Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Memorandum submitted by the Department for Environment, Food and Rural Affairs (X8)

A.  INTRODUCTION

1.  This memorandum covers implementation of the Landfill Directive in England as the devolved administrations have responsibility for policy and implementation in their countries.

Summary

  2.  The Government is committed to reducing the UK's reliance on landfill, in order to reduce its environmental impact and because landfilling is a missed opportunity to recover value from waste. This is part of the UK's commitment to more sustainable waste management in line with the objectives and policies set out in Waste Strategy 2000. Implementation of the provisions in the Landfill Directive is a key component of this commitment.

  3.  The Landfill Directive requires a fundamental change to previous UK practices. In particular the ban on the co-disposal of hazardous waste and non-hazardous waste resulted in the number of landfill sites available to accept hazardous waste post 16 July 2004 was reduced from some 230 to around 30. In general, however, the capacity within those sites (1.5-2 million tonnes per annum) is considered adequate to meet demand.

  4.  Annex II of the Landfill Directive sets out general principles for acceptance of waste at landfills, general procedures for testing and interim guidelines. This was supplemented by a Council Decision of December 2002 on the criteria and procedures for accepting waste at landfills. The main requirements of the Decision were implemented in England and Wales by the Landfill (England and Wales) (Amendment) Regulations 2004.

  5.  Article 5(2) of the Landfill Directive sets challenging targets to reduce the amount of biodegradable municipal waste (BMW) being sent to landfill to 35% of BMW arisings in 1995 by 2020; a reduction of almost 12 million tonnes compared with 1995 levels. Waste Strategy 2000 sets out a range of policies to help deliver the step change in waste management needed to meet these targets including the Landfill Tax, with the increases to bring it to £35/tonne in the medium term; establishment of Waste and Resources Action Programme (WRAP) to stimulate markets for recycled materials; setting statutory recycling and composting targets for local authorities; and increased funding for local authorities including the National Waste Minimisation and Recycling Fund and PFI credits. These have been strengthened in the last eighteen months with the establishment of Defra's Waste Implementation Programme to provide support for local authorities.

  6.  In addition the Government is introducing a scheme of tradable landfill allowances to provide local authorities with some flexibility to meet their required reductions in the most economically optimum way for them. The Waste and Emissions Trading Act 2003 provides the legal framework for schemes for limiting the amount of BMW that waste disposal authorities (WDAs) in the UK send to landfill. In England, regulations provided for in the Act will establish the Landfill Allowance Trading Scheme (LATS). The scheme, due to begin in April 2005, is based on allocating to WDAs a decreasing number of landfill allowances for each year from 2005-06 through to 2019-20.

  7.  While municipal waste arisings continues to grow, the quantity ending up in landfill is falling in both percentage terms and actual amount as a result of government actions identified in paragraph 3.

  8.  In addition to changes to legislation affecting landfills, new draft Hazardous Waste Regulations are now out for consultation. The overall aim of the Regulations is to ensure that the requirements of the Hazardous Waste Directive are fully implemented in a cost effective way which minimises additional burdens on industry.

General background

  9.  The Landfill Directive is a complex and highly technical piece of legislation that has serious ramifications for waste management in this country, representing a step change in current practice not only for landfill site operators but for all waste producers. The Directive is particularly challenging for the UK, as some of its requirements are practices that are already in place in other member states. In order to achieve as smooth a transition as possible, the Government has consulted widely and frequently before implementing the provisions of the Directive.

  10.  Annex A sets out a full chronology of events involved in implementing the Directive. The comprehensive consultation process contributed to the UK being 11 months late in transposing the technical and regulatory aspects of the Directive and 16 months late in transposing the Article 5(2) targets (see paragraphs 27-29); as a result the UK was infracted by the European Commission.

  11.  Infraction proceedings have also been taken against Germany, Belgium, Portugal, Luxembourg, Greece, Italy, and Finland for late implementation of the Landfill Directive. France, Spain and Greece have also had infraction proceedings started against them because of illegal landfill sites.

