Select Committee on European Scrutiny Thirtieth Report


5 Chernobyl nuclear power plant

(25839)

11544/04

COM(04) 481

+ ADD1

Commission Report: Third Progress Report on the implementation of the Chernobyl Shelter Fund December 2003

Commission Staff Working Document: Third Progress Report on the implementation of the Chernobyl Shelter Fund — December 2003

Legal base
Document originated14 July 2004
Deposited in Parliament21 July 2004
DepartmentTrade and Industry
Basis of considerationEM of 31 August 2004
Previous Committee ReportNone
To be discussed in CouncilNot applicable
Committee's assessmentPolitically important
Committee's decisionNot cleared; further information requested

Background

5.1 Following the accident of 26 April 1986, the shelter enclosing the remains of the Chernobyl Nuclear Power Plant Unit 4 was constructed rapidly and under extremely hazardous conditions. It was not intended to be a permanent solution, is increasingly unstable and has deteriorated such that rainwater gets in. There is a risk of collapse, which would lead to further radioactive contamination of the surrounding area.

5.2 In 1997 international experts finalised a multidisciplinary construction management programme, designated the Shelter Implementation Plan (SIP). The SIP envisaged remedial work directed towards making the Shelter physically stable and environmentally safe. Under European Bank for Reconstruction and Development (EBRD) management, the Chernobyl Shelter Fund (CSF) was constituted to finance and implement the SIP. The SIP project started effectively in 1998 with the setting up of the Project Management Unit. There are five major goals:

  • Reduce the potential for collapse of the Shelter.
  • Reduce the consequences of Shelter collapse, should one occur.
  • Improve the nuclear safety of the Shelter.
  • Improve worker industrial safety and environmental protection at the Shelter.
  • Conversion to a safe environmental site.

5.3 The Commission presented a first progress report in October 1999. A second report was presented in September 2001, which we cleared on 17 October 2001.[6] The present report updates the information provided in the previous ones, based mainly on the progress communicated by the EBRD at the December 2003 CSF Contributors Assembly in London. There, the EBRD reviewed the current situation of the CSF and presented revised cost estimates for the New Safe Confinement (NSC), as the final project is called. The USD 1059 million cost estimate (USD 995 million plus USD 64 million for potential additional work) is the first to be based on actual design work, and replaces the original SIP estimate (approximately USD 768 million). This is due to the inclusion of necessary works not foreseen in the initial budget, the potential additional works and what the EBRD regards as conservative escalation, risk and contingency assumptions, rather than increases in baseline costs. A better cost estimate will only become available once the market response for the largest element — the NSC — has been received.

5.4 At CSF pledging conferences in New York (1997) and Berlin (2000) the total sum pledged was USD 717 million (€754 million based on 2000 exchange rates). The Community contribution was USD100 million followed by a second contribution of €100 million. However, as at 31 October 2003, the EBRD reports that contribution agreements between contributors and itself amount to some €615 million, and that payments received by the end of November 2003 totalled some €480 million. So the EBRD has indicated that contributors are likely to be called on again in the near future to make new contributions for the completion of the project. However, the EBRD says no new payments into the fund would be required before 2005, and should be planned in principle for 2006-7.

5.5 Additional challenges are set out in the Explanatory Memorandum of 31 August from the Parliamentary Under-Secretary of State for Small Business and Enterprise at the Department for Trade and Industry (Mr Nigel Griffiths):

"The situation with the Ukrainian nuclear regulator has improved during the reporting period. However regulatory approvals remain one of major risks as they are on the critical path or are closely linked to activities which have the potential to become critical. It is essential that the regulator continues to be provided with the required level of support to ensure that delays are avoided and a proper regulatory and licensing process is fully implemented.

"A coordinated approach to the overall radioactive waste problem at the site is being developed which requires a strong involvement from the Ukrainian authorities. In particular a solution for the high-level solid wastes needs to be worked out. This implies additional costs and delays, and the EU TACIS Nuclear Safety programme may have to assist in supporting these additional costs.

"The schedule for the completion of the SIP, which had been foreseen for 2007 is significantly delayed. The completion of the project, with the commissioning of the NSC is now foreseen by 3rd/4th quarter 2008."

The Government's view

5.6 The Minister goes on to say that:

"the Government welcomes the Commission's Third Progress Report on the implementation of the Chernobyl Shelter Fund [and] is fully committed to the international effort to carry out remedial work on the Chernobyl Shelter directed towards making it physically stable and environmentally safe.

"As the Report states the EBRD will require further commitments from contributors prior to the signature of the contract for the New Safe Confinement, which is currently scheduled for the fourth quarter of 2004. These additional contributions would probably need to be in place by 2006/7. The UK has already contributed a further £10 million to the CSF from the G8 Global Partnership budget, in March 2004. The UK also contributed a further £5 million to EBRD-managed Nuclear Safety Account, specifically for work on radioactive waste clean up at the Chernobyl site. This combined extra contribution of £15 million towards the CSF and projects on the Chernobyl site financed by the CSF, means that the UK will not be in a position to have to contribute further to the CSF when the next pledging round takes place, as noted in the Commission report."

Conclusion

5.7 Previous reports illustrated steady progress in the early stages of a costly long-term programme. But this third progress report has highlighted some major challenges at what is clearly a crucial stage — significant cost increases, funding uncertainties and suggestions of inadequate responses on the part of the Ukrainian authorities. Nor is it clear what the prospects are for their successful resolution. It may be that "the UK will not be in a position to have to contribute further to the [Chernobyl Shelter Fund] when the next pledging round takes place". But others will not be free of such obligations. But are they likely to fulfil them, especially if the final estimates are, as intimated in the report, even higher, once potential suppliers have actually quoted for the New Safe Confinement? And what steps are being taken to ensure that the authorities in the Ukraine play their part, without which, as the Minister makes clear, successful completion of the project — which on best estimates is four years away — will be jeopardised? We are not as sanguine as the Minister appears to be, and would be grateful if he would let us have his views on these unresolved issues. Meanwhile, we will continue to hold the document under scrutiny.





6   (22465) 9455/01; see HC 152-ii (2001-02), para 43 (17 October 2001). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 22 September 2004