Select Committee on Environmental Audit Minutes of Evidence


Supplementary memorandum from English Nature

  Response to Specific Questions from the Environmental Audit Committee following English Nature's Oral Evidence Session, 2 March 2004.

  Question 1. Further details of the concerns expressed during evidence that investigations were not completed in a timely manner during AMP3, including examples of where results have not been available to feed into the current review.

  The initial profile of completion dates originally arrived at for AMP 3 investigations with nature conservation drivers is set out in English Nature's memorandum provided to the EAC for its previous enquiry in 2000. This is set out in Appendix 5 of volume II of "Water prices and the Environment", and is presented graphically in figure 1 below. From this it can be seen that for water resources 18 of 37 investigations were timetabled for completion in 2004 or later. For sewage effluent the figures are similar, with 12 out of 22 schemes timetabled for completion in 2004 or later. Given the need to finalise schemes for inclusion in final business plans in March 2004, investigations with completion dates later than this cannot be used to inform inclusion of schemes in AMP 4 business plans.


  Figure 1. Planned completion date for AMP 3 investigations at the start of the process.

  Additionally, some slippage has occurred with investigations. Fourteen water resources investigations were delayed by a year or more (10 were completed ahead of schedule by one year), and five water quality investigations were delayed by one year (none were completed ahead of schedule). These data are summarised in Tables 1 and 2.

Table 1

WATER RESOURCE INVESTIGATIONS UNDER AMP 3, AND SUBSEQUENT STATUS IN AMP4


Water Company SSSI nameCompletion date proposed by EA for AMP3 investigation Actual Completion/ Forecast Completion AMP4 scheme
(+ indicates that a scheme or investigation is proposed under AMP4)
AnglianBeetley and Hoe Meadows 20032004+
AnglianBooton Common 20022004+
AnglianCoston Fen, Runhall 20022004+
AnglianDidlington Park Lakes 20052005-
Anglian Foulden Common 20022004+
AnglianGreat Cressingham Fen 20022004+
Anglian Kenninghamll and Banham Fens and Quidenham Mere 20052005-
AnglianNene Washes2004 2003+
Anglian
(and Essex & Suffolk)
Ouse Washes/The Wash and North Norfolk Coast 20042004+
AnglianScoulton Mere 20032004+
Anglian Sheringham and Beeston Regis Common 20052003-
Anglian Whitwell Common 20032003+
AnglianYare Broads and Marshes 20052005+
Bristol WaterMax Bog 20012001-
CambridgeDernford Fen 20042003+
CambridgeFowlmere2002 2003-
Cambridge Sawston Hall Meadows 20042003+
Essex and SuffolkBurgh Common and Muckfleet Marshes 20022003-
Essex and SuffolkCattawade Marshes 20022003+
Folkestone and Dover Water ServicesDungeness 20032002-
North West WaterBowland Fells 2003-+
North West River Eden Tributaries 2001-+
PortsmouthChichester Harbour 20042003+
Severn Trent Aqualate Mere 20052005+
SouthernRainworth Lake 20022001+
Southern Water and Portsmouth WaterRiver Itchen 20042004+
Southern and Mid KentNorth Kent Marshes 20042006+
South East Penvensey Levels 20042005+
South West WaterEast Devon Pebblebed Heaths 20012002+
South West WaterRiver Camel 20012001-
South West WaterNorth Dartmoor (Taw Marsh) 20022000-
ThamesSulham and Tidmarsh Woods and Meadows 20052003+
ThamesKennet and Lambourn Floodplain, Boxford Water Meadows, Chilton Foliat Meadows, Thatcham Reedbeds 20022003+
Thames River Kennet 20062005+
WelshRiver Wye (Upper Wye and Lower Wye) 20042004-
YorkshireHatfield Moors, Thorne, Crowle and Goole Moors 20042004+
Yorkshire River Derwent, Derwent Ings, Melbourne and Thornton Ings, Breighton Meadows 20042005+


Table 2

SEWAGE DISCHARGE INVESTIGATIONS UNDER AMP 3, AND

SUBSEQUENT STATUS IN AMP4


Water CompanySSSI name STWScheme Completion
date agreed
by EA
Actual Completion/Forecast Completion AMP 4 scheme proposed


