5. Capital Expenditure And
Investment (continued)
2. FISC, the DoH finance sub-committee chaired
by Richard Douglas, the Director of Finance, provided a ruling
regarding revenue support for PFI projects. With effect from April
2003, no central budgets were to be maintained to provide revenue
subsidies for PFI projects. These were for smoothing money; support
for deferred assets/residual interest and for on balance sheet
PFI projects.
3. Following further consultation it was
decided to withdraw central support after a transitional phase.
This and the sums were agreed and notification circulated in Spring
this year.
4. Support for deferred assets/residual
interest and on balance sheet schemes is to be phased out by 2005-06.
5. Support for Smoothing money is to be
phased out by 2007-08.
5.3.4 Could the Department provide an
update of Tables 5.3.4? [5.3.4]
1. The information requested is provided
in Table 5.3.4.
Table 5.3.4
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
|
A | B | C
| D | E
| F |
North | Capital Cost at OBC Stage
| Capital Cost Reported Last Year
| Capital Value This Year |
% Increase Since OBC Stage |
% Increase Since Last Year |
| £m |
£m | £m
| | |
|
Leeds Teaching Hospitals | 125.0
| 174.0 | 221.0
| 76.8% | 27.0%
|
Newcastle upon Tyne Hospitals | 129.5
| 220.1 | 256.2
| 97.8% | 16.4%
|
Mid Yorkshire Hospitals | 164.1
| 211.0 | 256.0
| 56.0% | 21.3%
|
Hull and East Yorkshire Hospitals (Oncology)
| 37.6 | 56.0
| 60.4 | 60.6%
| 7.9% |
Newcastle, North TynesideMorpeth |
21.3 | 25.0
| 31.8 | 49.3%
| 27.2% |
Northgate and Prudhoe PCT | 14.0
| 14.0 | 24.0
| 71.4% | 71.4%
|
Sheffield Teaching Hospitals | 30.0
| 30.0 | 31.2
| 4.0% | 4.0%
|
Central Manchester and Manchester Children's
| 199.0 | 420.0
| 414.7 | 108.4%
| -1.3% |
East Lancashire HospitalsBurnley |
13.7 | 30.1
| 31.5 | 130.8%
| 4.7% |
St Helens and Knowsley | 211.0
| 229.0 | 257.8
| 22.2% | 12.6%
|
Salford Royal Hospitals | 114.0
| 196.3 | 186.2
| 63.3% | -5.1%
|
Tameside and Glossop | 41.0
| 84.2 | 84.2
| 105.4% | 0.0%
|
Doncaster and South Humber | 11.3
| 12.1 | 15.0
| 32.7% | 24.0%
|
Selby and York PCT | 23.6
| N/A | 24.2
| 2.5% | N/A
|
East Lincolnshire PCT | 24.0
| N/A | 24.0
| 0.0% | N/A
|
North Kirklees PCT | 25.0
| N/A | 27.0
| 8.0% | N/A
|
TOTAL NORTH | 1,184.1
| 1,701.8 | 1,945.2
| | |
|
COMMENT ON ANY INCREASES OVER 10%
|
Leeds Teaching Hospitals |
|
|
Initial OBC cost | 125
|
Increased Multi-storey car park requirement
| 21 |
Increased building size requirements including incorporation of elements of "improving the patient experience"
| 25 |
Detailed review of fixture and fittings |
3 |
Development of M & E services | 5
|
Inclusion of PACS | 2
|
Other equipment changes | 2
|
Specification developments and reviews including linnear accelerator shielding requirements and service requirements
| 20 |
MIPS uplift | 26
|
Reduction to enabling schemes | -8
|
Current Capital cost | 221
|
| |
Newcastle Upon Tyne Hospitals | % increase
|
Inflation | 30.27
|
Extended scope to contain Children's wing |
29.13 |
Improving the patient environment | 15.32
|
Service developments | 8.59
|
Design implications at RVI | 6.73
|
Roof Top Helipad for A&E (Revised CAA guidance will no longer allow a ground level landing pad)
| 1.09 |
Inclusion of items previously recorded as Charitably Funded (to align costs with PFI bids). NB: the trust will still pursue charitable funding for these elements (Cystic Fibrosis, relocation of Doulton Tiles).
