Select Committee on Defence Written Evidence


Further memorandum from the Ministry of Defence

  Further information requested following the evidence session with Air Chief Marshal Sir Malcolm Pledger KCB, OBE, AFC, Major General A J Raper CBE and Major M D Wood CBE on 17 November 2004.[11]

  A number of questions focused on the announcement made on 16 September 2004 that the preferred option was to re-locate support of Tornado G4 aircraft from the Defence Aviation Repair Agency (DARA) to the Main Operating Base (MOB) at RAE Marham and That support for rotary aircraft would be concentrated at DARA Fleetlands. The Committee would like to have copies of the Investment Appraisal and the Affordability Analysis supporting these two announcements. The Chief of Defence Logistics (Q441) said that this work was done under the direction of MoD's Senior Economic Adviser. The Committee would like to have copies of the papers produced by the Senior Economic Adviser which summaries the results of The Investment Appraisal and Affordability Analysis for both cases (various questions including Q463).

  These documents are attached.[12] As part of the process of assessing affordability, we revisited the costs associated with all the options developed for the Investment Appraisal, particularly in respect of service family and single living accommodation. This further analysis determined that changing the maintenance arrangements for Tornado F3 would generate net costs because the aircraft leaves service before long term savings outweigh up-front costs. In addition, we looked particularly closely at the extent to which additional efficiencies could be delivered if Lynx and Sea King were both "rolled back" to DARA Fleetlands.

  The consequence of this analysis is reflected in the following table, which shows the assessed cost against the effect of doing nothing of the three options considered in the Investment appraisal and the two further options considered (not changing Tornado F3 arrangements and rolling Lynx back to DARA Fleetlands).


FY
04/05 £M
FY
05/06 £M
FY
06/07 £M
FY
07/08 £M
FY
08/09 £M
FY
09/10 £M
FY
10/11 £M
FY
11/12 £M
FY
12/13 £M
FY
13/14 £M
Total
£M

Roll Forward
7.9
40.3
-1.0
-21.2
-26.2
7.0
-32.6
-33.4
-34.2
-34.9
-128.3
Roll Back
14.4
64.2
18.0
-28.5
-34.0
-37.0
-33.6
-33.4
-35.3
-36.2
-142.4
"Hybrid"
7.2
37.1
-4.4
-26.1
-33.9
60
-33.7
-33.5
-35.3
36.2
-153.8
"Hybrid" minus1
0.9
21.5
-11.5
-21.9
-16.4
9.1
-34.8
-35.7
-36.6
-37.5
-162.9
"Hybrid" minus, Lynx Back2
4.3
18.5
-21.5
-33.3
-22.2
3.2
-40.9
-41.9
-43.0
-44.0
-220.8

1  The "Hybrid" option without Tornado F3
2  The "Hybrid" option without Tornado F3 and with Lynx "rolled back" to DARA Fleetlands


  On the announcement about re-locating support of Tornado GR4 aircraft from DARA to RAF Marham, The Committee would be grateful for a note which sets out the grounds for this announcement, particularly as the announcement appears to be a reversal of policy (Q433). This note should set out which specific circumstances have changed which have led to this announcement. The Committee is particularly interested in the specific circumstances which have changed since the publication of the Defence Committee's report on DARA in March 2001. The note should also set out: the opportunity cost relating to the announcement ie how much is planned to be re-invested in the St Athan area (Qs 416-419); and the percentage of the Tornado GR4 aircraft work (by value) at RAF Marham which is expected to be undertaken by the private sector (Qs 426-427).

  The Committee are aware of the background to the decision on Recommendation 40 as laid out in Minister (AF)'s letter to the Chairman on 16 September. This explained that this work had been taken forward as a result of the End-to-End Logistics Review of the Air and Land Environments which took place in 2003. This review was the first time we had looked end-to-end at the logistic process and it provided some key insights and proposed new ways of providing logistic support to the Services more effectively and efficiently.

  In particular, the End-to-End Review concluded that there was substantial excess capacity in all areas of air systems support—in industry, the Defence Logistics Organisation and Front Line Commands alike—and duplication of facilities across the Services and other parts of the MoD such as DARA. There was both a need and substantial scope for improvement in all areas. It also reflected the fact that, with some notable exceptions, the Department and the Services were not using industry modem best practice to drive down the cost of supporting military aircraft. The case for significant change was unarguable.

