5.  Capital Expenditure And Investment (continued)

  5.3.2  Could the Department provide a commentary on cases where there are significant discrepancies between original estimates of completion dates and/or expenditures and current estimates? [5.3.2]

Avon and Wiltshire Mental Health Partnership NHS Trust

Old Manor Hospital

  The time delay is mainly due to the overrunning of another scheme preventing removal of closing wards from the site.

Good Hope Hospitals NHS Trust

Diagnostic and Treatment Unit

  The time delay is due to the discovery of asbestos in existing ducts and other issues that are the subject of discussion with the contractor. Efforts are under way to resolve existing problems and to mitigate any delays.

Royal Orthopaedic Hospital NHS Trust

Diagnostic and Treatment Unit

  The delay is due to the discovery of asbestos in existing wards and other issues that are the subject of discussion with the contractor. Efforts are under way to resolve existing problems and to mitigate any delays.

Royal Wolverhampton Hospitals NHS Trust

Cardiac Unit

  The delay is due to adverse weather conditions and the issue of variations to the project. Efforts are under way to resolve existing problems and to mitigate any delays.

South Tees Hospitals NHS Trust

Redevelopment of Friarage Hospital (Northallerton)

  The predicted time (+8.33%) and cost (+33.05%) overruns are due to the Trust's severe under-estimation of scheme content and cost at the single, combined Outline/Full Business Case Stage. This particularly relates to the Services Engineering Infrastructure On-Costs and Inflation, for which the Strategic Health Authority is processing a Revised Approval.

Portsmouth City Primary Care Trust

Reprovision of Adult Mental Health

  The original estimated completion date has slipped due to a delay in work starting on site. However, the original contract programme of 15 months duration remains the same.

Hull and East Yorkshire Hospitals NHS Trust

Cardiothoracic Services Development at Castle Hill Hospital, Hull

  The predicted time (+15.50%) overrun is due to a longer period required for refinement of the Scheme Brief and Development of Scheme Design post the single, combined Outline/Full Business Case Stage Approval.

Gateshead Health NHS Trust

Queen Elizabeth Hospital Treatment Centre at Gateshead

  The predicted cost overrun of 12.30% is due to the addition to the scheme of IT, Artwork and Green Issues provisions, together with extra "shell" accommodation to functionally future-proof the Treatment Facilities.

James Paget Healthcare NHS Trust

Treatment Centre—James Paget

  The reason for the overrun is changes to design post approval.

Royal Shrewsbury Hospitals NHS Trust

Royal Shrewsbury Acute services reconfiguration

  The delay is due to the need to repair and rebuild service ducts in the road that provides the exit route for the contractor from this site. This is a consequence of traffic associated with this contract. In addition, there are other issues that are the subject of discussion with the contractor. Efforts are under way to resolve existing problems and to mitigate any delays.

Guy's and St. Thomas' NHS Trust

Rationalisation of Acute Services, Women's Services and Cancer Services

  The rationalisation of Women's, Children's and Cancer Services at the Guy's site and the St Thomas' site is partly publicly funded and partly funded by Guy's and St Thomas' Charitable Foundation, the £50 million cost identified in the table being the public element. The majority of the publicly financed works are complete. On completion of the new charitably funded Children's Hospital, also part of this scheme, the remainder of the works will be completed. Additional funding of £3.5 million to deal with the issue of mixed sex accommodation, an initiative introduced after FBC approval, has been added to the scheme.

Great Ormond Street Hospital NHS Trust

Phases 1A/1B

  Whilst the programmes were delayed for various reasons including prolongation of design, planning consent etc, the Capital costs is still within forecast.

Barnet Primary Care NHS Trust

Phase 3 of the Edgware Community Hospital project

  The reasons for the time and cost overruns are complex and are connected to the completeness of design at the point of letting the construction contract together with a degree of client driven changes.

Newham Healthcare NHS Trust

Treatment Centre

  The Newham increase is due to a change in scope.

  5.3.3  Could the Department provide an update of Tables 5.3.3? [5.3.3]

  1.  An update of Tables 5.3.3(a) to 5.3.3(e) is attached.



 