Select Committee on Constitutional Affairs Written Evidence


Evidence submitted by The Association of Chief Police Officers (ACPO)

CONTENTS
1.Project Initiation
2.Project Achievements
3.Implementation across Forces
4.Challenges
5.Areas of Confidence
6.Areas of Less Confidence
7.ACPO View
8.Appendices (not printed)
9.Further Material

ANNEX
Snapshot of Genesis (not printed)
Central Referral Process
Partnership Structure

1.  PROJECT INITIATION

  The Association of Chief Police Officers (ACPO) has an established project to manage the implementation of the Freedom of Information Act 2000 (FOI or "the Act") across the Police Service. The national project was initiated in December 2001, after the Chief Constables Council agreed to provide funding; all forces paid £3,500 to fund the project until January 2005. A Project Manager (a Chief Inspector) and a Project Support Officer were recruited from and are housed by Hampshire Constabulary. The national project uses PRINCE2 project management methodology. The Project Initiation Document, which describes the project approach, is attached.

  The project is nearing completion and currently is on stage nine of a probable total of 10 stages. The project is due to finish in March 2005, allowing the team to report to ACPO on the initial impact the Act has had on the Service.

  The projects objectives were to produce the following:

    —  A model Publication Scheme, approved by the Information Commissioner.

    —  A Communications Strategy for the Police Service.

    —  FOI Compliance Guidelines: best practice and lessons learnt from overseas public authorities.

    —  A Training Strategy for the Police Service in conjunction with Centrex.

    —  A Manual of Guidance detailing a common interpretation of responsibilities required under the Act and guidelines for action where legislation allows discretion to be applied.

    —  A national template for local administration of FOI legislation, completed under a Workflow system.

    —  A Single Point of Contact to advise and assist the Police Service on FOI issues and to provide an interface with other organisations (including the Information Commissioner).

  Mid-way through the project, the project was audited by the National Audit Office (NAO). The conclusions have been adopted and implemented and also disseminated across the Service. The report is attached.

2.  PROJECT ACHIEVEMENTS

  It has been recognized by ACPO that it is best value to develop best practice and guidance nationally and then share the results amongst the 44 forces, to prevent repetition of work and duplication of effort. The key achievements the Service has completed nationally are:

2.1  The production of a Compliance Toolkit for the Police Service

  A "Compliance Toolkit for the Police Service" was produced and issued to all forces in April 2002. The toolkit:

    —  Introduced the national project team and described what the project team would produce

    —  Provided an overview of FOI

    —  Gave guidance on Section 45 Code of Practice—Discharge Functions

    —  Gave guidance on Section 46 Code of Practice—Records Management

    —  Provided LCD draft regulations on fees

    —  Introduced and described the ACPO Publication Scheme

    —  Provided useful references

2.2  The production and approval of the Publication Scheme

  A model Publication Scheme has been adapted by all 44 forces. The DCA and the ICO were instrumental in organising meetings to design and agree the Publication Scheme. This is an example of successful collaborative work between the Police Service, the DCA and ICO.

2.3  The creation of a discussion group on FOI on Genesis

  Genesis is a database hosted by Centrex that is accessed via a secure network and logon over the Police National Network. It is a notice board that allows users to communicate through message threads and discussion forums, and to share information and documents through topic areas. Para 10 contains a snapshot of the Genesis database (not printed).

  Around six to eight hundred documents are available for download from Genesis from the following areas: Project Plans; Lessons Learnt from Abroad; Metropolitan Police Experience; FOI Personnel; Training; Dealing with Requests Process Maps; PowerPoint Presentations; FOI National Project; Information Audit Documents; Guidance on Force Policies; Miscellaneous National Documents; National Working Parties; ACPO Disposal and Retention Scheme; Safety Camera Partnership; Procurement Exemption; Manual of Guidance; Written Articles on FOI; Mosaic Attacks; FOI Workflow System & ACPO Standard Letters.

  The Service will continue to use Genesis post January 2005 to facilitate the continued sharing of best practice and decisions (eg additional information classes for the Publication Scheme).

2.4  Extensive research on best practice and lessons learnt by overseas public authorities

  The project team have carried out several visits to public authorities overseas to learn from their experiences of implementing their local FOI Act. Guidance on best practice and lessons learnt were collected. Destinations have included Australia, America (FBI) and Canada.

  Reports on the findings of the research trips have been extensive, and have been shared across the Police Service and with other Public Authorities where appropriate (including the DCA, ICO and the Home Office), to ensure best value has been gained to offset the cost of the trips.