| 2.76 |
A larger multi-storey car park at the Freeman Hospital (City Council planning requirement.)
| 3.98 |
Total % increase since OBC | 97.87
|
Mid Yorkshire HospitalsWakefield
| |
Capital cost at SOC stage | 164.1
|
Increase relating to the NHS Estates Departmental CostAllowance Guides (DCAGs) taking into account the new principles in order to produce a better patient environment.
| 23.6 |
Changes in functional content | 12
|
Additional scope and space requirements |
17 |
Non works cost changes | 2
|
Additional contingency | 2
|
Other | 0.3
|
Increase to latest MIPS level | 32
|
Increased use of Public funds to advance the scheme as part of the OBC approvals process
| 3 |
Current Capital value | 256
|
Hull and East Yorks |
|
Capital cost at SOC stage | 37.6
|
Improving the patient environment | 2.9
|
Increased linnear accelerators (3 to 6) |
6.1 |
Inflation | 5.8
|
Undergraduate teaching accomodation | 1.2
|
Reprovision of boiler house | 1.5
|
Other functional and infrastructure changes
| 0.9 |
MIPS increases | 4.4
|
| 60.4 |
Newcastle, North TynesideMorpeth
| |
Improving the patient environment |
|
Design development | |
Refined on-costs following geo-technical survey
| |
Inflation (Mips 310 to FP 395) |
|
Central Manchester & Manchester Children's
| |
Original OBC figure | 199
|
MIPS increase | 12.6
|
Adult NBI growth & children's Burns & Cleft Lip
| 23.2 |
Energy targets, building regs & Health and safety
| 7.75 |
Mental Health reprovision | 7.75
|
Final OBC figure | 250.3
|
Early Delivery of Children's facilities |
26.9 |
Modernisation | |
Adults NBI growth | 12.8
|
Equipment consequences | 7.9
|
Cardiac services | 1.7
|
Obstetrics new model of care | 1.5
|
Improving the Patient Experience | 30.8
|
New Guidance (Health & Safety, building regs etc)
| 12 |
Service DevelopmentsNationally/Regionally Driven
| 10.4 |
Service DevelopmentsTrusts driven |
5 |
Service Developments University Driven |
1 |
Other | 9.6
|
Capital Costs as per FBC | 369.9
|
FBC Inflation | 50.2
|
reduction | -7.1
|
FBC Cost | 413
|
East Lancashire HospitalsBurnley
| |
Increase from £13.7 to £31.5m: |
|
NBI and NHS Plan | |
Renal Dialysis Unit |
|
MIPs increases to MIPS 408 |
|
Clarifications PSC |
|
St Helens & Knowsley Hospitals |
|
OBC costs | 229.8
|
Service changes/consumerism |
|
Whiston | |
wards consumerism | 3.7
|
Critical care new HBN 27 | 1.7
|
Whiston out-patients | 1.5
|
Pathology body storage | 0.2
|
relocate A & E, burns review | 1.2
|
CT & MRI link to A & E | 0.6
|
St Helens | |
In-patient facility at St Helens | 1.1
|
Nuclear medicine and CT suite | 1.1
|
Functional content changes |
|
Whiston | |
General changes in content, offices etc. |
2 |
Additional on-costs, circulation | 2
|
Temporary accommodation | 2.1
|
Remodelling of retained accommodation | 4.5
|
St Helens | |
Hamill day assessment | 1.5
|
Clinical psychology | 1.1
|
Clinical measurement | 1.1
|
Additional on/costs, circulation | 1.6
|
Additional on/costs, drainage, piling | 0.8
|
Enabling, R & D reprovision | 0.2
|
Revised PSC costs | 257.8
|
Salford Royal | |
SOC cost | 114
|
Building Inflation | 12
|
Improving the patient experience | 10
|
Estates standard | 9
|
A&E | 4.1
|
shift to HDU beds | 3.8
|
Post acute bed | 2.5
|
Neonatal | 0.6
|
Children's | 1.6
|
On costs | 18.3
|
Ceiling limits | 1.5
|
Deacked car park | 4
|
Equipment | 4.6
|
Contingency | 3.9
|
Reduction in VAT free costs | 3.1
|
Increase in Health & Social Care centre costs.
