Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Supplementary memorandum submitted by the Environment Agency (X22a)

SUPPLEMENTARY QUESTIONS ARISING FROM THE ENVIRONMENT AGENCY'S WRITTEN EVIDENCE

1.   Para 3.1.2 states that the decision to adopt the Technical Adaptation Committee's recommendation on the Waste Acceptance Criteria was only taken in December 2002—some 18 months later than expected. What were the reasons for the delay?

  The Directive came into force in July 1999 requiring its Technical Adaptation Committee (TAC) to agree Waste Acceptance Criteria by July 2001, the date for Directive implementation.

  The Commission did not establish the TAC Landfill sub-committee until February 2000. The sub-committee were unwilling to adopt existing German and Austrian limit values as most Member States wanted to set limit values related to environmental protection measures. A modelling group was therefore set up in May 2000 to develop these values and did a great deal of work in a short time-scale. However it took over a year to agree the methodology and the limit values for inert waste landfills. Sampling and testing standards under development by the Comité Européen de Normalisation (CEN) were not due to be ready for consultation until July 2002 and the European Commission agreed in April 2001 that the timetable would slip accordingly.

  Further delays occurred when the draft decision document presented at the July 2002 TAC meeting did not accord with the document agreed by the landfill sub committee. It included a new risk assessment provision and a much earlier implementation date than that requested by Member States and as a result it was not agreed. The decision was finally approved in Council on 19 December 2002.

2.   Para 3.1.3 states that "it is not clear whether the LFD constitutes "BAT" (best available technique) for landfill. This has resulted in uncertainty over the regulatory approach to be adopted". Why isn't it clear whether the LFD constitutes BAT?

  BAT is a requirement of the IPPC Directive. The concept of what is "best" and "available" is intended to change over time as knowledge and technology improves. Procedures exist through BAT reference documents (BREFS) and other means to define what constitutes BAT for any given process at any time. Landfills were only included in the IPPC Directive at a relatively late stage and the linkage to the already existing Landfill Directive (LFD) was not properly or fully described.

  As a consequence the LFD contains a number of prescriptive standards, such as those in relation to landfill lining, which seems to run contrary to the principle of BAT. In other respects, such as for landfill gas plant, the LFD is silent and it is therefore assumed that BAT applies.

3.   Para 3.3.1 states: "Despite the construction of liners and barriers absolute prevention [of list I substances into groundwater] is very difficult if not technically impossible to achieve in practice". Can you explain the technical reason why this is so difficult to achieve?

  In English law prevent means to stop—which strictly means even infinitesimal amounts of List I substances should not enter groundwater. All liners/barriers have a finite, albeit normally very low, permeability and over time will allow the migration of a small quantity of landfill leachate, given the large surface area of the base and sides of a landfill. If designed and constructed to the high standards expected of a modern landfill, this leakage will be very small and environmentally trivial. Nevertheless the Groundwater Directive's requirement for absolute prevention will not have been met, even if it complies with the spirit of the Directive in the sense that there is no environmental impact.

  We understand there may be slightly different translations and therefore meanings of the "prevent" clause in the Groundwater Directive across Europe. In practice it is often interpreted as using best endeavours or aiming to prevent, recognising that absolute prevention is unachievable. To meet this problem in the Agency's guidance on landfill risk assessment we require that there should be no discernible discharge of List I substances from the landfill.

  Under the Water Framework Directive (WFD) the existing Groundwater Directive will be repealed in 2013. However, an equivalent level of protection for groundwater is required under the WFD. The details of this are likely to be included within the proposed Groundwater Daughter Directive (GDD), which is currently progressing through the European Council and Parliament. It is notable that in the WFD a more purposive approach is taken and we hope that this will also be reflected in the proposed GWDD. Our position is that Member States should only be asked to use their best endeavours and not be asked to undertake measures that are technically not feasible or necessary for environmental protection.

4.   Para 3.4.2 notes that "Landfill permitting has not proceeded as quickly as we would like". What are the reasons for this?

  Permitting requires an assessment of the impacts of the landfill on the environment and public health. Applicants have to demonstrate that the site will satisfy the requirements of the Landfill, Groundwater, IPPC, Waste Framework and Habitats Directives. This is a challenging exercise for industry and the regulator, particularly where information, such as that required to undertake a hydrogeological risk assessment, is not readily available. Poor quality applications have contributed to delays, as we have to require further information, often repeatedly. Some applications have also been delayed whilst planning issues are resolved (the legislation prevents us from issuing a permit for a waste site unless planning permission is in place).

  We meet regularly with the main trade body (the Environmental Services Association) as well as individual operators to resolve generic issues and have held workshops with the industry to help improve the quality of applications. We continue to review the permitting process to identify efficiencies that we can make, such as the need for discussions on financial provision to commence much earlier in the permitting process. We are currently looking to simplify the process for inert landfill applications to ensure that we can continue to focus resource on those sites that pose the highest risk.

5.   Para 4.1.1 notes that the requirement that the gate price charged by landfill operators must reflect the full cost of operating the landfill, including long-term aftercare, "could have been imposed by Government at an earlier stage". Does the Agency have a view on why this did not happen earlier?