  It was clear then—and demonstration since has amply proven—that significant improvements can be made to the productivity of the RAF personnel through the application of lean techniques, enabling more work to be done at front-line bases, whereas there would be significant costs and operational penalties in moving these personnel from the Main Operating Bases (MOBs) to St Athan. These personnel form part of the "Crisis Manpower Requirement" for the Royal Air Force, which determines how many RAF personnel we need to sustain the level of concurrent operational deployments for which the Department plans. Accordingly, these personnel must be uniformed personnel and cannot be replaced by civilians or contractors. Where the total depth support task exceeds the number of RAF personnel required to support deployments, the remaining work would be carried out at MOBs by civilians or contractor personnel.

  The original decision to proceed with the modernisation of the St Athan site was taken on the basis of a sound business case which centred on the need to reduce DARA costs by rationalising the antiquated and inefficient infrastructure at St Athan. The work load projections in the Red Dragon business case indicated that the case for Red Dragon (in terms of MoD work) was soundly based in the short to medium term out to 2008-09 but that there was a need for DARA to find commercial work in the medium to long term. It was not possible to take into account the effect of the End to End Logistics Review at the time the Red Dragon business case was approved, since the Review had not yet then started.

  It is the case that the outcome of the E2E Review will change significantly the level of depth air support work required in the medium to long term. As Minister (AF) has made clear, sufficient work will remain at St Athan to maintain a viable operation there until 2008-09, both continuing work on Tornado GR4 until the new facilities at RAF Marham are available and on other platforms (Hawk and VC 10). This is in line with the assumptions on the payback period made in the Red Dragon business case. However, currently envisaged work on other Defence platforms will not be sufficient to sustain St Athan on an economic and viable basis after 2009. If no alternative work can be won to sustain St Athan, this would result in closure. Officials from the MoD, along with DARA senior management, have already had meetings with Welsh Assembly and Wales Office staff to explore possible options, and have agreed a strategic approach for taking this forward as a matter of urgency.

  The opportunity costs of the Red Dragon project have been treated in the IA in accordance with the Treasury "Green Book" and with additional HM Treasury guidance. Cancellation payments have been treated as a sunk cost as there is no part of the payment that gives rise to a future economic cost.

  Since the way ahead for DARA St Athan is not yet clear, there are accordingly no firm figures for any MoD re-investment in the St Athan area.

  Currently there is no contract in place and a priced proposal has yet to be submitted by the private sector for GR4 aircraft work at RAF Marham. However, the investment Appraisal clearly demonstrated that the re-location of logistic support for the Tornado GR4 from DARA St Athan to RAF Marham provided the optimum solution. It is on this basis that we are proceeding with the transfer.

  There are a range of programmes/initiatives in the DLO which are expected to deliver efficiency savings. These include the Defence Logistics Transformation Programme, DLO restructuring etc. Some of these programmes/initiatives were discussed at the evidence session. The Committee would be grateful for a note which sets out the total efficiency savings between the various programmes/initiatives. The note should indicate how much of the planned efficiency savings are expected to be reinvested in defence logistics and in what areas (Q488).

  The efficiency savings the Department plans to deliver over the Spending Review 04 period were laid out in the MoD Efficiency Technical Note which was published on the MoD Internet website on 29 October 2004. This document identifies, inter alia, the contribution of logistics to meeting the efficiency targets, however the DLO elements are broader than this. The table below lists the key programmes.


£M
2005-06
2006-07
2007-08

DLO collocation
5
DLO restructuring
25
25
26
DLO procurement reform
47
94
157
DLO elements of Defence Logistic
  Transformation Programme1
DLO element of end-to-end study
19
53
65
DLO change programme
374
432
555

1  The DLO Change programme and end-to-end study were merged to become the Defence logistic Transformation Programme on 1 April 2004.


  The overall savings from the MoD Efficiency Programme have been used to balance the Departmental programme as a whole. As such, the Department would not normally hypothecate the savings from DLTP towards specific logistic investments, rather seeking to improve military effect through investment and integration across a range of capabilities.