Northumbrian
Lindisfarne BelfordN&P removal 31.03.0531.03.05+
Haggerston Castle N&P removal31.03.04 31.03.04-
Severn TrentRiver Eye Somerby<2mg/1P31.03.05 31.03.05+
Langham <2mg/1P31.03.0531.03.05 +
Whissendine <2mg/1P31.03.0531.03.05 -
Severn TrentRiver Teme Tenbury1mg/P31.12.04 -
Knighton <2mg/1P31.03.04 +
SouthernPaghamSidlesham 31.02.022003 +
Harbour
SouthernWalland Marsh Walland Marsh31.03.02 2003-
SouthernLymingtonBrockenhurst P removal31.03.02May 2003 +
Boldre
Bridge
P removal
South WestSlapton
Ley
Slapton<2mg/1P (Scheme underway) 31.03.0531.03.05-
Blackawton 31.03.0531.03.05 -
ThamesRiver KennetMarlborough 2mg/1P31.03.01 +
Fyfield 2mg/1P31.03.04 +
Hungerford 2mg/1P31.03.03
WelshDee EstuaryBodenham
River Lugg
31.03.01
31.03.02
March 2003
2003
-
-
WelshRiver WyeRiver Wye
Monmouth
Schemes as outcome to investigations31.03.02
31.03.05
+
+
YorkshirePocklingtonPocklington 1mg/1P31.03.05-





  Question 2: Further detail about the difficulty of comparing different water companies' business plans due to the different criteria used to prepare them, together with examples of cases where water companies have not included work to meet their statutory obligations for nature conservation.

  In our joint advice in November 2003, English Nature and the Environment Agency advised Ministers to ask Ofwat to require companies to adopt a consistent format for presenting the pressures on prices of the improvements sought in their business plans. We expressed our concern about the lack of transparency, and comparability, of the information in draft business plans. In some cases companies had omitted from their draft business plans, environmental schemes which are required by legislation.

WATER RESOURCES

  The inconsistency in approach was particularly problematic in the case of water resources schemes. As a result of the mismatch in timetables for PR04, the review of consents process required under the Habitats Regulations, and the delivery of many investigations funded under the last review (AMP3), there is uncertainty over the final size of the water resources programme. With the exception of a small number of schemes the actions required to restore and protect sites will not become clear until the results of investigations become available.

  In order to inform the PR04 process, at sites where the outcome of investigation are as yet unknown, the Agency made an estimate of the likely impact of abstraction. This was based, where possible, on local knowledge of the site in question. Where local knowledge was insufficient to make a reasonable estimate, a simplified generic approach was used, based on a proportion of the total licensed volume of the water company abstractions in question in the catchment. The process of estimating "sustainability reductions" within water resources plans was thus an important way of accounting for water abstraction schemes under nature conservation drivers which were submitted at high levels of certainty, but where details for schemes could not be identified until a fuller options appraisal had been carried out by the company.

  Many companies did not followed the Agency's and Ministerial guidance, in developing their preferred plans, and excluded Sustainability Reductions from draft business plans even where these related to statutory obligations. The differing approach by companies is summarised in table 3 (taken from our joint advice to Ministers, November 2003). As an example, Thames Water, which excluded all water resources sustainability reductions for nature conservation schemes, stated in the public summary to their draft business plan that: "The availability of reliable water resources is a major concern with the impending implementation of the European Habitats Directive, which will have an impact on the volumes of water we are allowed to abstract from specific water sources. We have excluded further water availability reductions from our draft plan because of the overriding public interest in supplying water to customers."

WATER QUALITY

  A number of concerns about the nature conservation component of water quality improvements required in the environment programme were identified in companies' draft business plans. The most serious of this was the failure of several companies to include the minimum statutory environment programme in their preferred strategy, (summarised in Table 3 below) whilst some included environmental schemes which were not sought by the Agency or English Nature.

Table 3

SUMMARY OF COMPANIES' DRAFT BUSINESS PLANS BASED ON WHETHER THESE INCLUDE THE MINIMUM STATUTORY ENVIRONMENT PROGRAMME IN THEIR PREFERRED STRATEGY. BASED ON THE JOINT ENVIRONMENT AGENCY/ENGLISH NATURE NOVEMBER ADVICE TO MINISTERS
CompanyEnvironment Programme fully addressed in company preferred strategies
Improvements to water quality Improvements to restore sustainable abstractions


Anglian Waterv
x
Welsh Waterx
Northumbrian Water
United Utilities
Southern Waterx
Severn Trentxx
South West WaterxNo environment programme required
Thames WaterxEnvironment programme (water resources) excluded
Wessex Waterxx
Yorkshire Waterx-


­

    Minimum statutory environment programme fully addressed in company preferred strategy.

    Minimum statutory environment programme not fully addressed in company preferred strategy.

  As an example, one company (Wessex Water) had not included 21 schemes to remove phosphates from a number of nationally and internationally designated river systems in its preferred strategy. The Wessex area is especially notable for chalk rivers, containing by far the highest proportion of river SSSI of this type in Britain. The schemes required reflect the large extent of designated nature conservation sites in this area, their importance—many of the SSSIs are also Natura 2000 sites and Ramsar sites—and population pressures on the freshwater environment. Two other companies had excluded six nutrient removal schemes from their preferred strategies.

March 2003





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 6 May 2004