  We attach the report from the Metropolitan Police Service's visit to the FBI as an example. (Not printed.)

2.5  The production of approved disposal guidelines for policing records

  Disposal guidelines for policing records and general records held by forces have been produced and approved by the National Archives and the ICO. These have been adopted by all forces.

  Papers have been circulated to all Chief Constables on the definition of historical records and what should be sent to their local county archivists.

2.6  The delivery of national training

  25 training courses are being delivered, resulting in about 350 trained central decision makers across the country. Central decision makers are the individuals that will be applying the Public Interest Test. The provision of national training ensures a consistent application of this test across the country. We note that these central decision makers will have access to each other via Genesis and the established networking systems.

  250,000 leaflets have been issued to all Police Service employees to raise awareness. In addition, posters and a central training website (provided by NCALT which all Police Service employees can access to train on-line) have been provided.

  Material for one day training courses to be held locally by each force has been issued. These are for the local decision makers within each BCU and department who will supplement and support the central decision makers.

2.7  The production of a draft Manual of Guidance

  The draft Manual of Guidance is currently around 350 pages long, and has taken approximately 1500 to 2000 working hours to produce.

  Research for the Manual of Guidance has been shared out across all forces.

  The Manual of Guidance will be submitted to the Bichard Working Group to be incorporated into the Code of Practice.

2.8  The production of a Statement of Requirement for a Workflow System to log and process FOI requests

  A framework agreement is being constructed, to allow all Police Forces, all emergency services, all local authorities and the Home Office to select one of the chosen suppliers either now or at a later time.

  Therefore each public authority that signs up to the framework agreement has not only taken advantage of the large discount available in the framework (up to 33% off) but has also saved on the resources to produce a Statement of Requirement.

  The Statement of Requirement has taken approximately 750 hours to produce. Therefore the cost savings to organisations are extremely substantial.

  A statement of requirement for a Workflow system was promised by the DCA in November 2003 but was actually produced in April-May 2004, and has caused considerable problems to authorities due to the tight timeframe of the procurement process. We believe this is an example of a product that the DCA should have organised to be available to all Public Bodies as the potential savings to the Public Sector could have run into millions of pounds.

2.9  Established Hampshire Constabulary as the single point of contact

  The project office receives approximately 150 emails and answers approximately 200 phone calls a week.

  The office is in regular contact with both the DCA and the ICO; this centralised contact ensures consistency.

2.10  Designed the central referral process

  A central referral process is required to manage requests that are issued to several (or all) forces at the same time. To date several such requests have already been received. The Police Service require an essential overview of these requests, to ensure that all forces respond uniformly and to allow the determination of best practice and lessons learnt to be shared across all forces. The Annex includes a diagram illustrating how the central referral process is to work, which is currently with the Chief Constables Council for ratification and funding.

  We note that this is an area that we felt should have rested with the DCA to develop a strategy for public authorities in general. This is an example of a missed opportunity, which could have prevented the duplication of effort across public bodies.

2.11  Established the procedure for partnership agencies

  The Police Service shares its data with many partner agencies, who also share their data with us. It is imperative that partnership agencies have a clearly established process for handling requests for data that may belong to a partner agency.

  The national project team have recently completed some research on this subject on behalf of the Lord Chancellors Department. The project team have determined that establishing and sharing best practice for partnership working with partner agencies is key, in addition to creating work packages to share work across agencies to prevent the duplication of effort and to ensure compliance to the Act on data sharing. A diagram illustrating the process can be found in the Annex.

  The paper is to be presented to the Lord Chancellors Advisory Board for ratification on 22 October 2004.

  We note this is another area where the Service feels the DCA missed an opportunity for a more efficient implementation of the act; this topic should have been addressed by the DCA across the whole public sector to provide an overview to all public authorities.

3.  IMPLEMENTATION ACROSS FORCES

  Each force has a Project Manager for FOI implementation. The country was divided into seven regions, including Scotland as one region. Each region has an assigned regional chair. Below we present a brief summary of the implementation work carried out across the Police Service.

3.1  Compliance Toolkit for the Police Service

  As noted above (cf. 2.1), one of the first products of the national project was a Compliance Toolkit for the Police Service, to ensure all forces were briefed on the legislation and what preparation was required. Initially six weekly newsletters were produced to inform all force Project Managers on progress by the national project, until this was superseded by the Genesis database.

3.2  Regular regional meetings

  The national Project Manager meets with all force Project Managers at regional meetings held every six weeks. At these meetings the Project Manager raises the state of each forces preparedness and questions whether they are experiencing any issues.