| 3.3 |
Total | 196.3
|
This figure represents the capital costs of both the Hospital PFI scheme and the four Health and Social Care Centres, these have now been grouped together to reflect the scope and content of the OBC. However, the HSCCs are being procured under Lift and therefore not part of the PFI procurement. The capital costs below show the costs of the Hope Hospital PFI scheme only:
| |
Withdrawal of HSCCs from scheme costs | -19.4
|
Reconciliation | -3.2
|
Reduction of new build following review in 2003
| -3.6 |
Increase in MIPs for Hope Hospital from 360 to 395
| 16.1 |
| 186.2
|
Tameside & Glossop |
|
SOC cost | 41.0
|
Improving the Patient Experience/modernisation
| 18.3 |
Equipment | 3.5
|
Renal | 1.0
|
MRI | 1.6 |
Opthamology | 4.2
|
NBI growth | 4.5
|
EMI | 10.1
|
Total OBC | 84.2
|
Doncaster & South Humber |
|
Initial OBC cost | 11.3
|
Inflation to initial FBC date | 0.8
|
| 12.1
|
Inclusion of Equipment in construction costs
| 0.9 |
Additional costs re dealing with floodplane
| 0.2 |
MIPS increases to delayed financial close |
1.8 |
| 15.0
|
|
Table 5.3.4
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
|
A | B | C
| D | E
| F |
London | Capital Cost at OBC Stage
| Capital Cost Reported Last Year
| Capital Value This Year |
% Increase Since OBC Stage |
% Increase Since Last Year |
| £m |
£m | £m
| | |
|
Barking, Havering and Redbridge | 145.6
| 181.5 | 232.4
| 59.6% | 28.0%
|
Barts and The London | 620.0
| 1,052.0 | 1,052.0
| 69.7% | 0.0%
|
The Whittington Hospital | 23.0
| 23.0 | 29.4
| 27.8% | 27.8%
|
Wandsworth PCT | 20.5
| 42.9 | 57.4
| 180.0% | 33.8%
|
Newham Healthcare | 21.3
| 42.4 | 54.8
| 157.3% | 29.2%
|
Kingston Hospital | 22.1
| 27.6 | 32.8
| 48.4% | 18.8%
|
Paddington Basin | 327.0
| 800.0 | 800.0
| 144.6% | 0.0%
|
North West London Hospitals | 55.0
| 69.3 | 68.6
| 24.7% | -1.0%
|
Lewisham Hospital | 44.0
| 47.0 | 73.0
| 65.9% | 55.3%
|
North Middlesex | 73.0
| 74.0 | 100.8
| 38.1% | 36.2%
|
Barnet and Chase Farm | 41.0
| N/A | 79.8
| 94.6% | N/A
|
Whipps Cross | 184.0
| N/A | 329.7
| 79.2% | N/A
|
LONDON TOTAL | 1,576.5
| 2,359.7 | 2,910.7
| | |
|
COMMENT ON ANY INCREASES OVER 10%
Barking, Havering and Redbridge Hospitals
Building cost Inflation (MIPS) |
Indexation |
The location factorthe premium experienced for building in Outer London has increased
|
Design fee allowance and Contingency allowance
|
Additional 60 beds and clinical accommodation.
|
The project achieved financial close on 15 January 2004.
The final capital cost shown is the actual at financial close
and is the cost to the private sector plus the cost of land. The
cost quoted includes the costs of land, construction, equipment
and professional fees but excludes VAT, rolled up interest and
financing costs such as bank arrangement fees, bank due diligance
fees, banks' lawyers fees and third party equity costs. The cost
of the land (£26 million) was borne by the public sector
and is therefore excluded from the analysis for question 5.3.3.
Barts and the London
The Barts and The London OBC was approved at a cost of £462
million. The figure reported previously (£620 million) included
an estimate for building cost inflation, due to the complexity
and duration of the scheme. The increase to the current forecast
outturn is explained as follows:
|
| £m
|
|
OBC approved capital cost (MIP295) | 462
|
Changes in scope of project (MIP295) | 237
|
Building cost inflation | 353
|
Current forecast outturn cost (equivalent to MIPS 460)
| 1,052 |
|
The OBC was submitted in November 1999 and used the then
current MIPS index of 295 giving a base date for inflation calculation
of 1997.