  However, every change programme requires a level of investment and DLO elements of DLTP will have some £215 M invested over the above period to enable change to occur. Furthermore, the MoD has committed £61 M on investment in asset tracking and improving the supply chain and is considering, in the current budgeting round, the level of priority for further investment in these areas.

  The Committee sought assurance that the "patching" approach relating to asset tracking would deliver a proper system. The Chief of Defence Logistics said he would provide The Committee with a note on this (Q474).

  Following Op Telic, work directed by VCDS concluded that "the underlying flaw in the process . . . continues to be the lack of asset and consignment tracking, and insufficient communications and bearers dedicated to Logistics". To assure a coherent approach in addressing the capability gaps identified in the Report, Director General Logistics (Supply Chain) was appointed as the Senior Responsible Owner for asset tracking capability development and has brought all asset tracking projects into one programme to establish coherence, pace and focus.

  Director Supply Chain (integration) is the Programme Manager responsible for delivering the projects within the Programme and for providing a robust governance framework for all IS enabled business change in the asset tracking area. The Programme strategy follows the recommendations from the Tiger Team Report and directs that projects should drive convergence of single service processes and exploit best of breed current systems, using integrations software where possible to accelerate changes to asset tracking processes. Where there are still gaps, commercial off-the-shelf applications will be procured. This approach ensures that we fully exploit existing capabilities through progressive improvement and growth while, at the same time, introducing new capability to plug recognised gaps. This will reduce risk and provide the early delivery of operational capability. This is a robust programme with a clearly defined forward plan, based on coherent incremental delivery of capability, and has been specifically designed to avoid an ad hoc "patching" approach to Logistics Applications.


A table in The MoD Efficiency Note published on 29 October 2004 sets out the savings expected from procurement reform in the DLO—almost £300 million in the three years to 2007-08. What is the total DLO procurement budget against which these savings are being made? What reforms to the DLO's procurement arrangements are being introduced to deliver these expected savings and over what timescale?

  The total DLO procurement budget, ie the total DLO spend with Industry, forecast at the time, for the three years to 2007-08 was some £6,200 million each year.

  The DLO's Procurement Reform programme has three elements:

    (a)  Category Management, which is the strategic engagement of Industry through a market facing analysis of our total engagement with our suppliers.

    (b)  Supplier Performance, the development of a consistent, objective and analytical information on supplier delivery to inform procurement decision making.

    (c)  Key Supplier Management linked to the development of a close partnership with our strategic partners in Industry.

  Procurement Reform is underpinned by the creation of teams responsible for Category Management and Key Supplier Management staffed by professional procurement personnel with specialist knowledge of the requirements and suppliers for particular product areas. They will be responsible for delivering lower-cost procurement through development of best practice procurement strategies, better supplier management and developing the skills of DLO teams. As well as improved, consistent processes and better skilled staff, increasing use of procurement tools such as e-auctions, e-catalogues and e-tendering will also increase competitiveness and secure better value for money.

  The programme is being introduced progressively and will not be fully implemented until 2009-10.

The Chief of Defence Procurement told the Committee on 12 May 2004, That only one of The seven principles of Smart Acquisition had been implemented in full. In its Major Project Report 2004, the National Audit Office referred to the inconsistent application of the sensible acquisition principles enshrined in Smart Acquisition'. How fully has The Smart Acquisition initiative and specifically the seven principles of Smart Acquisition been implemented in the DLO?

  Smart Acquisition is every bit as applicable to DLO as it is to DPA and there is a vigorous programme to increase commitment to and enhance the Smart principles. There are fundamental differences between DLO's business and that of DPA. In sustaining UK military capability, the DLO is primarily concerned with equipment in its later life cycle phases and delivering to the end user, principally the Front Line Commands, as the customer. However, this does not preclude informing and influencing earlier acquisition life cycle phases from a through life perspective; this is a key DLO activity. Furthermore, about half the volume of DLO's business is "Non-equipment" acquisition of services, support and commodities. A Smart acquisition maturity survey is undertaken annually to monitor progress. The situation in respect of the seven principles is:

  (a)  a whole life approach typified by applying through life costing techniques

    (i)  The DLO operates a costed whole life approach to programme management in association with the DPA. Ensuring that projects are effectively managed through life is a basic tenet of Smart Acquisition and is achieved through dual DPA and DLO joint accountability and assurance policies.

