Select Committee on Office of the Deputy Prime Minister: Housing, Planning, Local Government and the Regions Written Evidence


Supplementary Memorandum by the Office of the Deputy Prime Minister (DEC 01(a))

1.  INTRODUCTION

  1.1  In its Memorandum submitted to the Committee on 17 November ODPM indicated that it would submit a Supplementary Memorandum on the following issues:

    —  assessment of individual local authority (LA) performance; and

    —  achievements in the social sector.

2.  ASSESSMENT OF LA PERFORMANCE

  2.1  Since April 2002 Government Offices for the Regions (GORs) have provided quarterly reports on the performance of individual LAs in working towards delivery of the decent homes target. The reports provide information on barriers to delivery, planned work by the LA, planned work by the GOR, report on work that had been planned the previous quarter as well as an assessment of whether or not the LA was at risk of non-delivery of the target. The reasons for LAs being classed as at risk ranged from lack of a robust business plan to lack of resources and uncertainty about the outcome of a transfer ballot.

  2.2  The number of LAs classed as at risk changed with each quarterly report. At the last report on this basis (June 2003) 101 out of 256 LAs that had owned stock when the target was introduced were reported as at risk of non delivery. It is important to note that the degree of risk varies considerably—from LAs facing relatively minor challenges to those with substantial problems.

  2.3  A revised reporting system has now been introduced with the first reports giving the local authority position at end October 2003. The aim was to provide sharper performance assessments and to provide information on progress towards option appraisal sign-off (see section 7 of previous Memorandum).

  2.4  Assessment of individual LA performance is now based on a traffic light classification. Each LA is classed as Red, Amber/Red, Amber/Green or Green for both their ability to deliver the target by 2010 as well as their ability to reach option appraisal sign-off by July 2005. This revised reporting system is based on an informal assessment by Government Office and the Community Housing Task Force using whatever information they have available.

  2.5  The current position of the 256 LAs that owned stock at the baseline date of 1 April 2001 is given in Table 1. The broad equivalent to the "at risk" classification under the previous system is red and amber red. 100 authorities are assessed as being in these two categories in terms of their ability to meet the 2010 target. There are 113 authorities classed as red or amber-red in relation to option appraisal sign off, 87 of which are also red or amber-red on delivering by 2010.

Table 1

MATRIX OF OVERALL AND OPTION APPRAISAL SIGN OFF ASSESSMENTS


OA sign-off
assessment
Overall assessment
Total
RedAmber/Red Amber/GreenGreen


Red
82 0111
Amber/Red968 205102
Amber/Green36 71383
Green04 94760
Total2080 10056256



  2.6  The purpose of categorising authorities is so we can work with those at most risk of not meeting the target and those who need support with option appraisals to help them develop solutions that will deliver decent homes to their tenants. This list of authorities in each category therefore changes over time as authorities put effective strategies in place that, when implemented, will result in delivery.

3.  ASSESSMENT OF RSL PERFORMANCE

  3.1  The Housing Corporation is developing a risk register for RSLs. The Corporation's asset management database is enabling regulators to identify those RSLs at risk of failing to meet the target and they will work with them to ensure they have plans and adequate resources to tackle the problem. This may include targeting major repairs grant on the most acute cases. The risk register will be ready by the end of the year.

4.  ACHIEVEMENTS IN THE SOCIAL SECTOR

  4.1  On the basis of the most recent LA and RSL data (their returns for 2002-03) it would appear that:

    —  between April 2001 and March 2004 the number of non-decent properties will have been reduced by around 500,000;

    —  the total reduction in non-decent properties since 1997 will be nearly 1 million by March 2004; and

    —  we will achieve the milestone of reducing the April 2001 number of non-decent properties by a third in the course of 2004, a few months later than the original date of March 2004.

  4.2  Initial analysis indicates there are two main reasons why progress has been slower than anticipated:

    —  in 2002-03 local authorities spent 6% less (£150 million) on delivering decent homes than indicated in their plans for the year; and

    —  some local authorities have increased their estimation of the problem, making the target more difficult to achieve.

  4.3  Work is in hand to understand why this is the case and the implications this might have for the achievement of the 2010 decent homes target. In particular we need to understand:

    —  the extent to which the shortfall will be compensated for by higher figures than now forecast for 2004-05;

    —  how far the decision to apply for a programme that brings in additional funding delays existing plans for reducing numbers of non decent homes;

    —  the extent to which the figures for 2002-03 are lower than expected because LAs arrange their work programmes to tackle building elements one at a time eg windows first, bathroom next then roof repairs etc—with the consequence that the homes do not become decent until all the programmes are complete;

    —  how changes to procurement practice have taken longer than planned reducing the amount of work commissioned during the year; and

    —  whether some LAs have misinterpreted the target and their estimate of the proportion of the stock that is non decent.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 7 May 2004