The changes in scope include an additional 125 beds and other
supporting facilities, improvements to the patient environment
in line with the NHS Plan, and the removal of ICT systems (to
be procured separately) from the scheme. All changes have been
agreed with the Trust's commissioners.
The current forecast outturn assumes construction takes place
between 2005 and 2013. The £353 million building cost inflation
equates to an increase of 51%. Building cost inflation, as measured
by the NHS Estates MIPS index, has increased by 33% since 1997.
Building cost inflation is estimated to be rising at approximately
3% to 5% per annum (this needs to be treated with caution as the
predictive accuracy of the MIPS index is not strong and building
costs can be volatile, particularly in London). The current forecast
outturn includes an estimate of inflation up to the completion
of the majority of the new build in the scheme in 2009.
It should be noted that the increase from £620 million
to £1,052 million is the cumulative increase over the last
four years since the OBC was approved. All these figures relate
to the Trust's Public Sector Comparator that has been updated
periodically throughout the last four years to reflect the changing
content of the scheme. A full review of the of the PSC was carried
out during summer 2002 and more recently building cost inflation
assumptions were updated in the light information available to
the Trust from its bid development process.
The Whittington Hospital
As previously reported, the increase from OBC at MIPS 310
is largely due to inflation, combined with the excercising by
the Trust of an Option in the Project Agreement to fit-out an
additional floor with 40 beds. Inflation accounts for the bulk
of the increase (MIPS 310 to MIPS 380 at financial close). The
Trust has also opted to let the retail fit-out works as a separate
contract, leading to a slightly reduced capital cost figure.
Wandsworth PCT
The building price index (MIPS) has increased the base capital
cost by £13.170 million. The location factor has increased
from 12% to 23% as Wandsworth is deemed an Inner London Borough.
This has increased costs by a further £2.551 million. Gross
inflationary increases are £15.721 million. The SHA took
a decision to include Mental Health (69 beds, Day Hospital and
CMHT bases) and Shell Space to allow for future service provision
in Summer 2002 amounting to a furhter cost of £19.236 million.
Additional costs of equipment, lifecycle costs and revisions to
programme resulted in an extra cost of £2.036 million.
Newham Healthcare
Increases in inflation since OBC account for £6.8 million.
Increase in location factor from 9% to 16% accounts for a further
£2.2 million. Hence £9 million of the £21 million
increase relates to inflationary pressures. Changes in Building
Regulations and Landfill Costs have added a further £2.8
million. Actual changes in specifications, additional equipment
etc account for £3 million. The requirement for other unforeseen
works on sitedecanting, upgrading of kitchen facilities
and construction traffic access from the A13 have added £4
million. The final £3.8 million relates to increased risk
allowance for working within existing buildings and near to occupied
patient areas.
Increase since last year due to: change in MIPS index, an
increase in the location factor adjustment and the finalisation
of all details of the scheme up to financial close in January
2004.
Kingston
OBC capital cost was £22.1 million based on a MIPS index
of 310. The FBC capital cost is £32.7 million based on a
MIPS index of 422. The movement due to inflation is £8.1
million. The movement due to changes in specification is £2.5
million which is 11% of the OBC cost.
Paddington Basin
The capital cost at OBC was at MIPS 310 and the current costings
are at MIPS 360, giving an inflation increase of 16% or £50
million. The Imperial College NHLI building is now included within
the project scope. This was to have been procured seperately.
The requirements to improve the patient experience have been worked
into a more detailed design solution. The proportion of critical
care beds has also increased with a consequent increase in the
space required. The overall campus will have an increase of 26
beds, giving a current total of 1,088. Buildings to be retained
(QEQM and Clarence Memorial) will now be completely refurbished
as part of the project. Underground construction work has been
priced more realistically and an appropriate contingency now allowedthere
are several tube lines close to the surface of the site.
The Paddington Basin Health Campus project is in the process
of submitting a new Outline Business Case for the project. The
likely capital cost is £800 million which is the same as
reported last year.
