Select Committee on Public Accounts Twenty-Fourth Report


1 The implementation of the e-programme

1. In 2001 Customs began a ten year e-programme to transform its business mainly through electronic service delivery. While continuing to offer paper-based systems Customs has Public Service Agreement targets to deliver 100% of its services electronically by 2005 and achieve 50% take up by March 2006. This is Customs' contribution to the wider Government agenda to make all departmental services available online by 2005 with key services achieving high levels of use. The e-programme is aimed at achieving these targets and further improvements in performance and capability in the longer term. At the end of 2003 around 80% of Customs' services were available electronically and over half of all transactions with customers were completed electronically but take-up of e-VAT was very low.[3]

2. The aims of the e-programme are to increase revenue and improve efficiency by using new ways of working and new integrated IT systems, including a new website, to deliver a wider range of services electronically. It also involves replacing existing IT systems, which are nearing the end of their operational life. Customs has made good progress on some parts of the e-programme but it needs to improve its business case and benefits realisation plans (Figure 1).[4]

Figure 1: Customs' progress in taking forward the e-programme



Source: C&AG's Report, p10

3. Customs estimates that the programme will cost over £300 million over the ten-year period. In return Customs expects to achieve increased revenue of £500 million a year by the end of the period by producing better information and analysis to target resources more effectively on tax compliance and anti-smuggling activities, in addition to the £2.7 billion extra revenue expected by 2005-06 from implementing its VAT strategy. Customs also expects the e-programme to deliver £130 million in efficiency savings from redeploying staff from processing jobs into other parts of the department, and to reduce compliance costs for businesses. Since 2001 Customs has undertaken extensive planning and spent over £100 million on the programme.[5]

4. The main risk for Customs is that the significant expenditure on the e-programme does not generate the expected benefits in service delivery, increased revenue collection and improved efficiency. Private sector and international comparisons show that it can take a long time to secure a positive return on investments in e-services. For example Canada, although accepted as a leader in the implementation of e-government, had found that e-services have not generated any major cost savings to date.[6]

5. Our Report on e-Revenue in February 2002 concluded that the drive to meet 2005 e-government targets should not compromise the need to develop rigorous business cases for each service and the overall e-strategy. Customs developed an outline business case in October 2002 estimating the financial benefits of the e-programme at £4 billion but this was not a rigorous estimate. Customs then reduced it to £1.2 billion in November 2003. As a result the expected return on investment fell from 12:1 to between 4:1and 3:1. It has yet to complete a detailed analysis of the costs and benefits and needed to revisit the estimated cost of the e-programme in the light of contractual amendments to the PFI contract with Fujitsu.[7]

6. On the basis of the latest figures, Customs expects the e-programme to break even by 2007 (Figure 2). This date could be delayed, however, because benefits may come on stream later than Customs expects or costs could prove to be greater than the original estimate of £327 million. Customs planned to complete a full business case by March 2004 which would take account of all the costs of the e-programme, including IT development and business changes.[8]



7. Customs' IT projects go through the Office of Government Commerce's gateway reviews and it will not go live with an application if a gateway review indicates a major problem. In implementing initial stages of the e-programme, however, Customs had not followed good practice as recommended by Treasury in the following areas.[9]

  • Sensitivity analysis should be used to test the vulnerability of options to unavoidable uncertainties. Customs did not subject the estimated financial benefits in its outline business case to sensitivity analysis to show, for example, the effect of variations in take-up levels. Customs proposes to undertake such analysis for the full business case, which will be subject to Treasury review.[10]
  • There should be proper management of consultants. Customs spent nearly £28 million on 300 consultants for the e-programme between November 2001 and March 2003. Consultants were engaged and contracts extended with insufficient evidence to assess their performance or to support the need for the services they were to provide. Following an internal review, Customs has reduced the number of consultants to 130 and strengthened management controls.[11]
  • High risk and important projects should have clearly identified senior responsible owners. Customs assigned this responsibility for each sub-programme but did not appoint an overall senior responsible owner for the e-programme until May 2003.[12]

8. In a programme of this scale contingency planning is particularly important. Customs has procedures for measuring risk at project level and some short-term contingency plans. But there is no contingency plan for the e-programme as a whole to cover, for example, the risks of breakdowns in service. As part of the PFI contract with Fujitsu, Customs has begun to develop recovery plans for each site and critical service, which will be subject to annual review.[13]


3   Q 40; C&AG's Report, Executive Summary paras 1, 2 and Report, para 1.6  Back

4   C&AG's Report, para 1.4 Back

5   Qq 53, 55-56, 61, 65-66, 101; C&AG's Report, Preface, para 1.11 and Figure 7, p15 Back

6   Qq 104-107; C&AG's Report, para 1.13 Back

7   Qq 113-114; 52nd Report from the Committee of Public Accounts, E-Revenue (HC 707, Session 2001-02); C&AG's Report, paras 1.11-1.12, 2.7 Back

8   Qq 2-4 ; C&AG's Report, paras 1.11-1.12 Back

9   Qq 26-39 Back

10   Qq 23, 25; C&AG's Report, para 2.7; The Green Book: Appraisal and evaluation in Central Government, HM Treasury, 2003 Back

11   Qq 8, 11-18 Back

12   Qq 10, 25; C&AG's Report, para 2.12; Delivering success in Government IT-enabled projects & programmes, HM Treasury, 2003, p2 Back

13   Q 111; C&AG's Report, Executive Summary para 18 and Appendix 3, para 43  Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 22 June 2004