Select Committee on Procedure First Report


Annex B: Supply and Appropriation Process: Response to issues raised by Parliamentary Committees

Responses to the letter of 13 November from the Liaison Committee:

That House of Commons Standing Order No. 55 be amended to extend the time that must elapse between presentation of the Estimates and the ensuing vote to authorise spending from 7 clear days to 14 days.

I understand the benefits that this would bring by providing Select Committees with more time to analyse the Estimates in advance of the Parliamentary vote. This is, as you say, also consistent with the 14-day target set out in Government Accounting.

This does bring some additional risks (such as the greater risk of parliamentary time being taken up by a debatable motion on the floor of the House in order to allow any late or revised Supplementary Estimates not meeting the deadline to be dealt with at the same time). However, on balance, the benefits clearly outweigh these risks and I support the proposal to amend Standing Order No. 55.

You ask what further guidance the Treasury will give to departments to ensure that they do not submit unrealistically low Estimates at the beginning of the year and then leave the request for additional resources until the spring Supplementary Estimates.

You note that Government Accounting already makes clear to departments their responsibilities to produce Estimates that are "taut and realistic". I have asked officials to ensure that this message is emphasised in our Public Spending Guidance (web based guidance material available to departments) and the next Public Expenditure System papers covering the Supply Estimates.

However, we do need to be careful to balance an emphasis of the requirement for departments to include in their Estimates all spending pressures that they expect to lead to an increase in resources with an acknowledgement that departments should not seek additional resources until it is clear that the pressures cannot be absorbed through savings in other areas. Not unrelated to this, and also set out in Government Accounting, is the requirement that Estimates must also be consistent with the Government's spending plans (eg, additional DEL pressures must be absorbed within agreed limits).

You also ask about the expenditure monitoring systems departments have in place. This is an area that departments have been developing extensively, with encouragement and guidance from Treasury and the NAO, since the move to resource accounting and budgeting. Despite this, it is perhaps inevitable that forecasting non-cash spending requirements is more difficult than forecasting cash requirements and late changes are always going to be more likely than they were under a cash based regime.

The Treasury should produce a template for use by departments when drafting the introductory section explaining what the Estimate is doing.

I fully endorse this suggestion. We want to ensure that Introductions are helpful and informative but without placing any unnecessary additional burden on departments. To this end we must ensure that it does not unnecessarily duplicate information already provided elsewhere. The main purpose of the Introduction should be to identify the changes taking place and how any increases are being financed (eg, in budgetary terms).

What I would like to avoid, of course, is unnecessary repetition of information between this, the body of the Estimate and the proposed "Estimate Memorandum". I see the Introduction as providing an outline summary of movements in the various budgetary and parliamentary limits, whereas any "Estimate Memorandum" could be used to provide the background detail in respect of such changes.

A draft template is attached at the Appendix. The template sets out the required format and content, where relevant, for each Introduction. Use of such a template should not generally be required for the Introduction to Main Estimates, since this simply sets out the department's starting position.

If the Committees are content, the Treasury will issue the template to departments for use from 2004-05 onwards.

An additional Note to the Estimates should summarise the position on DEL end-year flexibility (how much is being drawn down and how much remains

As you know, the Notes to the Estimates already contain a "DEL and administration cost limit" note. Rather than adding a further note, this could, if necessary, be revised to include information on how much EYF the department is taking up in the Estimate and how much is left. However, the new template for the Introduction would identify draw down of EYF in the Estimate and, to set out the wider EYE position, departments could use the proposed "Estimate Memorandum". I would suggest that this is preferable to adding another note to the Estimates, particularly since this would only apply where relevant and may require a degree of explanation about voted and non-voted splits or the type of EYF available (administration, programme, etc).

Each department should produce an "Estimate Memorandum" for its Select Committee. This would explain the consequences of the Estimate and how this links to departmental targets. etc.

This could represent a significant additional reporting requirement for departments, though I acknowledge the potential benefits it would bring in helping Select Committees to follow the spending plans implied by the departmental Estimate and the link to published targets.

I can support this suggestion but should like to propose that Treasury guidance to departments, including Government Accounting when next revised, include the following provisions:

A similar Memorandum should be produced by departments that are not seeking a Supplementary Estimate but are, with Treasury approval, switching spending within voted limits.

Government Accounting already sets out criteria under which the Treasury can agree virement within an Estimate. This allows switches of resources only where the spending is, for example, not large in relation to the sections concerned, does not arise from a major change of policy, and is neither novel nor contentious. Since such virement is limited in this way, and often takes place after the year-end, it is unlikely to be of significant interest to many Select Committees.