North West London Hospitals
The increase from the OBC is due to:
Increase in the price base from MIPS 325 to MIPS 360£5.8
million
Increase in the outer London location adjustment£0.5
million
In line with plans developed by Park Royal Partnership for
the regeneration of Park Royal, the footprint for BECaD has been
moved. This has lead to significant costs in providing temporary
accommodation for departments that will be displaced. Additional
costs of £2 million will be covered by a grant from the London
Development Agency.
A multi storey car park has been added to the FBC at a cost
of £2.4 million. This contributes to the potential for land
development which the new footprint allows.
A planned extension to ACAD as part of the overall change
in the delivery of services at Central Middlesex Hospital has
been increased in size at a cost of £0.7 million. This is
partly to provide temporary accommodation for displaced departments
during BECAD construction and partly to allow for increased capacity
in the long term.
There has been few changes in the content of the BECAD building.
Changes that have been made include:
Two additional radiology film rooms to improve throughput
reducing waiting times and length of stay £1.5 million
A sterile services department 0.7 million
The balance is due to general increases in department areas
and specifications in line with NHS Estates guidelines to improve
the patient experience. All the above costs exclude VAT as this
is not a cost within the overall public accounts. The capital
value this year is at the approval MIPS level of 360.
Lewisham Hospital
The capital cost at OBC was at MIPS 310 and the current costings
are at MIPS 422, giving an inflation increase of £11 million.
The increase in the inner London location adjustment from 21%
to 23% accounts for a further £1 million. General increases
in department areas and specifications in line with NHS Estates
guidelines to "improve the patient environment" have
increased costs by £5 million. Changes in Building Regulations
added £2 million and additional equipment to meet health
and safety requirements has added £2 million. Changes in
the scope of the scheme included an additional floor to accomodate
beds for elderly patients, increasing the number of beds reprovided
in the scheme from 284 to 419. The total cost of changes in scope
and functional content was £5 million. All changes have been
agreed with the Trust's commissioners.
North Middlesex Hospital NHS Trust
The main reason for the increase is the 18% increase in out-turn
inflation of £13.2 million due to upwards revision of MIPS
indices since OBC. A number of pressures on accommodation requirements,
including the issue of new HBNs has resulted in an increase in
functional content of £4.8 million, or 4.6%. The active switching
element of IT£1.2 millionwas excluded from
the OBC capital cost as it was assumed this would be funded directly
by the Trust, however there is insufficient block capital funding
available. The OBC cost forms relied on ECAGs and the equipment
costs were subsequently revised to take account of the Trust's
manual handling policy and include the cost of digital imaging
technology. Additionally the OBC contained aggressive assumptions
about transfers, which, following an in-depth consideration of
individual equipment items, are not reflected in the equipment
schedules provided to bidders in the ITN. The overall increase
in the net cost of equipment is £3.7 million.
Finally the scheme now includes Ophthalmology£1.7
million, which was excluded from the OBC, but which the PCTs have
now asked to be included, and approximately 2,200 sq m of shell
space£3 million, which will provide flexibility to
respond to a number of current issues and strategic changes across
the sector.
Barnet and Chase Farm Hospitals NHS Trust
The functional content of the project has been revised to
include an additional two theatres and an additional endoscopy
suite. An additional 17 beds are also to be provided. The capital
costs have also increased in line with the increase in MIPS and
the consequent increases generated by this in fees, contingencies
etc.
Whipp Cross University Hospital NHS Trust
The OBC was approved in principle in July 2003 and finally
approved by the SHA in January 2004. The scheme cost has increased
due to: changes in the MIPS index, change in location factor and
the consequent increases in associated costs (fees, contingencies
etc). The project has also responded in full to improving the
patient experience and the revised space standards. The approved
OBC sum was £328 million (with the SOC being £184 million).
A schedule of decanting and enabling works has been developed
to assist the future PFI provider in clearing the site. One of
these early schemes is the creation of a new energy centre on
the site which woudlj have been necessary in any event. An uplift
was agreed to the cost of this (due to building price inflation)
which added a further net £1.7 million to the project control
total. The current control total is £329.7 million.
