Select Committee on Public Accounts Twenty-Fourth Report


3 The Private Finance Initiative contract with Fujitsu

15. The Department's IT infrastructure was taken over by ICL (now Fujitsu) from April 2000 under a Private Finance Initiative (PFI) contract. This contract is for IT infrastructure services only; development of electronic services is done in-house, with external partners if necessary.[20]

16. The whole life cost of the 10 year contract when it was originally let was £500 million (with an estimated net present value of £398.2 million). By 2003 the cost had risen to £680 million. This was due partly to an increase in the number of Departmental staff user from 18,000 to 22,000 and partly due to new or enhanced information systems and services, such as the national co-ordination unit. This unit gathers and disseminates intelligence information to Customs staff to help target their operations.[21]

17. Customs found it increasingly difficult under the contract to make changes to the IT infrastructure. The original contract contained some flexibility but Customs had not foreseen the extent of the changes needed for the e-programme. With assistance from Rothschild, Customs compared the value for money of amending the contract to cope with changes needed with the option of terminating the contract and re-tendering. They found that the termination route was marginally better in cost benefit terms, but would put at risk £508 million of existing revenue and a further £472 million from a two year delay in delivering the benefits of the e-programme. Customs therefore decided not to retender.[22]

18. The contract amendments agreed in August 2003 increased the net present value of the 10 year contract to £631 million and the whole life cost to £929 million. All the increase in costs was for additional or enhanced services. Customs does not expect further significant amendments but does not rule out changes to deal with, for example, new services.[23]

19. In July 2003 the Chancellor announced a major review of the organisations dealing with tax policy and administration (Customs and Inland Revenue) chaired by the Permanent Secretary to the Treasury, Gus O'Donnell. The primary purpose of the review was to make public service delivery more effective and efficient, examining ways to enhance service delivery through closer working or organisational change. At the time of our examination the review had not reported. Customs considered that the review might affect Customs' IT needs but that its IT infrastructure could, if necessary, be connected to the Inland Revenue's systems at no significant additional costs. However, if the review led to the breaking up of current service provision under the PFI contract, Customs might have to reach a negotiated settlement with Fujitsu. The review, Financial Britain's Future - Review of the Revenue Departments, published in March 2004 announced the creation of a new department integrating the work of Customs and Inland Revenue. It found that the differences in IT provision should not present a barrier to the integration of the departments. But management would need to consider their IT strategy including the need to harmonise provision, to identify the model that will best serve business needs and ensure a collaborative approach to resolving any issues that arise bringing in IT partners promptly.[24]

20. Since Customs entered into the contract with Fujitsu, the Treasury has issued revised guidance on managing major IT projects and the use of PFI. New procedures introduced in February 2003 permit departments to authorise only modular, incremental IT developments and implementations. 'Big bang' projects have to be approved by a central scrutiny authority. In July 2003 the Government announced that there would be a presumption against future IT projects using PFI which would be replaced by a range of procurement models. This was because PFI deals for IT, unlike construction, had not led to a step change in performance; were unlikely to attract third party finance and had not coped well with rapid technological change.[25]

21. In December 2003 the Office of Government Commerce issued a consultation document on guidance to help departments decide the best strategy for the procurement of IT. The guidance outlined three broad strategies. The guidance notes that the more stable the technology, the more likely it is that long-term contracts using a partnering or output specification approach will be appropriate. More innovative projects, however, are likely to have a better chance of success with short, small, input-based contracts, thereby minimising costs if the innovation does not work. This guidance, when finalised, may also help departments in selecting the appropriate procurement strategy when new services or major changes are needed in an existing PFI contract.[26]


20   C&AG's Report, Executive Summary, para 13 and Report, para 2.18 Back

21   Qq 43-44, 72-73, 76, 82; C&AG's Report, Executive Summary, para 13 and Report, para 2.18 Back

22   Qq 9, 42-43; C&AG's Report, paras 2.18-2.19, 2.21 Back

23   Qq 71, 112; C&AG's Report, para 2.22 Back

24   C&AG's Report, para 2.23; Financing Britain's Future - Review of the Revenue Departments (Cm 6163), March 2004 Back

25   Qq 122-123, 129-130; Ev 13-15; PFI: meeting the investment challenge, HM Treasury, July 2003; Delivering success in Government IT-enabled projects & programmes, DAO (GEN) 01/03 Back

26   Q 123; Decision map for procurement and accompanying guidance for IT contracting, Office of Government Commerce, December 2003 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 22 June 2004