B.  GOVERNMENT ACTIONS: HAZARDOUS WASTE

  12.  To address key issues arising from implementation of the Landfill Directive, Defra has:

    —  set up the Hazardous Waste Forum and the Landfill Directive Implementation Group—membership includes representatives of waste producers such as the CBI, the Chemical Industries Association and the Federation of Small Businesses as well as representatives of the waste management industry, regulators, local authorities, the Environment Agency, devolved administrations and Government Departments;

    —  published the Hazardous Waste Forum action plan on the reduction and environmentally sound management of hazardous waste;

    —  with the Environment Agency, set up the Landfill and Hazardous Waste Implementation Programme (LHIP);

    —  assisted in the issue of guidance material by the Environment Agency, including technical guidance on assessing and classifying hazardous waste;

    —  organised seminars and taken part in those organised by others (eg the Environmental Services Association, the Chemical Industries Association, the Engineers Employers Federation, the Parliamentary Sustainable Waste Group and Envirowise);

    —  held bilateral meetings with a wide range of industry and other interests; and

    —  commissioned research and other projects (either direct or though the Hazardous Waste Forum or the Environment Agency).

Hazardous Waste Forum

  13.  The Hazardous Waste Forum was established by the Government in December 2002, to bring together key stakeholders to advise on the way forward on the management of hazardous waste. The Forum has a strategic role in considering the demands on industry of existing and forthcoming legislation and providing a means of bringing all relevant sectors together to work towards the goals of hazardous waste reduction and managing it safely. It has set out advice on the way forward for hazardous waste management. The Forum produced an Action Plan in December 2003 and has been pressing Government and the Environment Agency to deliver the key actions and decisions that are needed. The Forum has also done some valuable work in assessing likely future landfill and treatment capacity for hazardous waste and communicating the very real concerns of the waste management industry. The terms of reference for the Forum are at Annex B.

Landfill and Hazardous Waste Implementation Programme (LHIP)

  14.  In order to manage implementation of both the Landfill and Hazardous Waste Directives, Defra and the Environment Agency jointly set up the Landfill and Hazardous Waste Implementation Programme (LHIP). The Programme brings together all of the activities related to the change in requirements under a single reporting structure, with dedicated management and communications resources and a coherent view of activities across its breadth. The LHIP is managed as a Programme within Defra, and involves all the Governmental bodies related to the change. This includes: the Environment Agency, DTI, ODPM, the Welsh Assembly, the Scottish Executive, DOENI and Envirowise. The LHIP Programme has a full-time professional programme office, which produces weekly status reports for those involved, coordinates the activities of the Programme, maintains an up-to-date register of risks.

Hazardous Waste Regulations

  15.  In addition to changes to disposal of hazardous waste arising from the Landfill Directive, there are other changes arising from the requirements of the Hazardous Waste Directive. A consultation on new Hazardous Waste Regulations is now in progress. The proposed new regulations in England will replace the Special Waste Regulations 1996 (the 1996 regulations) and implement the revised European hazardous waste list, now incorporated into the European Waste Catalogue. The 1996 Regulations have provided a system of control to ensure that hazardous wastes are soundly managed from the point at which they are produced to the final point of disposal. They were intended to implement the requirements of the Hazardous Waste Directive and the 1994 EC Hazardous Waste List.

  16.  On 1 January 2002 changes to the Hazardous Waste List were applied in the EU and the list was incorporated into the European Waste Catalogue. The 1996 regulations need amendment to take account of these changes. In particular, the revised list classifies more waste as "hazardous" than was previously the case. The review of the Special Waste Regulations provides an opportunity to consider the application of the current procedures for consigning special waste, and to streamline those procedures where possible. The aim is to ensure that the requirements of the Hazardous Waste Directive are fully implemented in a cost effective way which minimises additional burdens on industry.

Site classification

  17.  As part of the 2002 conditioning plan exercise required by the Landfill Regulations, sites had to say what classification they required. Around 230 landfills opted for a hazardous waste classification, most so they could continue as co-disposal sites (ie being able to take all types of waste, including municipal) for as long as possible. Under the interim national waste acceptance criteria set out in Schedule 1 of the Landfill Regulations:

    —  Hazardous waste sites could accept wastes on the Hazardous Waste List. In addition, until July 2004 they can also accept non-hazardous wastes;

    —  Non-hazardous waste sites could accept all wastes accept hazardous wastes. However, stable and non-reactive hazardous wastes can go to non-hazardous sites as long as they are landfilled in separate cells.