Table 5.3.4
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
|
A | B | C
| D | E
| F |
South | Capital Cost at OBC Stage
| Capital Cost Reported Last Year
| Capital Value This Year |
% Increase Since OBC Stage |
% Increase Since Last Year |
| £m |
£m | £m
| | |
|
Avon and Western Wiltshire MH Partnerships |
68.0 | 83.0
| 83.0 | 22.1%
| 0.0% |
Salisbury Healthcare | 15.6
| 22.0 | 24.1
| 54.5% | 9.5%
|
Taunton and Somerset Cancer Unit | 16.0
| 18.0 | 18.0
| 12.5% | 0.0%
|
Portsmouth Hospitals | 127.7
| 192.0 | 192.0
| 50.4% | 0.0%
|
Oxford Radcliffe HospitalsRelocation |
95.0 | 134.0
| 137.0 | 44.2%
| 2.2% |
Buckinghamshire Hospitals
Stoke Mandeville
| 23.7 | 47.7
| 46.6 | 96.6%
| -2.3% |
Brighton HealthcareChildren's scheme |
30.9 | 43.0
| 37.1 | 20.1%
| -13.7% |
Oxford Radcliffe HospitalsCancer |
60.0 | 93.0
| 99.7 | 66.2%
| 7.2% |
Plymouth Hospitals | 101.0
| 274.4 | 348.7
| 245.2% | 27.1%
|
New Forest PCTLymington | 36.0
| 36.0 | 36.0
| 0.0% | 0.0%
|
South Devon | 65.0
| N/A | 250.0
| 284.6% | N/A
|
Southampton | 52.0
| N/A | 80.0
| 53.8% | N/A
|
Maidstone & Tunbridge Wells | 175.0
| N/A | 290.0
| 65.7% | N/A
|
TOTAL SOUTH | 865.9
| 943.1 | 1,642.2
| | |
|
COMMENT ON ANY INCREASES OVER 10%
Avon and Western Wiltshire
Projected increase up to financial close from MIPS 325 to
MIPS 398.
Projects transferred from PFI to other procurement packages
(treasury funded and LIFT)
Design and developmentimproving the patient experience
Uplift in on-costs for Secure Services
Salisbury Healthcare
Addition of Laundry and increase from MIPS 325 to MIPS 360.
Taunton and Somerset
Increase from MIPS 325 to MIPS 360
Portsmouth Hospitals
Impact of change from MIPs 378 to MIPs 415
Improving the patient environment
Additional 20 Maternity beds
Impact of building regulations
|
OxfordRelocation Scheme
Change to MIPS
| 27.3 |
|
Adjustment to price level to correct for location factor
| 5.0 |
Impact of Building Regulations Part L | 3.5
|
Impact of "improving the patient environment"
| 6.0 |
"Real" changes in design/functional content
| 0.2 |
| 42.0 |
Stoke Mandeville | |
Cost at OBC | 23.7
|
New Mortuary | 0.7
|
Improving the patient environment | 3.0
|
Intermediate Care ward (22 beds) | 1.6
|
Pharmacy and Cook-chill reprovision | 1.8
|
Additional Acute Medical beds/Stroke Unit (44 beds)
| 3.4 |
Trust Admin | 0.9
|
Uplift from MIPS 310 to MIPS 394 | 11.5
|
Cost this year at MIPS 394 | 46.6
|
Brighton | |
| |
For the 2003-04 Return, the outurn capital cost figure was quoted as
opposed to current MIPS rate
| 30.9 |
OxfordCancer Centre Scheme |
|
| |
Capital cost at MIPS 325 | 60.0
|
Uplift from MIPS level at previous report to MIPS as at 1 April 2002
(MIPS 325 to MIPS 361)
| 6.4 |
Elderly care scheme added | 27.2
|
Value reported last year | 93.6
|
Elderly scheme removed | -27.2
|
Uplift from MIPS 361 to 438 | 14.2
|
Addition of variant proposals: Private patients, Theatres, PET/MRI build.
| 19.1 |
Current capital cost | 99.7
|
Plymouth Hospitals |
|
Capital Cost Reported "Last Year" to "Capital Cost at OBC Stage" variance: The figure of £101 million was the estimated cost at the SOC stage in 2000-01. Following the SOC, a detailed review has resulted in the original scheme being combined with a rehabilitation SOC for the Plymouth Health Communiy. This has a benefit for patient services in creating a more integrated solution and for the PFI process as a combined scheme. In addition, further improvements in the patient environment and associated costs for VAT and inflation have resulted in a new scheme design and cost. The revised total cost includes the following amendments:
| |
Post SOC inclusion of an Intensive Rehabilitation Capital project previosuly managed by Plymouth Community Trust.
