Select Committee on European Scrutiny Twenty-Fifth Report


3 Decommissioning the Joint Research Centre's nuclear research facilities

(25699)

9818/04

SEC(04) 621

Commission Communication: Decommissioning of nuclear installations and waste management — Nuclear liabilities arising out of activities of the Joint Research Centre (JRC) carried out under the Euratom Treaty

Legal base
Document originated19 May 2004
Deposited in Parliament1 June 2004
DepartmentTrade and Industry
Basis of considerationEM of 22 June 2004
Previous Committee ReportNone, but see footnote
To be discussed in CouncilNo date set
Committee's assessmentPolitically important
Committee's decisionNot cleared; further information requested

Background

3.1 The Commissions Joint Research Centre (JRC) has a number of ageing nuclear research facilities, and its original management policy was one of keeping them in a state of safe conservation (abeyance). However, the Commission considers such an approach to be very costly, and, in a Communication[9] in March 1999, it proposed a long-term action programme, costing some €450 million,[10] under which obsolete installations would be decommissioned, with priority being given to the site at Ispra in Italy,[11] at a cost of €25.4 million over the following four years. The Commission also proposed that this work should be funded, not by additional resources, but by transferring credits from research and development to a newly-created budget heading.

3.2 As our predecessors noted in their Report of 21 July 1999, the UK accepted that the decommissioning of obsolete nuclear installations needed to be addressed, but had expressed serious reservations about this proposal. This was partly because of the suggestion that money targeted for research should be diverted to cover decommissioning costs, but, more importantly, because it considered that the Commission had failed to justify its conclusion that decommissioning, rather than maintenance and surveillance, is the cheaper option. However, they cleared the document on 1 December 1999, after they had been told by the Parliamentary Under-Secretary of State for Science and Innovation at the Department of Trade and Industry (Lord Sainsbury of Turville) that the JRC Board of Governors had supported the Commissions view that immediate action on decommissioning should be taken at Ispra, and that the Research Council was being asked to agree that the Commission should undertake further work to produce a long-term plan, based on an in-depth technical analysis of each site by an independent panel, with a separate budget line being established to fund this work. A subsequent supplementary Explanatory Memorandum from the Minister also confirmed the Government's belief in the importance of such a plan, based on a proper technical evaluation, and, where appropriate, a comparison of costs for individual installations between decommissioning and a strategy of continued abeyance.

The current document

3.3 The Commission has now produced this further Communication on the subject, which deals with the implementation of the programme between 1999 and 2003, and sets out an action plan for the longer term. This makes it clear that the Commission intends to maintain its original approach, and to decommission all the existing installations to the point where all nuclear material, waste and activated or contaminated equipment has been taken out, and all traces of residual radioactivity in the buildings have been removed so that they can be used for other purposes. This process has already begun at Ispra (where the installations have been obsolete for a number of years), but, since those at Petten, Geel and Karlsruhe are still in operation, the Commission does not expect their decommissioning to start before 2015, and possibly not until 2025. The Communication also makes it clear that the costs of the decommissioning programme have risen sharply since the original evaluation, and that, although estimates vary, are now likely to be in excess of €1.1 billion, of which 56% would arise at Ispra, 34% at Karlsruhe, 6% at Petten, and 4% at Geel.

The Government's view

3.4 In his Explanatory Memorandum of 22 June 2004, the Parliamentary Under-Secretary of State for Science and Innovation at the Department of Trade and Industry (Lord Sainsbury of Turville) simply says that there is a clear need to decommission obsolete nuclear installations at these JRC sites, and to have decommissioning plans in train for the closure of those installations which are still in use. He adds that the proposals made here appear to provide an acceptable way forward in dealing with this issue, and that there are no direct financial implications for the UK arising from them.

Conclusion

3.5 Although we accept the need for action to deal with these sites, we are of course not ourselves in a position to judge the respective merits of decommissioning and an approach based on abeyance. However, we note that, whereas the Government had earlier insisted on an in-depth evaluation at each site, with a comparison being made where appropriate between the costs of decommissioning and abeyance, it now appears willing to go along with the decommissioning programme outlined by the Commission. If so, we would like to know the reason for this. Similarly, the Minister's Explanatory Memorandum gives no indication whether the UK accepts that the significant increase in the estimated cost of the programme is justified, or whether its previous concerns that funds earmarked for research were being diverted to this programme have been addressed satisfactorily. Pending further information on these points, we are holding the document under scrutiny.


9   (20239) 8245/99; see HC 34-xxvii (1998-99), para 5 (21 July 1999), HC 23-ii (1999-2000), para 11 (1 December 1999) and HC 23-x (1999-2000), para 7 (1 March 2000). Back

10   This sum was divided between historical liabilities (€230 million) and future liabilities (€223 million). Back

11   The other sites are at Petten in the Netherlands, Geel in Belgium, and Karlsruhe in Germany. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 13 July 2004