Select Committee on Defence Written Evidence


Further memorandum from the Ministry of Defence

  Further information requested following the evidence session with Air Chief Marshal Sir Jock Stirrup KCB, AFC, ADC on 20 October 2004.[6]

  Q102-4.  Details on progress with the negotiations for the contract for the second tranche of Typhoon.

  The collaborative arrangements for the Eurofighter (Typhoon) programme require each of the four partner nations (Germany, Italy, Spain and the UK) to negotiate prices with their national industries, while NETMA (the NATO procurement agency that places and manages contracts on the nations' behalf) negotiates the contract terms and conditions. The UK Ministry of Defence is completing negotiations with BAE SYSTEMS and the normal project scrutiny and approval process. The other nations have also reached agreements with their respective partner companies and are seeking their own national approvals. All four partner nations expect to be in a position to authorise NETMA to place the contracts before Christmas.

  Q114.  Clarification of what financial penalties, if any, would be incurred by the British Government deciding not to proceed with the third tranche of Typhoon.

  The Typhoon programme is organised under a series of Memoranda of Understanding between the four partner nations, Italy, Germany, Spain and the UK. Although not legally binding, such MOU are the basis of most international collaborative defence projects and are relied upon by nations. The key principle of the Typhoon production arrangement is that each nation's industry builds a share of each aircraft, that share being equivalent to the nation's declared total "offtake" of aircraft. Each nation's government is then responsible for paying its own industry, with the end result that each nation's total share of manufacturing work and cost equates to its share of the aircraft, and costs are largely immune to currency exchange rate variations. If any nation reduced its offtake of aircraft, for instance by not proceeding with Tranche 3, it follows that manufacturing work would need to be redistributed between the nations to restore the balance of work and cost-share to aircraft offtake. This redistribution would be a complex, time-consuming and potentially expensive process. There is no question of a financial "penalty" but the MOU requires any nation that changes its requirement to bear these additional costs on behalf of the others, up to a ceiling based on the amount the nation would have paid for its original requirement. Such costs would not arise in the event that all four partner nations were to agree to proportionally similar changes to their offtake requirements.

  Q142.  Whether, and when, the business case and investment appraisal studies being undertaken for each individual site under the Defence Airfield Review will be published.

  The Defence Airfield Review business case and investment appraisal (IA) studies will be published after the Minister for Armed Forces has announced any decisions that are informed by the studies. The documents may need to be redacted before publication. Any redactions will be made by reference to the exemption categories in the Freedom of Information Act and Environmental Information Regulations.

  The Committee may find it helpful to note that, whereas all options are assessed on the same criteria in the IA process, some assumptions may differ. For example, in the IAs being undertaken in respect of the future basing of Nimrod MRA4 it is assumed that RAF Waddington would remain open irrespective of the outcome whereas for RAF Kinloss the assumption is that the Station would close if the outcome were that the Nimrod MRA4 force would be established at Waddington. This reflects the fact that RAF Waddington is home to a number of aircraft types and a range of support units which, on current planning, would continue to be based there in the future. RAF Kinloss, on the other hand, is predominately home only to Nimrod MR2 and in terms of the IA it is therefore appropriate to assume that the Station would close if not chosen as a base for MRA4 or any other defence use. IAs are technical documents, designed to balance the relative costs and benefits of different options, which are used to by the Department to inform the decision making process.

  Q144.  Why the Overall Force Levels table in the Future Capabilities paper (Cmd 6269) lists only "deployable force elements" for the offensive aircraft and "deployable aircraft and the aircraft held at readiness for the QRA air defence of the UK" for air defence aircraft rather than total holdings as is the case for all other force elements?

  The presentation of meaningful statistics reflecting planned capability of fast jets is complicated by a number of factors, principally the fact that capability is delivered by a combination of combat ready crew and aircraft. As CAS explained during the evidence session, the assumptions made about the number of crew required to deploy on operations affects the number of aircraft resourced to fly to support force generation of crew and the number of aircraft procured to support the planned life of the given aircraft type.

  In the Supporting Essays to the SDR White Paper of 1998 (Cmd 3999) we attempted to express the impact force generation of crew had on the number of aircraft required to be held in squadrons to support routine flying. However, for the tables in Cmd 6269 we took the view that the number of aircraft routinely flying in squadrons is a management issue, rather than a measurement of capability available for contingent operations. The latter is defined by the numbers of aircraft held at readiness for operations and for QRA air defence tasks.

  Q153.  Confirmation of the number of deployable fast jets and of QRA aircraft.

  The maximum number of deployable fast jets (held at readiness) (shown in the Large Scale table) is 64 offensive support and 16 air defence. In addition four air defence aircraft are required in the UK to cover QRA tasks.

  Q191.  Whether the additional C-17 to be purchased will include enhancements currently being fitted to the US fleet as a result of experience in Afghanistan and Iraq?