| 45 |
| |
Improvements to the patient environmentthe original refurbishment of the Hospital Building within the SOC only included the reconfiguration/relocation of services. As further work was conducted it became evident that a significant part of the buildings infrastructure needed replacement to meet modern standards, hence, additional costs were included to cover the replacement of lifts, electricity infrastructure and other infrastructure items.
| 65 |
Additional VAT costs not included within the original SOC
| 40 |
Uplift for inflation from SOC to OBC stage |
23 |
Total increase since SOC | 173
|
Capital Value "This Year" to "Capital Cost Reported Last Year" variance: The capital value last year showed the uninflated figure (MIPS VOP345), this has now been inflated using NHS Estates guidelines to the relevant inflation figures for each year which results in an additional £77.6 million for inflation up until 2010. The MIPS increase has been offset by minor savings of £3 million on the scheme.
| |
Total Increase since last Year | 74.4
|
South Devon Healthcare |
|
The figure of £65 million was the anticipated cost at the SOC stage. The SOC of Torbay was based on a scheme, which was focused on an improvement in Surgical Services and A&E only and the refurbishment of 15,600m2 of existing buildings. Following the SOC and as a consequence of a review of the Torbay site conducted by external advisers to the NHS Estates Design Panel, it was recognised that a cogent solution to this requirement was impossible to achieve given the fragmented nature of previous developments on this site. Consequently a wider review of the services provided on the site was undertaken which resulted in the recognition of the need for a more comprehensive development at Torbay, which reflected the objectives of the NHS Plan.
| 130 |
In carrying out this further evaluation it was also possible to include many of the items included in "Improvements to the Patient Environment" agenda, which had not been reflected in the original review.
| 42 |
The SOC at Newton Abbot had an allowance for the purchase of industrial land at a cost of £0.9 million which was subsequently rezoned and re-valued at £2.5 million.
| 1.6 |
Additionally, with the review of the services at Torbay it was recognised that a number of these services would be more appropriately located at Newton Abbot.
| 11.4 |
Total Increase since SOC | 185
|
Southampton | |
Change to scope of scheme as SOC is updated.
| |
Maidstone and Tumbridge Wells |
|
MIPS | |
|
Table 5.3.4
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
|
A | B | C
| D | E
| F |
Midlands and Eastern | Capital Cost at OBC Stage
| Capital Cost Reported Last Year
| Capital Value This Year |
% Increase Since OBC Stage |
% Increase Since Last Year |
| £m |
£m | £m
| | |
|
North Staffordshire | 224.0
| 269.0 | 308.0
| 37.5% | 14.5%
|
University Hospitals Birmingham | 291.0
| 379.3 | 440.1
| 51.2% | 16.0%
|
Peterborough Hospitals | 135.0
| 293.0 | 293.0
| 117.0% | 0.0%
|
Addenbrookes | 30.0
| 76.0 | 76.0
| 153.3% | 0.0%
|
Mid Essex hospitalsChelmsford | 80.0
| 110.0 | 121.0
| 51.3% | 10.0%
|
Essex Rivers HealthcareColchester |
79.0 | 127.0
| 139.0 | 75.9%
| 9.4% |
Sherwood Forest Hospitals | 66.0
| 125.0 | 147.4
| 123.3% | 17.9%
|
Southern Derbyshire Acute Hospitals | 177.0
| 312.2 | 312.2
| 76.4% | 0.0%
|
Nottinghamshire Healthcare | 13.9
| 18.7 | 19.4
| 39.6% | 3.7%
|
University Hospitals of Leicester | 286.0
| 403.0 | 447.0
| 56.3% | 10.9%
|
Daventry & South Northants PCT | 19.5
| 23.7 | 28.2
| 44.6% | 19.0%
|
Northampton PCT | 19.5
| 28.9 | 31.2
| 60.0% | 8.0%
|
South Holland Community Hospitals | 24.2
| N/A | 25.0
| 3.3% | N/A
|
Ipswich Hospital | 24.9
| N/A | 26.0
| 4.4% | N/A
|
Brentwood, Billericay & Wickford PCT |
20.0 | N/A
| 20.0 | 0.0%
| N/A |
South Essex Mental Health & Community |
17.0 | N/A
| 17.0 | 0.0%
| N/A |
Mid Essex hospitalsChelmsford | 16.8
| N/A | 16.8
| 0.0% | N/A
|
Epping Forest PCT | 10.0
| N/A | 13.4
| 34.0% | N/A
|
Derbyshire Mental Health | 31.6
| N/A | 31.6
| 0.0% | N/A
|
Witham & Braintree | 8.0
| N/A | 12.7
| 58.8% | N/A
|
Royal Wolverhampton | 110.0
| N/A | 312.0
| 183.6% | N/A
|
Walsall Hospitals | 43.0
| N/A | 127.0
| 195.3% | N/A
|
TOTAL MIDLANDS & EASTERN | 1,726.4
| 2,165.8 | 2,964.0
| | |
|
COMMENT ON ANY INCREASES OVER 10%
North Staffordshire Hospitals
Uplift from MIPS 345 to MIPS 385
Inclusion of expansion and education space.
