Responses to the letter of 13
November from the Liaison Committee:
That House of Commons Standing Order No. 55 be
amended to extend the time that must elapse between presentation
of the Estimates and the ensuing vote to authorise spending from
7 clear days to 14 days.
I understand the benefits that this would bring by
providing Select Committees with more time to analyse the Estimates
in advance of the Parliamentary vote. This is, as you say, also
consistent with the 14-day target set out in Government Accounting.
This does bring some additional risks (such as the
greater risk of parliamentary time being taken up by a debatable
motion on the floor of the House in order to allow any late or
revised Supplementary Estimates not meeting the deadline to be
dealt with at the same time). However, on balance, the benefits
clearly outweigh these risks and I support the proposal to amend
Standing Order No. 55.
You ask what further guidance the Treasury will
give to departments to ensure that they do not submit unrealistically
low Estimates at the beginning of the year and then leave the
request for additional resources until the spring Supplementary
Estimates.
You note that Government Accounting already
makes clear to departments their responsibilities to produce Estimates
that are "taut and realistic". I have asked officials
to ensure that this message is emphasised in our Public Spending
Guidance (web based guidance material available to departments)
and the next Public Expenditure System papers covering the Supply
Estimates.
However, we do need to be careful to balance an emphasis
of the requirement for departments to include in their Estimates
all spending pressures that they expect to lead to an increase
in resources with an acknowledgement that departments should not
seek additional resources until it is clear that the pressures
cannot be absorbed through savings in other areas. Not unrelated
to this, and also set out in Government Accounting, is
the requirement that Estimates must also be consistent with the
Government's spending plans (eg, additional DEL pressures must
be absorbed within agreed limits).
You also ask about the expenditure monitoring systems
departments have in place. This is an area that departments have
been developing extensively, with encouragement and guidance from
Treasury and the NAO, since the move to resource accounting and
budgeting. Despite this, it is perhaps inevitable that forecasting
non-cash spending requirements is more difficult than forecasting
cash requirements and late changes are always going to be more
likely than they were under a cash based regime.
The Treasury should produce a template for use
by departments when drafting the introductory section explaining
what the Estimate is doing.
I fully endorse this suggestion. We want to ensure
that Introductions are helpful and informative but without placing
any unnecessary additional burden on departments. To this end
we must ensure that it
does not unnecessarily duplicate
information already provided elsewhere. The main purpose of the
Introduction should be to identify the changes taking place and
how any increases are being financed (eg, in budgetary terms).
What I would like to avoid, of course, is unnecessary
repetition of information between this, the body of the Estimate
and the proposed "Estimate Memorandum". I see the Introduction
as providing an outline summary of movements in the various budgetary
and parliamentary limits, whereas any "Estimate Memorandum"
could be used to provide the background detail in respect of such
changes.
A draft template is attached at the Appendix. The
template sets out the required format and content, where relevant,
for each Introduction. Use of such a template should not generally
be required for the Introduction to Main Estimates, since this
simply sets out the department's starting position.
If the Committees are content, the Treasury will
issue the template to departments for use from 2004-05 onwards.
An additional Note to the Estimates should summarise
the position on DEL end-year flexibility (how much is being drawn
down and how much remains
As you know, the Notes to the Estimates already contain
a "DEL and administration cost limit" note. Rather than
adding a further note, this could, if necessary, be revised to
include information on how much EYF the department is taking up
in the Estimate and how much is left. However, the new template
for the Introduction would identify draw down of EYF in the Estimate
and, to set out the wider EYE position, departments could use
the proposed "Estimate Memorandum". I would suggest
that this is preferable to adding another note to the Estimates,
particularly since this would only apply where relevant and may
require a degree of explanation about voted and non-voted splits
or the type of EYF available (administration, programme, etc).
Each department should produce an "Estimate
Memorandum" for its Select Committee. This would explain
the consequences of the Estimate and how this links to departmental
targets. etc.
This could represent a significant additional reporting
requirement for departments, though I acknowledge the potential
benefits it would bring in helping Select Committees to follow
the spending plans implied by the departmental Estimate and the
link to published targets.
I can support this suggestion but should like to
propose that Treasury guidance to departments, including Government
Accounting when next revised, include the following provisions:
- The memorandum should not duplicate
reporting requirements and should replace certain existing requirements,
in particular:
- Notification to Parliament
of DEL changes, which departments currently make through written
statements, would in future be included in such memoranda, replacing
the need for written statements;
- The proposed template for the Introduction to
each Estimate should limit the detail to the changes to the various
control limits (Treasury and parliamentary). Any detailed explanation
of the reasons for these changes, how they are funded, etc, would
be included in the memorandum;
- Your suggestion of a new Note to the Estimates
relating to the department's DEL EYF position would be replaced
by the provision of such information in the Introduction (how
much is being taken-up) and the memorandum (what it is being used
for and how much is left).
- Beyond the above requirements,
the detail of what was included in each memorandum would be a
matter for agreement between each department and its Select Committee.
A similar Memorandum should be produced by departments
that are not seeking a Supplementary Estimate but are, with Treasury
approval, switching spending within voted limits.
