Select Committee on Defence Written Evidence


E2E Recommendation 40 Follow on Work

HARRIER ROLL FORWARD/BACKWARD INVESTMENT APPRAISAL

  References:

  A.  Streamlining End to End Air and Land Logistics—Final Report dated 1 July 2003.

  B.  D/EA/2/15/6 dated 22 October 2003.

  C.  D/EA/2/15/6 dated 19 December 2003.

  D.  ES(Air)/Wyt/505315/2/55 dated 31 October 2003.

  E.  DARA Proposal for Harrier Roll Back of 2nd Line Maintenance—November 2003.

  F.  JSP 507 MOD Guide to Investment Appraisal.

INTRODUCTION

  1.  Reference A advocates the concentration of support facilities at the logistic centre of gravity in line with UK doctrine, with systems being driven from front to back to achieve the required effect. In the air environment it recommends that activity be concentrated principally at Main Operating Bases and, specifically for Harrier, at RAF Cottesmore.

  2.  The Defence Aviation Repair Agency (DARA) provides significant capacity for depth servicing of aircraft, particularly at its Fixed-Wing Operating unit (FOU) at St Athan in the Vale of Glamorgan. This facility is currently being rationalised with the building of a new super hangar, as part of Project RED DRAGON, which is due to be taken into use in December 2004.

  3.  RAF Cottesmore currently provides a 2nd line maintenance facility that has recently seen the introduction of a pulse line process. It is the intention of the Harrier IPT to develop RAF Cottesmore as a logistical centre of gravity for Harrier, subject to ministerial approval.

  4.  Recommendation 40 of the E2E study recommends that MoD:

    "Put in place a formal, transparent process to evaluate the options to reconfigure support infrastructure in Air. DARA should take an active part in this process both providing alternate options for the provision of Depth support, and competing to manage work on or adjacent to the MOB."

AIM

  5.  The aim of this report is to provide an objective comparison of the incremental costs of:

    (a)  Rolling forward all Harrier on-aircraft depth servicing to RAF Cottesmore.

    (b)  Rolling back all Harrier on-aircraft depth servicing to DARA St Athan.

  6.  The report has been produced by MAS(A) in accordance with the direction given by the E2E Investment Appraisal Reference Group under the chairmanship of DGMO. MAS(A) has reported to DGMO, who has overall responsibility for the work, via the SEA who has directed the assumptions on DGMO's behalf.

METHODOLOGY

  7.  The methodology adopted was agreed at the Reference Group meeting of 22 October 2003 and is detailed at Reference B. The incremental approach was accepted as being less comprehensive but more appropriate given the complexities of analysing full cost and overhead absorption.

  8.  As a result any costs that may be regarded as common to both the roll back and roll forward options have been excluded. The net result is a comparison of incremental costs only, which gives little indication of affordability or overall cost.

OPTIONS

  9.  The Reference Group has determined the two options considered in this IA and MAS(A)'s work has therefore been restricted to these options alone. No account has been taken, at this stage, of the impact of any separate decision on other platforms on this IA.

  10.  It is likely that the costs included when examining Harrier in isolation will be different to those included for Harrier in an IA covering several additional platforms—such as Tornado. This is particularly true in the areas of redundancy costs and additional infrastructure requirements at St Athan.

SOURCE MATERIAL

  11.  A large amount of information has been analysed, provided by several organisations, most notably DARA, Harrier IPT and RAF Cottesmore. All information has been tested for robustness where practicable. Where material has been provided by several sources and is contradictory, we have applied our judgement to arrive at a most likely value.

ASSUMPTIONS

  12.  The key assumptions are listed at Annex A. Where possible a reliable source has been used to inform assumptions and very few have been made with no external input.

EXCLUSIONS

  13.  A number of issues were identified as possibly impacting on this IA which, when balanced against the timeframe for its completion, have necessarily been excluded. Several of these issues were discussed in detail at a workshop held at RAF Wyton on 10 December 2003, where the following was broadly agreed;

    (a)  Supply Chain Savings. It was not possible to quantify these savings in the time available and therefore to understand their magnitude. A less fragmented supply chain is desirable in order to reduce buffer stocks but the major cost driver in terms of spares is their failure rate. This would not change under any scenario.

    (b)  Aircraft Availability. DARA are capable of contracting to provide the level of aircraft availability required by Harrier IPT. There is an additional cost in manpower and time of preparing and delivering jets to St Athan on a regular basis and these costs have been included. There is also a consequential reduction in aircraft availability for this time which has not been quantified in financial terms.