    —  inert waste sites can accept wastes on the list of wastes in Schedule 1 and any other wastes which fall within the definition of inert waste in the regulations.

    —  The criteria in Schedule 1 of the current Regulations will be replaced on 16 July 2005 by the waste acceptance criteria in the Landfill (England and Wales) (Amendment) Regulations 2004. These set more detailed criteria based on the achievement of limit values following leaching tests on the waste.

  18.  With effect from 16 July 2004, the Landfill (England and Wales) Regulations 2002 banned the co-disposal of hazardous waste and non-hazardous waste and waste can only go to a landfill site classified to accept such waste (ie hazardous waste can only go to hazardous waste landfills, non-hazardous to non-hazardous landfills and inert waste to inert and non-hazardous landfills). From that date, co-disposal (hazardous) sites had to decide whether to continue as hazardous sites and so accept only hazardous waste, or be reclassified as non-hazardous and accept all wastes accept hazardous wastes (and stabilised, non-reactive hazardous wastes in separate cells). The result of this change was that the number of landfill sites available to accept hazardous waste was reduced substantially (see below).

Landfill capacity

  19.  The Environment Agency has received 18 applications for permits to operate merchant hazardous waste landfills post June 2004. A further 12 applications were received to operate in-house landfills. Of this total of 30 applications, permits have been issued for nine sites, five applications have been refused, two have planning issues to resolve and the remainder are under consideration. In total, the capacity amounts to 1.5-2 million tonnes per annum. While the aim to complete the consideration process before 16 July in most cases was not achieved, sites with a current waste management licence to accept hazardous waste can continue to do so.

  20.  In addition to the above, the Environment Agency has received 39 applications to operate separate cells for stable, non-reactive hazardous waste at non-hazardous waste landfills; six permits have been issued, two applications have been refused and the remainder are under consideration. These figures are continually updated and the latest position can be found on the Environment Agency website (www.environment-agency.gov.uk)

Alternative disposal options

  21.  Many hazardous waste streams are not generally landfilled at present. For those that are, research for the Defra concluded that there was sufficient alternative disposal systems (in use or planned) to cope with the large volume of organic process waste streams requiring diversion from landfill.

  22.  Stable and non-reactive hazardous wastes that are not banned from landfill can be disposed of in separate cells at non-hazardous landfill sites. The Directive will also act as a driver for waste producers to minimise waste arisings and recycle, re-use or recover in order to divert waste from landfill.

Waste acceptance criteria

  23.  The Landfill Directive agreed by Council in 1999 contained waste acceptance procedures. Annex II sets out general principles for acceptance of waste at landfills, general procedures for testing and interim guidelines. However, the Council decided that more detailed procedures were required if the overall objective of the Directive was to be met consistently in member states. The Commission was very slow to come forward with a proposal to met the Council's request and were only able to do so as a result of the work of a modelling group, chaired by the UK.

  24.  Council agreed a revised proposal (by unanimity) on 19 December 2002 which was published in the Official Journal on 16 January 2003 as Council Decision 2003/33. A provision in the Decision allowed only 18 months for it to be transposed into national law (rather than the more usual two years) as this had to be achieved by 16 July 2004. For England and Wales, this target was met, with the Landfill (England and Wales) (Amendment) Regulations 2004 coming into force in June 2004, for implementation on 15 July 2005.

C.  GOVERNMENT ACTIONS: ARTICLE 5(2) TARGETS

Background

  25.  Article 5(2) of the Directive sets challenging targets to reduce the amount of biodegradable municipal waste (BMW) being sent to landfill. The reduction targets set by the Directive are:

    —  by 2006 to reduce the amount of BMW going to landfill to 75% of that produced in 1995;

    —  by 2009 to reduce the amount of BMW going to landfill to 50% of that produced in 1995;

    —  by 2016 to reduce the amount of BMW going to landfill to 35% of that produced in 1995.

  The Directive allows member states which landfilled over 80% of their municipal waste in 1995 to postpone meeting the targets by up to four years and the Government intends to make use of this derogation. National target dates of 2010, 2013 and 2020 are set out in the Waste and Emissions Trading Act .