However, I am content that any guidance relating to the "Estimate Memorandum" dealt with above should also set out the requirement for a similar memorandum in these circumstances where this has been agreed between the department and its Select Committee. If you accept my proposals relating to the "Estimate Memorandum" above, such a memorandum would also be submitted to the Select Committee where there are DEL changes to report even when no Supplementary Estimate is required.

Responses to the further letter, of 24 November, jointly from the Public Accounts and Treasury Committees:

A request for information on what measures are, or will be, in place to ensure that departments meet the July 2005 deadline for closure of the 2004-05 resource accounts, and the planned timetable for 2003-04 accounts.

As mentioned in my 30 September letter, the aim is for departments to have their resource accounts signed, certified and laid before the summer recess by 2005-06—in other words, for the 2005-06 accounts to be published by July 2006. Departments will use the intervening years leading up to 2005-06 to advance their own timetables in order to achieve the July 2006 deadline.

Departments are, of course, at very different stages of progress towards achieving this. Nine departments succeeded in laying and publishing their 2002-03 accounts before the summer recess this year. Most departments are showing an improvement—in some cases significant—compared with their 2001-02 accounts. The Treasury is working closely with the National Audit Office and departments to ensure that further improvements are made for the 2003-04 accounts.

Detailed guidance on accelerated closure was set out in the "Mauve Guide" in the Managing Resources series "Faster closing" (copies attached). The Guide explains the benefits to departments and others (including Parliament) of faster closing, and how the barriers can be overcome. It also sets out 10 ways in which departments can help smooth progress towards faster closure, working closely in partnership with the NAO. This message has been reinforced at various conferences and seminars with departments.

Whether the proposals relating to Machinery of Government changes would involve backdating changes to the start of the financial year.

Machinery of Government changes are currently treated as mergers in both resource accounts and Estimates. This means that where a transfer takes place mid-year responsibility for spending in relation to the transferred activity lies with the receiving department in respect of the whole financial year. The suggested changes, to allow the Estimate of the transferring department to show a reduction in resources and cash following the transfer, will not affect this position.

Allowing "negative Estimates" (ie Estimates seeking a reduction in already voted limits) to be extended to cover not only Machinery of Government changes but also to other changes, such as switches of provision between RfRs in an Estimate.

I support this suggestion. My initial proposal restricted the use of negative Estimates to Machinery of Government changes because this is where the current rules cause greatest difficulty, and the process of adjusting Estimates is straight-forward, with completely off-setting movements between Estimates. However, there would certainly be benefits in extending this proposal to cover situations where a department is reducing spending in one RfR in order to finance additional spending in another. There would be no overall reduction in resources or cash voted in the departmental Estimate. If these were the only changes taking place in the Estimate the department would need to ensure that a token increase in resources of £1,000 remained to be voted by Parliament.

I suggest that the use of "negative" Estimates (or RfRs) is limited to these specific circumstances, at least for the present. To move to a position where voted limits on departmental spending might be reduced overall would need careful consideration. There would possibly be legal and procedural issues to address.

Appendix: Draft Template for introductory section of Estimate

Supplementary Estimate 200X-0X  [Department Name]

[Department Name]  

Introduction

1. This Supplementary Estimate is required for the following purposes:

RfR1: [RfR title, replicated in full]

Increases (excluding Token Estimates):

1. Type (e.g. administration costs, programme)

    {amount

    {section(s)

    {reason

2. Etc

  • Transfers from Central Funds

1. Type (e.g. Invest to Save Budget, Capital Modernisation Fund)

    {amount

    {section(s)

    {reason

  • Transfers from non-voted spending

1. Type (e.g. Departmental Unallocated Provision (DUP))

    {amount

    {section(s)

    {reason

  • Transfers from other government departments

1. Type (e.g. Machinery of Government change)

    {amount

    {section(s)

    {reason

  • Other increases

1. Type (e.g. DEL Reserve claims, Classification changes, transfer from another RfR)

    {amount

    {section(s)

    {reason

Decreases:

  • Transfers to non-voted spending

1. Type (e.g. Non-Departmental Public Bodies)

    {amount

    {section(s)

    {reason

  • Transfers to other government departments

1. Type (e.g. Machinery of Government change)

    {amount

    {section(s)

    {reason

  • Other decreases

1. Type (e.g. Classification changes, transfer to another RfR)

    {amount

    {section(s)

    {reason

Neutral changes (including Token Estimates):

  • Increased spending offset by income

  1.  {amount

    {section(s)

    {reason

  • Token Estimates

1. Type (e.g. Ambit change, change to type of income)

    {amount

    {section(s)

    {reason

  • Transfers within the RfR

  1.  {amount

    {section(s)

    {reason

[RfR 2: etc]

2. As a result of these changes, there is [an increase/a reduction] in the Net Cash Requirement of [£xxx,xxx,xxx].

3. Symbols are explained in the Introduction to this booklet.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 3 March 2004