Select Committee on Public Accounts Fourteenth Report


1  Problems with the new Tax Credit system

1. The Government introduced Child Tax Credit and Working Tax Credit for payment from April 2003 and received some 4.5 million applications by the end of June 2003. These two tax credits are expected to cost some £16 billion per year. The Department's IT service provider, EDS, created a new IT system for processing the new tax credits. It links to other Inland Revenue databases and exchanges data electronically with the Department for Work and Pensions to help check tax credit claim forms.[3]

2. The Office of Government Commerce have a government-wide role for advising Departments on IT projects and they conduct Gateway reviews during major IT system developments. In December 2002, the Gateway 4 review, "Readiness for Service" described the new tax credit programme as "an exemplar of good programme management", while noting that a large amount of work remained against a tight schedule. The implementation of new tax credits was overseen by a Programme Board, chaired by the Inland Revenue, with senior representation from the Department for Work and Pensions and EDS. The Board received regular progress reports from Inland Revenue and EDS teams and monitored progress in implementing the projects.[4]

3. When the new tax credits schemes went live for payment in April 2003, problems with the IT systems resulted in several hundred thousand claimants receiving payments after they fell due, while the Department were unable to reconcile payments made with amounts authorised.[5]

4. Analysis of the technical problems by EDS and "tuning" the system to perform more reliably took several weeks. EDS did not achieve a stable system until after 10 weeks of live operations.[6] In July 2003 the Department engaged consultants to conduct a review to provide independent assurance about the analysis of the technical problems and the action being taken to address them. The Department's consideration with EDS of the underlying technical problems had to have regard to the discussions between them about compensation for the unsatisfactory performance of the system and the possibility of legal action. For the past two years, EDS have also been re-competing for the Department's overall IT service provision, in a project called ASPIRE.[7] The Department announced on 11 December 2003 that Cap Gemini Ernst & Young (CGEY) had been selected as the Department's preferred supplier for the ASPIRE Contract, rather than the consortium that included EDS.

5. The C&AG's Report recorded the view of the Department and EDS about the testing of the new tax credits systems in the following terms: — They had worked together with other parties involved, on testing to make sure that key functions needed for April were ready. This was a complex task. To ensure robust IT functions were available at the time they were needed, the testing strategy was to prioritise the functionality needed first, and to delay less urgent testing. The period of instability in the early months of the live service was caused by queues building up in the channels between system components. The causes of these queues were not detected during testing. The nature of the particular testing regime meant that the underlying technical faults could not have been discovered and corrected in testing although more testing might have reduced the effects of some of the problems.[8]

6. The Department and EDS had not foreseen that the new tax credit systems would prove unstable and not fit for purpose. EDS recognised the disruption that was caused within the Department and the pain in the country at large, and they deeply regretted the consequences of the system instability. They prioritised the testing to make sure that they could get tax credit payments to people and the testing that was undertaken did not identify the problems that eventually resulted.[9]

7. The Department relied on advice from EDS as to what was feasible. EDS gave the best advice they had at the time, but it proved to be wrong and they accept responsibility for their advice and for the IT systems being unstable. EDS accepted that the instability contributed to the overall New Tax Credit problems and that they shared some responsibility with the Department.[10]

8. EDS emphasised that the project was one of the most challenging the Government had ever undertaken and that the timetable had been compressed. There was a six week delay while the rules for calculating tax credits were finalised. The 19 week system testing window had been cut significantly. In particular the volume testing timetable was cut from 12 to 4 weeks because EDS had to solve problems with National Insurance numbers. Both EDS and the Department considered that the compressed timetable had adverse consequences for the project.[11]

9. EDS said that if they had been aware during the testing period that they would have the problems which eventually resulted, they would have advised the Project Board not to go ahead with the system. Likewise if the Department had had any indication that the system would not be fit for purpose they would have advised Ministers to invoke the contingency arrangements.[12]

10. In their partnership with EDS, the Department had been concerned not to duplicate the functions of EDS. With the benefit of hindsight, they have looked at what went wrong with the New Tax Credits systems. For the forthcoming tax credit system extension they have retained Deloitte and Touche to work for the Department to make them a more intelligent customer.[13] The Department and EDS are also considering what lessons can be learned about technical system design and testing strategy, including the effects of a compressed testing timetable.[14]

11. This Committee and our predecessor Committees have criticised on several occasions major IT systems and developments, including the National Insurance Recording System (NIRS2) and the Passport Office system, both of which involved partnerships with IT suppliers. The problems with NIRS2 showed the dangers of setting too tight a deadline for implementing the Pensions Act 1995 and not properly assessing the effect on NIRS2 of changes to pensions and national insurance legislation.[15] The Passport Agency were far too optimistic in assuming that their new system, involving substantial changes in working methods, could be implemented over a few months without detriment to services.[16]

12. The Department transferred many staff from other work to deal with the problems with new tax credits. They subsequently revised their business plans and made arrangements to catch up on the backlogs where possible. They have not quantified the overall cost of what went wrong or the opportunity cost, but consideration of those matters will inform their negotiations with EDS over the scale of compensation. The Department believe that their contract was robust and they hope to negotiate a reasonable level of compensation without litigation.[17] For their part EDS acknowledge that they have some responsibility for the problems that were caused when new tax credits went live. Discussions on compensation were continuing at the time of the Committee's hearing in December 2003.


3   C&AG's Report, paras 3.1, 3.7 Back

4   ibid, paras 3.8-3.9 Back

5   ibid, para 3.21 Back

6   Q 74 Back

7   C&AG's Report, paras 3.11-3.12 Back

8   C&AG's Report, para 3.13 Back

9   Qq 2, 15, 22 Back

10   Qq 24, 65, 175 Back

11   Qq 74, 19, 42  Back

12   Qq 152-154, 88 Back

13   Q 45 Back

14   C&AG's Report, para 3.13 Back

15   38th Report from the Committee of Public Accounts, NIRS 2: Contract Extension (HC 423, Session 2001-02) Back

16   24th Report from the Committee of Public Accounts, The Passport Delays of Summer 1999 (HC 208, Session 1999-2000) Back

17   C&AG's Report, para 3.14; Qq 83, 121 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 22 April 2004