FINDINGS

  14.  The principal findings in the form of an IA are attached at Annexes B and C and are expanded upon below. The overall result, using our initial set of assumptions, is that roll forward offers better value for money. However, the difference in NPVs of £4.416 million may be considered relatively small given the additional non-financial considerations.

  15.  It should also be noted that the IA deals only with incremental costs, therefore the relative difference between the two options is exaggerated by the figures shown. Had the IA been carried out on a full cost basis the differential would represent a much smaller percentage of the respective NPVs.

  16.  Several figures have been highlighted as being key cost drivers and the assumptions associated with them are shown below:

    (a)  CMR. A figure of 237 has been used for CMR with a further 12 support staff, bringing the total to 249. This figure includes off-aircraft personnel who are not within the scope of the IA, however STC have asserted that the splitting of the on and off aircraft work cannot be justified as it would generate diseconomies.

    (b)  Task Hours (Manpower). There are significant differences in the number of hours forecast to achieve the same outputs, no doubt due in part to different processes being employed at each location. After lengthy consideration it has been decided to use a common set of hours and this decision is explained more fully at Reference C.

    (c)  Build of New Quarters. The figures used for the new quarters at St Athan are based on a traditional capital build. It is accepted that there may be a more innovative solution that may alter the cost profile but there is insufficient robust data to support an alternative assumption at this stage.

SENSITIVITY ANALYSIS

  17.  In testing the sensitivity of the NPV to the key variables shown above it has been necessary to identify realistic alternative values. The results are as follows:

    (a)  CMR—On and Off Aircraft Split. If the off-aircraft personnel are excluded from the CMR figure the number of CMR required to move reduces to 189, 180 CMR plus nine support staff. This is calculated by applying the same ratio of on to off aircraft personnel to the depth environment as is consistent across the entire fleet. This does not however change the ranking of the two options but merely closes the gap by £1.502 million to £2.914 million.

    (b)  CMR—Harmony Ratio. It is accepted that presently the harmony ratio for CMR is five providing 20 months home service followed by four months deployment. If this were assumed to be four it would have a significant impact on this IA changing the decision in favour of roll back, as it would reduce the CMR requirement to 109, generating NPVs (costs) of £4.493 million and £6.336 million for roll back and roll forward respectively.

    (c)  Task Hours. An alternative assumption on the number of task hours, based on the highest adjusted forecasts for both 2nd and 3rd Line, produces a total number of task hours of 2.3 million. Under this scenario the result is not altered but the cost of roll forward increases by £0.843 million to give an NPV of £4.295 million compared to the £7.868 million for roll back. Several other scenarios were modelled, including the highest unadjusted forecast for task hours, and the decision was not affected, although all scenarios assumed that each organisation would take the same number of hours.

    (d)  Build of New Quarters. See below.

RISK AND OPTIMISM BIAS

  18.  Harrier IPT and DARA have detailed their risk management proposals at References D and E respectively. No risk premium has been added to either NPV.

  19.  Optimism bias has been applied to the major capital works in accordance with Reference F. Both the new quarters and the paint/strip facility have been considered standard buildings and an optimism bias of 24% applied to the original figures.

SUMMARY

  20.  This report deals specifically with the options for the concentration of depth support for Harrier, following on from Recommendation 40 of E2E (paras 1-4). It aims to provide an objective comparison of the incremental costs of rolling forward all Harrier on-aircraft depth support to RAF Cottesmore, or rolling the same work back to DARA St Athan (para 5). It has been produced by MAS(A) under the direction of DGMO and the SEA (para 6).

  21.  The methodology adopted considers only incremental costs (para 7), the result therefore gives little guidance on affordability (para 8). Only 2 options have been considered and the costs included may well be different if used in an IA covering other platforms as well as Harrier (paras 9-10).

  22.  The best available source material has been used and all assumptions are listed (paras 11-12). Certain potential costs have been identified but excluded due to the constraints of time and the difficulty in quantifying them (para13). The roll forward of the Harrier work presents the best value for money using the base assumptions (para 14). The relatively small figures are a result of using incremental costs only (para 15). Key cost drivers have been identified and the respective assumptions expanded upon (para 16).

  23.  Sensitivity analysis suggests that the decision is only altered by a reduction in the CMR harmony ratio from five to four (para 17). No risk premium has been applied to either scenario but optimism bias has been applied to capital works (paras 18-19).

  Annexes:

  A.  Key Assumptions

  B.  Investment Appraisal—Roll Forward Harrier Option.

  C.  Investment Appraisal—Roll Back Harrier Option.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 17 March 2005