impact of numerous point source discharges into the river Wye SAC, which has enabled more targeted recommendations for phosphorus removal at sewage treatment works under AMP4. Installation of some phosphorus and ammonia reduction schemes has already led to reported favourable condition on downstream stretches of the river;

    —  reduced abstraction has, with other action to restore wetland conditions, allowed a return to good quality reedswamp at East Ruston Common SSSI and improvements are expected to waterfowl populations.

The AMP4 nature conservation programme

  5.3  A summary of the environmental programme has been published in A Good Deal for water (September 2003). A list of schemes was submitted to water companies for costing at the end of May 2003 and has subsequently been further reviewed by English Nature and the Environment Agency in the light of additional information. Table1 shows numbers of sites affected by schemes submitted under the statutory nature conservation drivers. Around 260 schemes to tackle water quality problems at 63 statutory nature conservation sites were identified at higher levels of certainty. Similarly, schemes are needed at 46 sites to deal with water abstraction problems. A further 121 site investigations also require funding under the AMP4 programme.

Table 1

SITES SUBMITTED BY EA/ENGLISH NATURE FOR AMP 4 FUNDING FOR SCHEMES OR INVESTIGATIONS UNDER STATUTORY NATURE CONSERVATION DRIVERS

Sites with schemes at LoC 1-3 Sites with investigations


Water quality
HD 4335
SSSI20 25


Total63 60


Water resources
HD 3542
SSSI11 19


Total46 61



  HD refers to Habitats and Birds Directive and Ramsar sites, LoC refers to the Level of Certainty with which a scheme has been identified.

  5.4  For water resources schemes, it is difficult to identify schemes without further options appraisal (eg of water availability or use within a catchment) even though impacts on or risks to sites (and hence need for action) from water abstraction were clearly recognised at a high level of certainty. Hence, where water resources schemes could not be proposed at this stage, the Environment Agency recommended to water companies the use of a "sustainability reduction" approach, to enable an estimate of the scale of compensatory water provision that would need to be made in order to protect sites. Estimates based on sustainability reductions should have been included within draft business plans for schemes with high levels of certainty and on this basis a forecast of the scale of the cost of water resources programme could be made.

  5.5  In its advice to Ministers, Ofwat has proposed a constrained capital programme of £15 billion. We believe that this would significantly reduce the scope and number of nature conservation schemes below that required to achieve statutory obligations. As the nature conservation programme comprises only around 10% of the cost of the total quality programme, this reduction is likely to have only minimal impact on the average overall size of the bill increase and will probably have to be reversed within the AMP4 period for reasons set out above (see paras 4.2-4.4). The Environment Agency has advised that the assessment on which Ofwat's recommendations are based has overestimated the costs of environmental improvements, and that there is scope for greater scrutiny of the other pressures for bill increases. We refer you to the evidence from the Environment Agency on this point.

  5.6  English Nature joined the other regulators, as well as Water UK and Wildlife and Countryside Link, in commissioning a survey of customer views on the services provided by the water companies. Nationally, customers confirmed that it is important to maintain current levels of service, rather than allow reduced levels. They also wanted to see some improvements and support was given by the majority of customers to environmental improvements. A similar picture of national support for environmental improvements was evident from the responses to the joint statement launched by regulators in August 2003 (see Ofwat website for a summary of responses).

Parallel action on diffuse pollution

  5.7  In joint advice to Ministers (November 2003), the Environment Agency and English Nature have made it clear that measures to reduce impacts by other sectors are needed in parallel with action on the discharges and abstractions made by water companies. Nutrient pollution, especially from phosphates, causes changes in aquatic plant communities and eventually can lead to algal blooms. Both point and diffuse sources contribute in different ways to this problem and both sources must be tackled together. Diffuse water pollution from agriculture (DWPA) is a major source of nutrient enrichment in many freshwater SSSIs and Natura 2000 sites and English Nature has recently identified those sites most at risk (Prioritising designated wildlife sites at risk from diffuse agricultural pollution. English Nature Research Report 551, November 2003). We have proposed a two tier approach with basic measures across all catchments at risk, and targeted action where additional SSSI protection is necessary. We expect Defra to be consulting on its DWPA proposals in the Spring, and it is important that swift action is taken following the consultation. Such action is needed by 2010, in addition to sewage schemes under AMP4, to meet legal obligations under the Habitats Directive, to help achieve the SSSI PSA target and to ensure proportionate action by other sectors in tackling water quality impacts on SSSIs.

6.   Dealing with uncertainties in this AMP round

  6.1  The timetable for the Environment Agency Review of Consents for Natura 2000 sites does not match that for the price review (para 4.2 above) and so a number of assessments to determine which discharges or abstractions are adversely affecting Natura 2000 sites will not be completed in time for this price review

  6.2  Similarly, a number of investigations or options appraisals have been identified for funding by the water companies under AMP4, where it is not certain whether schemes, or what type of schemes, are needed to achieve favourable condition of SSSIs. In order to ensure that the PSA target for SSSIs is achieved, it is likely that investigations funded in this price review will lead to a need to take remedial action before the next review.

  6.3  Some companies may therefore face changes to costs between this price review and the next. The licences by which water companies operate provide for changes in price limits between reviews under the interim determination order (IDOK) process, where extra costs arising from new obligations exceed a particular threshold related to the turnover of the company. Where the net additional costs do not exceed this threshold, the company must carry these costs under the logging up process until new price limits are set out the next review.

  6.4  It is likely that many of the additional nature conservation schemes will be insufficient to trigger the IDOK threshold for changing price limits, although the scope for this is currently being assessed by the Environment Agency with Ofwat. However the uncertainties associated with the present logging up procedure have led to concerns about reliance on it for bringing forward essential nature conservation schemes. We think that measures should be put in place to give companies confidence that funding (including financing costs up to the next price limit period) will be made available for schemes that are justified under the Habitats Directive and CRoW Act drivers outside the timetable for the price review.

  6.5  Given that the scale and nature of uncertainty of this element of the environment programme is known already, as well as the timetable for producing further information that will enable schemes to be determined, a planned approach to logging up is both possible and justifiable. We suggest that serious consideration should be given to amending the present procedure such that companies receive assurance that schemes will receive funding as soon as they have been approved by the quality regulators (having considered the additional information), rather than at the end of the AMP programme, so that action can be taken to implement schemes within the timetables required to comply with statutory drivers.

February 2004





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 6 May 2004