Government Accounting
already sets out criteria under which the Treasury can agree virement
within an Estimate. This allows switches of resources only where
the spending is, for example, not large in relation to the sections
concerned, does not arise from a major change of policy, and is
neither novel nor contentious. Since such virement is limited
in this way, and often takes place after the year-end, it is unlikely
to be of significant interest to many Select Committees.
However, I am content that any guidance relating
to the "Estimate Memorandum" dealt with above should
also set out the requirement for a similar memorandum in these
circumstances where this has been agreed between the department
and its Select Committee. If you accept my proposals relating
to the "Estimate Memorandum" above, such a memorandum
would also be submitted to the Select Committee where there are
DEL changes to report even when no Supplementary Estimate is required.
Responses to the further letter,
of 24 November, jointly from the Public Accounts and Treasury
Committees:
A request for information on what measures are,
or will be, in place to ensure that departments meet the July
2005 deadline for closure of the 2004-05 resource accounts, and
the planned timetable for 2003-04 accounts.
As mentioned in my 30 September letter, the aim is
for departments to have their resource accounts signed, certified
and laid before the summer recess by 2005-06in other words,
for the 2005-06 accounts to be published by July 2006. Departments
will use the intervening years leading up to 2005-06 to advance
their own timetables in order to achieve the July 2006 deadline.
Departments are, of course, at very different stages
of progress towards achieving this. Nine departments succeeded
in laying and publishing their 2002-03 accounts before the summer
recess this year. Most departments are showing an improvementin
some cases significantcompared with their 2001-02 accounts.
The Treasury is working closely with the National Audit Office
and departments to ensure that further improvements are made for
the 2003-04 accounts.
Detailed guidance on accelerated closure was set
out in the "Mauve Guide" in the Managing Resources series
"Faster closing" (copies
attached). The Guide explains the benefits to departments and
others (including Parliament) of faster closing, and how the barriers
can be overcome. It also sets out 10 ways in which departments
can help smooth progress towards faster closure, working closely
in partnership with the NAO. This message has been reinforced
at various conferences and seminars with departments.
Whether the proposals relating to Machinery of
Government changes would involve backdating changes to the start
of the financial year.
Machinery of Government changes are currently treated
as mergers in both resource accounts and Estimates. This means
that where a transfer takes place mid-year responsibility for
spending in relation to the transferred activity lies with the
receiving department in respect of the whole financial year. The
suggested changes, to allow the Estimate of the transferring department
to show a reduction in resources and cash following the transfer,
will not affect this position.
Allowing "negative Estimates" (ie Estimates
seeking a reduction in already voted limits) to be extended to
cover not only Machinery of Government changes but also to other
changes, such as switches of provision between RfRs in an Estimate.
I support this suggestion. My initial proposal restricted
the use of negative Estimates to Machinery of Government changes
because this is where the current rules cause greatest difficulty,
and the process of adjusting Estimates is straight-forward, with
completely off-setting movements between Estimates. However, there
would certainly be benefits in extending this proposal to cover
situations where a department is reducing spending in one RfR
in order to finance additional spending in another. There would
be no overall reduction in resources or cash voted in the departmental
Estimate. If these were the only changes taking place in the Estimate
the department would need to ensure that a token increase in resources
of £1,000 remained to be voted by Parliament.
I suggest that the use of "negative" Estimates
(or RfRs) is limited to these specific circumstances, at least
for the present. To move to a position where voted limits on departmental
spending might be reduced overall would need careful consideration.
There would possibly be legal and procedural issues to address.
Appendix: Draft Template for introductory
section of Estimate
Supplementary
Estimate 200X-0X [Department Name]
[Department
Name]
Introduction
1. This Supplementary
Estimate is required for the following purposes:
RfR1: [RfR title,
replicated in full]
Increases (excluding
Token Estimates):
- Take up of
End-Year Flexibility
1. Type (e.g. administration
costs, programme)
{amount
{section(s)
{reason
2. Etc
- Transfers
from Central Funds
1. Type (e.g. Invest
to Save Budget, Capital Modernisation Fund)
{amount
{section(s)
{reason
- Transfers
from non-voted spending
1. Type (e.g. Departmental
Unallocated Provision (DUP))
{amount
{section(s)
{reason
- Transfers
from other government departments
1. Type (e.g. Machinery
of Government change)
{amount
{section(s)
{reason
1. Type (e.g. DEL
Reserve claims, Classification changes, transfer from another
RfR)
{amount
{section(s)
{reason
Decreases:
- Transfers
to non-voted spending
1. Type (e.g. Non-Departmental
Public Bodies)
{amount
{section(s)
{reason
- Transfers
to other government departments
1. Type (e.g. Machinery
of Government change)
{amount
{section(s)
{reason
1. Type (e.g. Classification
changes, transfer to another RfR)
{amount
{section(s)
{reason
Neutral changes
(including Token Estimates):
- Increased
spending offset by income
1. {amount
{section(s)
{reason
1. Type (e.g. Ambit
change, change to type of income)
{amount
{section(s)
{reason
1. {amount
{section(s)
{reason
[RfR 2: etc]
2. As a result of
these changes, there is [an increase/a reduction] in the Net Cash
Requirement of [£xxx,xxx,xxx].
3. Symbols are explained
in the Introduction to this booklet.