  It may have been considered that this requirement was aimed at those countries where the State is responsible for running waste disposal facilities.

  In England and Wales, local authorities were required to contract out waste collection and disposal services during the 1990s. It may have been assumed that under a situation were market forces prevailed, no further action was required to ensure that the true costs of disposal are reflected in landfill gate prices. Despite this landfill prices remained low with the only substantial upward pressure coming from the landfill tax. The Environment Agency has advocated a price increase in order to drive waste minimisation and reduce society's reliance on landfill. We resisted previous suggestions that we should be given a role in monitoring gate prices as we do not have the necessary expertise and considered it could undermine our role as environmental regulator. Government has been reluctant to intervene in the market place itself or to identify an economic regulator to monitor and potentially influence gate prices. We do think it would be have been prudent to consider other measures needed to reduce reliance on landfill in advance of the co-disposal ban taking effect and that active application of Article 10 should have been explored more fully.

6.   Para 4.1.3 states that "producers will need support from Envirowise, the Agency and others to help them to take advantage of waste minimisation opportunities". Why will they need this support; and can you give examples of the kind of support available?

  Whilst many larger businesses have taken steps to reduce and even eliminate hazardous materials and wastes, the majority of hazardous waste producers will be small and medium sized enterprises (SME's) from a range of often fragmented business sectors. Surveys show that SME's are generally less aware of their environmental obligations and the business opportunities of good product design, waste minimisation and waste recovery and have little capacity to take advantage of good practice. The Environment Agency recognises the difficulties for small businesses and has developed sector specific web-based guidance (NETREGS) that explains regulatory requirements simply.

  Envirowise is an established Government programme that provides support to businesses through a national helpline, publications, tools and on site assistance. The Environment Agency is working with Envirowise to develop new tools for hazardous waste producers including the HAZNET web tool of good practice materials. In addition local business support organisations, such as Groundwork, provide advice to businesses and waste minimisation clubs provide a forum for training and support.

7.   Para 4.1.4 refers to the issue of fragmentiser residue. Can you give more detail about this episode, the problems that arose and the lessons to be drawn?

  The Environment Agency meets regularly with the metal recycling industry to discuss emerging issues and provide support on regulatory and policy issues, particularly those associated with the End of Life Vehicles (ELV) Directive. That Directive has required, since November 2003, vehicles to be "depolluted" which involves removing the hazardous components.

  In the lead up to the co-disposal ban the shredder industry raised concerns about the suitability of the analytical method most commonly used by industry for determining the mineral oil content of fragmentiser waste. They had been unable to persuade landfill operators that fragmentiser residues were non-hazardous and were unwilling to pay the much higher costs of landfilling hazardous waste. This was presented to the Environment Agency as a problem for us to resolve on the 12 July, with the threat of all the shredder operators shutting their doors to ELV's on 16 July. This would have had the effect of increasing vehicle abandonment.

  Elliot Morley called an urgent meeting on 19 July with all parties to clarify the underlying issues and agree a way forward. The Environment Agency met with the key stakeholders on 20 July and was able to agree and issue a statement on 21 July. This statement gave comfort to the waste management industry that, provided ELV's had been depolluted and this could be evidenced through the waste transfer note, the residue would be treated as non hazardous. The Environment Agency also offered to let a contract to develop a form of sampling and testing that would verify the hazardousness, or otherwise, of fragmentiser residue. It took a number of months for industry to agree the methodology for this work and the findings will be delivered shortly. The original statement has therefore been reviewed and reissued whilst the Environment Agency continues to work with the shredder and waste management industry to ensure a long term solution is developed and subsequently signed up to by all parties.

  The episode highlighted the need for waste producers and waste management service providers to engage at an early stage to understand the impacts of legislative change and work together to develop solutions. We consider trade bodies have an important role in this respect. We have organised a seminar on the Waste Acceptance Criteria, jointly with Government, to bring various trade bodies together and ensure such debate happens well in advance of the July 2005 requirements, and avoid a repetition of the fragmentiser issue.

8.   Para 5.5 states that there needs to be a commitment to the implementation of Defra's waste data strategy. Are you confident that there is such a commitment?

  We believe that there is a clear commitment to the data strategy. This will need to be reflected through the provision of additional resource for the Environment Agency to allow it to develop the necessary IT systems to implement its role effectively.

  We are required to provide information on wastes and their management to the Commission under the Waste Statistics Regulation. We do this by carrying out national surveys of a sample of industry and commerce. Although the sample is several thousand and the work costs several million pounds, we can only reach a small proportion of the 1.5 million businesses that exist and the figures are necessarily estimates.

  It also takes a great deal of time to collate the data and to clean and complete it to a stage where we can use it to produce the estimates. This means that information tends to be published later than we would like.

  We agree with the phased approach in the Data Strategy and we support the use of regulatory mechanisms wherever possible. To give effect to the waste data strategy will mean we have to develop new software systems to record data returns from licensed and exempt sites. We consider this to be a better use of the money that Government would otherwise have to provide to carry out surveys and should be cheaper than traditional surveys.

30 November 2004





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 17 March 2005