University Hospitals Birmingham
Inclusion of new DCAGs for "improving the patient environment
agenda". Inclusion of 64 new beds and associated support.
Accommodation related to growth identified through the capacity
planning exercise.
Increase from MIPS 310 to MIPS 385
Addenbrookes
Inclusion of a genetics centrecapital cost £9
million. This was originally a separate scheme but has now been
merged with the larger scheme. Inclusion of new DCAGs for "improving
the patient environment". Inclusion of an integrated capital
development to be funded by the University of Cambridge and the
MRC (c£20 million)
Mid Essex Hospital
Inclusion of new DCAGs for "improving the patient environment";
70 extra beds and two additional theatres; removal of staff accommodation
element.
Peterborough
Inclusion of new DCAGs for "improving the patient environment".
Expansion of cancer, renal and neo-natal intensive care services.
Inclusion of £23.8 million Mental Health scheme.
Essex Rivers
Inclusion of new DCAGs for "improving patient experience",
indexation and incorporation of NHS Plan targets and revised activity
figures.
Sherwood Forest Hospitals
Inclusion of "improving the patient experience"
standards; expansion of services, including emergency care and
pathology; indexation.
Southern Derbyshire Acute
Inclusion of "improving the patient experience"
standards; inclusion of a new Medical School; modernisation of
maternity and gynae services; indexation.
Nottinghamshire Healthcare
Improvement of ICU facilities; additional office space; indexation.
Leicester
UHL Pathway project has increased by 56.3% since SOC approval.
This is due to a number of factors: the application of "improving
the patient environment" standards, inflation and the inclusion
of the reprovision of academic space due to be replaced within
the PFI.
Daventry and South Northants
Increase in capital cost due to inclusion of VAT, recalculation
of inflation allowance and additional costs related to Local Authority
planning requirements.
Northampton Healthcare
Revised models of care and "improving the patient environment.
Trust currently working with commissioners to reduce the impact
of changes to the original proposal.
Epping Forest
Inclusion of improving the patient experience.
Additional ward,outpatient/physiotherapy, free standing cafeteria,
creation of expansion space.
Whitham and Braintree
Inclusion of "improving the patient experience",
indexation and the inclusion of additional community services.
Wolverhampton
Return not received from SHA.
Walsall Hospitals
Increase to MIPS 385.
5.3.5 Could the Department provide an update of Tables
5.3.5, showing, for major projects (those greater than £25
million in value), a comparison between the PFI price and the
publicly financed option. The publicly financed comparator's costings
should be broken down as follows:
Basic construction contract, broken down between pre-implementation
and post implementation costs;
The value of risk adjustment, again broken down between
pre-implementation and post implementation costs, in both pounds
and percentage terms, and
The final total real full life cost of both options. [5.3.5]
1. The information requested is provided in the attached
tables.













5.3.6 Could the Department provide an update of Table
5.3.6? [5.3.6]
1. The information requested is provided in the attached
table.
|