3.3  Sharing of work across forces

  Work has been shared across forces wherever possible. For instance, as noted above, all forces were involved in the preparation of the Manual of Guidance (cf. 2.7), in particular the interpretation of exemptions. Each of the regions was given one or more topics to research and report back the findings to the national project. Research topics for the Manual of Guidance included:

    —  Appeals Process

    —  Charging

    —  Communications/Marketing

    —  Contracts and Confidential

    —  Government Protective Marking Scheme

    —  Campaign and vexatious requests

    —  Post Publication Scheme

    —  Process and Requests

    —  Public Interest Test

    —  Section 30 (Investigation), Section 31 (Law Enforcement) and Section 32 (Court Records) Exemptions

3.4  Disseminated best practice

  The national project team has researched, collated and disseminated best practice, lessons learnt and good advice across the Service (cf. 2.4).

3.5  Identified high risk areas to the Service

  The national project team have identified the high risk areas to the Service, to ensure the Service moves forward together. Where possible procedures and templates have been produced and shared with forces, to ensure a corporate approach. Identified high risk areas include:

    —  Special Branch

    —  Safety Camera Partnership Scheme

    —  BCU Minutes

    —  Chief Constable Expenses

3.6  Letters to Chief Constables

  Where necessary, letters have been sent to Chief Constables by the Project Executive. Letters regarding the publication of BCU minutes and Chief Constable Expenses are attached.

3.7  Review of force Publication Schemes

  The national team have centrally checked all force Publication Schemes to ensure they are being maintained correctly and are up to date; those forces who were found wanting have had letters sent to their Chief Constables from the Project Executive.

3.8  Regular ACPO meetings

  Quarterly ACPO meetings are held with all the regional chairs in attendance and this is to continue post implementation. These meetings are, and will continue to be, used to ratify new Publication Scheme information classes and to disseminate best practice.

4.  CHALLENGES

  The key identified challenges to the implementation of FOI for the Police Service include the following:

4.1  Consistent application of the Manual of Guidance

  The Manual of Guidance will be submitted to the Bichard Working Group to ensure it is linked to the new Code of Practice for Police information management (cf. 2.7). This is a key area where we need consistency. Although there are 44 forces we are all doing the same role, ie policing, and there is a massive opportunity for the Service to be "divided and conquered" by requests if there is inconsistent application of the Manual of Guidance.

4.2  Central referral process

  Our ability to identify vexatious and campaign requests across forces is a key challenge. The central referral process is designed to highlight these types of request; a paper on the proposed process is going to the Chief Constables Council for ratification (cf. 2.10).

4.3  Data sharing

  Ensuring we and our partner agencies communicate effectively regarding the release of data we share. The national project has prepared a paper on data sharing on behalf of the Lord Chancellor's Advisory Board (cf. 2.11).

4.4  Lack of commitment by forces

  Some forces may not be taking the implications of the Act as seriously as others and therefore may not be committing sufficient resources to preparing for FOI. These forces are being challenged by the Project Executive through guidance and letters.

4.5  Consistency between ACPO and ACPOS

  A consistent response from ACPO and ACPOS is required. Regular meetings are being organised via the Information Compliance Partnership Group and ACPOS are adapting the ACPO Manual of Guidance. The intention is for ACPO and ACPOS to agree any future information classes to be added to the Publication Scheme.

5.  AREAS OF CONFIDENCE

  The Police Service has confidence in:

5.1  The ICO

  The Police Service has confidence in the ICO policy officers, whom have been extremely helpful. Two officers have been permanently attached to the Police, to assist in interpreting policy and exemptions, namely Sections 30, 31 and 32 which are distinctly Police related. In the recent reorganisation of the ICO office, one of those officers has been given responsibility for the Police Service post 2005, giving us confidence in the decision making process as they have a thorough understanding of the policing business. We have an extremely good working relationship both nationally and locally. They have always assisted forces when required to give presentations to Senior Management and these have always been well received. Richard Thomas's office has assisted greatly throughout the project and ACPO greatly appreciate their help and support through the implementation phase. We are confident that this relationship will continue post 2005.

5.2  Central referral process

  When the central referral process is fully operational the Service believes that we will be able to have a central overview of the requests that are received which have national implications. The Service will be able to assist applicants when appropriate by giving a Service response as well as individual force responses, to ensure that there is consistency in disclosure.