    (ii)  The cost of ownership includes the procurement, operation, training, support and maintenance costs associated with delivering and owning a project (and hence its aggregated capability) through life.

    (iii)  The Department has an ongoing change programme (completing in Dec 2005) that will implement the methodology needed to ensure optimal cost informed whole life management of its projects and the capability they aggregate to provide. The change programme content has been informed by the May 03 NAO report into Departmental whole life management effectiveness and the NAO continue to monitor progress in change programme implementation.

  (b)  Integrated Project Teams (IPT) with clearly identified customers

    (i)  In excess of 100 IPTs have been formed within the DLO. Appendices to the 4* Customer Supplier Agreements define the relationship that each IPT has with its customer.

  (c)  a better, more open relationship with industry

    (i)  The DLO is working in partnership with the DPA in the implementation of the Department's Key Supplier Management initiative, with senior officials acting as a single point of contact for relationships with individual key defence suppliers. This proactive engagement with industry will lead to an improved understanding of the most important issues, and should help decision-making and forward planning on both sides.

  (d)  more investment during early project phases

    (i)  In his recent directive, re-affirming commitment to the tenets of Smart Acquisition, CDL emphasised the need for scrutiny against Smart approvals criteria to ensure that options and trade-offs are properly explored, and the project is feasible at an acceptable risk.

    (ii)  In addition, the Project Review and Assurance Process, applied throughout the life cycle increases confidence in the delivery of successful project outcomes and manages risk on a transparent basis.

  (e)  effective trade-offs between system performance through life costs and time

    (i)  This is one of the key tests applied when scrutinising the proposed investment in terms of value for money. The DLO approvals team look for a robust Investment Appraisal and benefits realisation plan.

  (f)  new procurement approaches, including incremental acquisition

    (i)  Pathfinder projects, launched under the Defence Logistics Transformation Programme, are leading on new procurement approaches as a key enabler to realise the overall aims of the programme.

  (g)  a streamlined process for project approvals

    (i)  As a result of CDL's directive on Smart Acquisition and Smart Approvals (Aug 04), new scrutiny and approval processes in the DLO are being introduced. These new processes should be fully embedded by Jan 05 and they will lead to a more streamlined overall process.

The current Chief of Defence Procurement commissioned a review of the performance of The Defence Procurement Agency in implementing The Smart Acquisition initiative. Has the Chief of Defence Logistics commissioned such a review? If so, what were the findings of the review? If not, are there plans to do so?

  CDL commissioned the DLO Restructuring Study in 2003 to review the business process of the DLO in line with the strategic goals of the organisation. The Study recommended major structural changes to the DLO, in order to provide a more effective and efficient service to our customers—the Armed Forces. A Restructuring Team and a number of Work Streams were established to develop, test and then implement the detailed processes and new structures required. The Detailed Design report for the new DLO has now been published and Trade Union Consultation on the new design began on 25 October 2004 and is expected to conclude in January 2005. The key benefits of the new DLO organisation which is due to be launched in April 2005, are:

  (a)  A single DLO working to a coherent agenda and in common ways across the whole organisation;

  (b)  The new organisation will have a clear focus on the customer. The Domain 2-stars will provide a single, senior point of accountability for delivering the totality of outputs to our customers based on comprehensive Customer Supplier Agreements. Flexibility and responsiveness to customer requirements will be the key success criteria for the new DLO.

  (c)  Common Enabling Services will support integrated Project Ten (lPTs) in meeting their commitments to customers and enable the effective management of the DLO business. They will replace the Higher Level Budget and Top Level Budget headquarters corporate service functions and provide pan-DLO services using common processes.

  (d)  Joint woridng with the DPA will be pursued where ever possible. There will be joint DPA/DLO Enabling Services where appropriate; Technical Support will be established as a joint service at the outset and others will follow. This will have a coherent and consistent approach to managing projects to ensure effective through life management of equipments.

  (e)  Strong governance will be based on clear authority, responsibility and accountability maximum delegation with further earned autonomy consistent with maintaining coherence. This will be accompanied by an effective assurance system that Identifies non-compliance; Increases confidence In the delivery of successful project outcomes and manages risk on a consistent and transparent basis.

January 2005





11   Ev 57-74 Back

12   Not printed. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 17 March 2005