  Current plans assume that the fifth C-17 will be fitted with the same enhancements as those that are fitted to the US Fleet. Our understanding is that this will include those enhancements fitted as a result of experience in Afghanistan and Iraq. Indeed, the fifth UK C-17 aircraft will be manufactured to the most current USAF production block standard, which will be inherently more capable than current operational USAF C-17 aircraft. Furthermore, the existing four UK C-17 aircraft are nearing the end of a return-to-works programme to have the same enhancements installed as fitted to the US C-17 fleet.

  Q212.  Whether the first commander of the Joint Helicopter Command asked that one of the three service chiefs assume overall responsibility for the JHC, and if so for what reasons it was turned down?

  The first Commander of the Joint Helicopter Command (JHC) was Air Vice Marshal Niven: he retired from the RAF on leaving that post in 2002. Before taking up that appointment AVM Niven led the study that examined the viability of a Joint command arrangement for helicopters that operate in the land environment and subsequently the team that implemented the Chiefs of Staff (COS) endorsed recommendations of that study. Central to the recommendations accepted by the COS in December 1998 was a proposal that all helicopter units that fell within the scope of the review should have a clear chain of command with no confusion as to who has authority, for example, to issue regulations, conduct Boards of Inquiry and to task Battlefield (BH) and Support (SH) Helicopters. As CAS explained to the Committee, the Royal Navy's anti-submarine warfare and airborne warning helicopters mounted from ships were excluded from the review. So too were the RAF's search and rescue helicopters.

  In addition to clarifying operational command of all helicopters operating in the land environment a key argument advanced in favour of a Joint command structure was that it would facilitate improved balance of investment decisions thus enabling and encouraging the realisation of economies of scale. The COS agreed that the ability to rationalise and deliver efficiencies would be restricted if full financial authority was not delegated to a single TLB. It was therefore agreed that JHC would be funded on the lead Command Model with operational and financial responsibility placed with the Land Command TLB.

  With effect from 1 October 1999 Operational Command (OPCOM) of all helicopter units operating in the land environment (ie all Royal Navy, Army and RAF helicopters, with the exception of the Royal Navy's anti-submarine warfare and airborne warning helicopters mounted from ships and the RAF's search and rescue helicopters, was delegated to CINCLAND, and exercised by Commander JHC. OPCOM of 16 Air Asslt Bde was formally delegated to Comd JHC from April 2000, following completion of the major part of its reorganisation.

  However, the COS also endorsed the Study Team's recommendation that it would be inappropriate for the Commander JHC to assume Full Command (FC) (defined as "military authority and responsibility of a superior officer to issue orders to subordinates (and) covering every aspect of military operations and administration") of personnel and units from another Service. It would not be in line with Queen's Regulations and there is no clear procedural mechanism within the UK Armed Forces for such an arrangement on a permanent basis in peacetime. The single-Service front line Command CinCs (FLEET, LAND and STC), therefore, continue to exercise FC over personnel of their respective Service for units in the JHC.

  Q222.  When and how the capability gap caused by the non-availability of the Chinook Mk3s will be filled?

  The capability gap caused by the non-availability of the Chinook Mk3s is currently being filled by Chinook Mk2/2a fitted with the Night Enhancement Package (NEP). Chinook Mk2/2a (NEP) will continue to fill the gap until either the Chinook Mk3 is brought into service or new capability procured. A Combined Operational Effectiveness and Investment Appraisal (COEIA) concluded that a "Fix-to-Field" solution is the probable best value for money option for the Mk3. This solution has been ratified by three independent technical advisors as being realistic. An investment of around £13 million has been approved for preparatory work including risk reduction, which will enable us to determine with greater fidelity whether Fix-to-Field is both technically and financially acceptable, which are not yet proven. If the Fix-to-Field does proceed beyond the risk reduction stage, the likely in-service date for Chinook Mk3 is currently assessed to be late 2007.

  Q224.  What measures has the RAF taken to protect its control towers from terrorist attack and how, if necessary, it would replace one which had been destroyed?

  Air Traffic Control (ATC) towers are afforded the same level of security as all other operational assets. Control of entry to RAF Stations is effected by armed Service and armed Ministry of Defence Police personnel. Regular counter terrorist patrols are conducted by Station Guard Forces on all units. These include patrols by RAF Police dog units. Specific defensive measures are dependent on the threat and are driven by intelligence from a variety of sources, including liaison with local Police Forces. Additionally, regular routine unit security surveys and the application of Risk Management processes assist in ensuring that defensive measures against terrorist attacks are appropriate. Access to ATC towers is restricted to authorised persons through control of entry procedures and all visitors are checked and escorted.

  RAF station recovery plans are designed to deal with all losses of capability, including air traffic control. The loss of an air traffic control tower through terrorist activities would have a major impact on flying operations at the station. In the immediate aftermath routine flying operations would cease. Airborne home-based aircraft would divert to an alternate airfield: all sorties have two identified diversionary airfields in case of malfunction or bad weather. If deemed operationally necessary, however, aircraft could operate using silent procedures even though ATC services were not available. This would allow aircraft to be redeployed to serviceable airfields if required. Mobile ATC assets would then be made available to allow normal operational fair weather flying to resume. In the longer term further mobile ATC assets would be deployed to provide a bad-weather capability.

December 2004







6   Ev 19-37 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 17 March 2005