Select Committee on Public Accounts Forty-Third Report


3 Building open and honest relationships with industry

14. The Defence Industrial Policy published in October 2002 recognised that the Department and its main suppliers are in a long-term mutually dependent relationship. The Policy states that a thriving, innovative and competitive defence industry is essential to provide the Armed Forces with the equipment which they require, on time, and at best value for money for the taxpayer.[25] The Department considers that its relationships with industry are generally good, although there have recently been well publicised tensions with parts of BAE Systems,[26] with which the Department has contracts worth some £37-38 billion.[27]

15. The Chief Executive of BAE Systems told us that his company had made the wrong strategic decision to accept the Nimrod contract in the mid-1990's. At the time, the Board had been convinced by a presentation made by the programme management team who assured them that it would be a profitable contract.[28] As recent experience on the Support Vehicle programme highlights, a similar culture exists within the Department, and has led to short term decision-making and over-optimism in estimating costs and timescales on many projects. There are few examples where a judgement has been made not to proceed with a project, although the decision not to procure an acoustic sonar buoy for the Nimrod after estimates of the cost of the programme had tripled does provide an isolated example.[29]

16. Following the publication of the Major Projects Report 2003, Sir Raymond Lygo, Chief Executive of British Aerospace during the 1980's, said that the company consistently underbid for contracts knowing that it could recover the true costs when the project was underway. This is a very serious charge and a practice which we would view as completely unacceptable if it were shown to be happening. Mike Turner, the current Chief Executive of BAE Systems, stated categorically that the company did not knowingly underbid for contracts. Sir Kevin Tebbit added that, even if underbidding had been prevalent during the era of cost plus contracting 20 years ago, the Department now had a sophisticated system to understand the price base of bids, and said he was absolutely certain that underbidding was not taking place today.[30] We will want to be satisfied of the continuing effectiveness of this system as we consider future equipment acquisitions by the Department.

17. The Defence Industrial Policy states that "the Government is responsible for providing the Armed Forces with high quality equipment at best value for money for the taxpayer. It is also firmly committed to the UK manufacturing sector, and to promoting a strong and competitive UK defence industry, bringing economic and technological benefits to the nation. The Government must take decisions within a policy framework that recognises any tensions between these two objectives." The July 2003 decision to purchase up to 44 Hawk 128 aircraft from BAE Systems to meet the requirement for an Advanced Jet Trainer provides a good illustration of these tensions.

18. The Accounting Officer's analysis of the case for procuring the Hawk 128 took into account industrial capacity and employment arguments, but because of issues about the timing of the order, and on the grounds that an international competition would offer the most likely prospect of a value for money solution, he sought a Direction from the Secretary of State for Defence to proceed.[31] In his evidence the Chief Executive of BAE Systems noted that BAE Systems would be making only a 7% return on the project, and argued that the Department adopted a very narrow definition of value-for-money which failed to take account of exports, wealth creation and the defence industrial base.[32]

19. When the contracts for the Astute submarine and Nimrod aircraft were placed in the mid-1990s the Department considered that the best way of delivering the capability was by putting responsibility for managing risks in the programme, as well as in delivering the programme, on to a prime contractor. On these two programmes the approach failed. The Department is going without equipments they need, BAE Systems has lost £1 billion on the deals,[33] the Department will have to contribute an extra £1.5 billion and will receive three fewer Nimrod aircraft (worth £180 million) than planned.[34] The Department now believes that there is a limit to which it can transfer financial risk and that operational or time risk cannot be transferred.[35] The Defence Industrial Policy therefore states that "we will seek to provide a more appropriate risk/reward ratio for programmes with high technological risk".

20. The Astute submarine and Nimrod aircraft contracts were placed with fixed price contracts covering both development and production. The Department and BAE Systems disagree on what the best pricing mechanism is for highly complex technology programmes where there is excessive risk. BAE Systems favours cost plus arrangements. The Department considers there are more robust arrangements which would protect the taxpayer as well as be fair to the supplier.[36] Figure 4 illustrates how the various pricing options available may be better suited to particular combinations of risk and certainty of outcome. Using a variety of pricing methods should allow the Department and industry to achieve a fairer risk and reward balance appropriate to the circumstances of an individual programme. For example, a fixed or firm price may be more suitable for production work once the design is stable than for most early risk reduction work.[37]Figure 4: Alternative pricing mechanisms


Notes

Cost plus: Where a contractor is paid his agreed costs plus an agreed profit rate.

Target cost with maximum price: A target cost is established together with an arrangement to share the amount by which actual costs are above or below the target between the Department and the contractor. There is a maximum price above which the contractor has to bear all the costs.

Fixed price: An agreed price that is subject to variation to take account of inflationary and/or exchange rate movements.

Firm price: An agreed price that is not subject to variation for inflation.


25   Ministry of Defence Paper 5, Defence Industrial Policy Back

26   Qq 191-192, 281 Back

27   Q 42 Back

28   Qq 28-30 Back

29   Q 90 Back

30   Qq 9-11 Back

31   Qq 12-14  Back

32   Q 15  Back

33   Qq 29-32 Back

34   Qq 28-42 Back

35   Qq 23-24 Back

36   Qq 105-107, 140, 152-155 Back

37   Qq 5, 59, 66, 73 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 21 October 2004