5.3  Our ability to learn from experience

  The Service has confidence in our ability to learn from each force's experiences whilst dealing with requests. The Genesis database will be used to gather and disseminate best practice post implementation (cf. 2.3).

6.  AREAS OF LESS CONFIDENCE

  ACPO has less confidence in:

6.1  Lord Chancellors Advisory Board

  The governance of the Lord Chancellors Advisory Board, how it is organised and its membership; there is a lack of synergy from the Board members. We feel the set up and membership of the Advisory Board was a good concept to provide an overview of the Public Sector. However, it has not actually fulfilled its anticipated role of providing governance and direction to the Public Sector; it seems to have worked with an individual sector approach rather than across the whole sector.

6.2  Requests affecting several authorities

  The Police Service believes that there is no holistic overview of requests that would affect more than one Public Authority. We have major concerns within the Police Service that we may be "divided and conquered" by requests; the Service consists of 44 separate authorities and there is a risk that one or more forces may disclose differing information to the same request. We feel that many other organisations within the Public Sector are vulnerable to "divide and conquer" requests, and this is an area that requires further research and development centrally.

6.3  Consistency from the DCA

  There have been high staff turnover levels in the DCA since the development of the Publication Scheme in 2003. Indeed, the individuals who drafted the legislation in the DCA have since moved on and it is our belief that there is nobody left within the team who was involved in writing the legislation. This is causing problems in interpreting the legislation in certain areas and ACPO are having to take QC advice on certain sections where the wording is not clearly defined (eg Section 8). The DCA representatives that attend Project Board meetings are never the same, resulting in little consistency.

6.4  Fees

  Fees within the Act are causing us concern due to the impact of these on the Service plus the lack of a planned review process that is essential to reassess costs after the initial implementation.

6.5  Data sharing

  Due to the different levels of preparedness of authorities within the public sector, it is unclear how each individual authority will deal with requests and ACPO are concerned that there is a possibility that our information may be released inappropriately without consultation.

6.6  Publicity

  Publicity of the Act to the general public; we are unsure as to what will be done and what the impacts to the Service may be.

6.7  Future FOI conferences

  Pre the development of the Publication Scheme, considerable conferences were hosted by the DCA, which were extremely informative, well received and free to Public Authorities. Post the delivery of the Publication Scheme (mid 2003) this has ended. Since then, the Project Executive, Project Manager and numerous force Project Managers have been consistently bombarded by conference organising companies to give speeches on FOI free of charge at conferences where delegate places cost around £400 to £600. This is an area where we feel the public sector has wasted considerable money; a more centralized approach could have been continued by the DCA or another central body to keep authorities informed and up to date.

6.8  Future DCA guidance

  All guidance the DCA has provided has been Whitehall centric and consideration to other authorities has not been given. For example the Fees Working Group didn't include a Police Service representative and the national project team had to push for our inclusion. In addition, all the guidance that is produced undergoes Quality Assurance by Whitehall bodies, again ignoring the Police Service and other public authorities.

7.  ACPO VIEW

  In addition to the remarks made above, we feel we have the systems in place for FOI but we acknowledge that these are as yet untested. The Police Service is at a high level of preparedness, although we accept there are still dangers to certain areas of business, particularly historical cases. The Service has a holistic overview and is hoping this will be enough, due to the lack of extra resources being provided by the Government.

8.  APPENDICES (NOT PRINTED)

  Project Initiation Document (cf. 1)

National Audit Office Review (cf. 1)

FBI High Level Learning by the MPS (cf. 2.4)

The Freedom of Information Manual ACPO v1 (Section 1 only) (cf. 2.7)

Letters to Chief Constables (cf. 3.6)

    (i)          re publication of BCU Minutes

    (ii)          re Chief Constable Expenses

9.  FURTHER MATERIAL (AVAILABLE UPON REQUEST)

  All Stage Plans and End Stage Reports for the project (cf. 1)

Compliance Toolkit for the Police Service (cf. 2.1)

Video of Australian research (cf. 2.4)

Other research material (Papers on the Public Interest Test, Sections 30 and 31, Procurement) (cf. 2.4)

ACPO disposal and retention schedule (cf. 2.5)

Manual of Guidance (cf. 2.7 note file size is over 1MB)

Workflow System Statement of Requirement (cf. 2.8)

Safety Camera Partnership Report (cf. 3.5)

The Association of Chief Police Officers

5 October 2004

Annex

CENTRAL REFERRAL PROCESS (CF 2.10)

PARTNERSHIP STRUCTURE (CF 2.11)






 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 7 December 2004