Select Committee on International Development Memoranda


Memorandum submitted by the Department of International Development replying to questions raised by the Committee on the 2003/04 DFID spring supplementary estimate

Central Reserve

We understand that the Department is seeking two further transfers from the central reserve: £25,269,000 towards the Heavily Indebted Poor Countries (HIPC) programme and £6,500,000 towards Iraq Reconstruction. In addition to the £120,000,000 central reserve transfer in the Winter Estimate. Would you please confirm the basis upon which these central reserve resources have been transferred. Specifically, will DFID have to repay any of these amounts and will any offset against future resource allocations be required or is all this funding to be treated as additional to the original estimate for 2003-04?

The £25.269 million HIPC 100% call on the Central Reserve resulted from the financing arrangements for this initiative as set out in the Spending Review 2002 Settlement Letter. Under these arrangements, any spending in excess of £6.5 million per year in 2002-03 and 2003-04 was to be financed from the Reserve. The £26.269 million represented our best estimate of expenditure (in excess of the £6.5 million) for 2003-04. It was wholly additional to the original Estimate.

Under the Settlement arrangements, any unspent balance from this Supplementary will return to the Central Reserve. Treasury have however agreed in principle that if an under-spend is forthcoming a new Reserve claim may be submitted to the Chief Secretary to the Treasury for the remainder of the funds in 2004/05.

The call on the reserve for the £120 million in the Winter Supplementary and the £6.5m in the Spring Supplementary were both to finance humanitarian and reconstruction needs of Iraq. These allocations are additional to the original Estimate and will not be affected by any underspend on other allocations. We are confident that full disbursement of these funds will have occurred in 2003/04.

The Treasury have acknowledged that, as the £120 million Reserve claim was part of the £544 million UK commitment announced at Madrid, there is a strong case for DFID to carry over any unspent balances into 2004/05. Therefore, although we cannot roll any unspent funds forward, the Treasury have undertaken to consider whether, if there were an underspend, part or all of it could be returned to DFID by way of a separate Reserve claim in 2004/05.

Capital

We also understand that capital receipts are likely to be £8,400,000 less than expected and there is an overall increase of 39% in the capital budget (to £67,600,000). To fund this increase all the End Year Flexibility from 2001-02 has been drawn-down, together with a number of transfers from programme resources elsewhere in the estimate. Can further information be provided regarding what projects the additional capital funding is needed for, whether programme cuts suffered elsewhere to fund this additional spend and details of what caused the £8,400, 000 reduction in forecast capital receipts.

The revised estimate of £67.6m for Capital spending is made up of £33 million administration capital (an increase of £5m from the £28 million set out in the SR2002 Settlement Letter), £19 - £20 million of existing programme capital (consistent with previous estimates) and £15 million for a new capital item related to the European Development Fund (EDF). The EDF capital spend results from a technical adjustment whereby the part of our annual financing of the European Development Fund that is passed on to the European Investment Bank is now treated as Capital rather than Resource spend.

The forecast increase in Administration Capital expenditure was responding to the need for new offices to support expanding country programmes. In the event, there were slippages in capital expenditure and the latest figures for 2003/04 suggest that the final outturn for Administration Capital will be in the region of £29 - £30m.

The net transfer from Resource to Capital, excluding the £15m related to EDF, is £3.9m. This will be funded from anticipated resource under-spends and will not have an adverse affect upon individual programmes.

The 2003/04 Main Estimate figure for Appropriations-in-Aid of £37 million was based on the figure set out in the SR2002 Settlement Letter. Since that time we have revised downwards our forecasts of repayments of multilateral and bilateral loans. The £8.4m reduction is primarily due to the application of HIPC terms to loans formerly held by CDC.

May 2004


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 5 July 2004