Trading scheme

  26.  In October 1999, in the consultation paper "Limiting Landfill"[1] the Government outlined several options for meeting the targets in Article 5(2) of the Directive. The option of a tradable permit (now allowance) scheme was supported by over 70% of the responses to the paper. As a result Waste Strategy 2000 signalled the Government's intention to introduce a system of tradable landfill allowances in England to limit the amount of BMW authorities could landfill.

  27.  The Government published a second consultation paper, Tradable Landfill Permits[2] in June 2001, outlining the basis of how the scheme might work and suggesting options for its implementation. In the light of responses to the second consultation paper the Government introduced the Waste and Emissions Trading Bill for consideration by the Houses of Parliament in November 2002. The Bill, which became an Act in November 2003, sets the framework for a landfill allowance trading scheme and provides for the details of the scheme to be established in regulations made by the Secretary of State.

  28.  The first set of Regulations[3], sharing the UK total of allowances between the four component countries, have been agreed by Parliament. England's Landfill Allowances and Trading Scheme Regulations will be considered by Parliament in the Autumn. Each local authority was notified of its provisional allocation for each year of the landfill allowances scheme (2005-06 to 2019-20) on 11 August. The notification explains how each authority's landfill allowances has been calculated, gives them an early indication of the allocation they will receive under the scheme and provides an opportunity to comment on the calculation of their provisional allocation and to notify Defra of any errors in the data used by 8 October 2004.

Data

  29.  Defra publishes estimates and final figures on municipal waste arisings and management in its Municipal Waste Management Survey. The latest results are based on information supplied by local authorities in England for the financial year 2002-03.

  Municipal waste arisings and management:

    —  The total amount of municipal waste has continued to rise to an estimated 29.3 million tonnes in England in 2002-03 compared to 28.8 million tonnes in 2001-02, an increase of 1.8%.

    —  In total, 24.8% (7.3 million tonnes) of municipal waste had some sort of value (recycling, composting, energy from waste) recovered from it in 2002-03, a rise from 22.4% (6.4 million tonnes) in 2001-02.

    —  The proportion of municipal waste being recycled or composted increased from 13.6% in 2001-02 to 15.6% in 2002-03. The proportion of waste incinerated with energy recovery has remained roughly constant at just under 9%.

    —  The proportion of municipal waste being disposed of in landfill has decreased from 77% in 2001-02 to 75% in 2002-03.

    —  For the first time in recent years the actual tonnage of municipal waste disposed of in landfill has also decreased slightly from 22.3 million tonnes in 2001-02 to 22.0 million tonnes in 2002-03. It is now about the same level it was in 1999-2000.

  WIP/WRAP

  30.  The Waste Implementation Programme (WIP) was set up by Defra in June 2003. WIP is focused on supporting local authorities to deliver improved services and meet their targets. These include statutory recycling and composting targets for each local authority in England. The national target of 17% of household waste recycling and composting by 2003-04 is a key milestone on the way to meeting the Landfill Directive targets.

  31.  WIP is taking forward eight work-streams, three of which are being managed by WRAP, that, alongside policies set out in Waste Strategy 2000 (eg increases in landfill tax), are aimed at driving waste management solutions up the waste hierarchy. WIP is heavily focused on delivery—looking to make a strong positive impact and work with stakeholders. The eight WIP programmes are:

    —  Local authority funding

    —  New Technologies

    —  Local Authority Support

    —  Waste Minimisation (WRAP takes the lead)

    —  Kerbside (WRAP takes the lead)

    —  Waste Awareness (WRAP takes the lead)

    —  Data

    —  Research.

  32.  WIP is making good progress in rolling-out these programmes. For example, WIP's Local Authority Support Unit has provided a range of targeted support measures, which can be found on the Defra website at http://lasupport.defra.gov.uk/. Issues covered on the website include procurement; strategy making; kerbside, including a recyclables capture toolkit; estates; civic amenity sites and bulky goods collections. Additionally, the Local Authority Support Unit has offered all local authorities up to £20,000 of direct consultancy support, including to assist planning for the introduction of the Landfill Allowance Trading Scheme.

  33.  Preferred bidders have now been identified to take forward a first tranche of new technology demonstration plants. This will give local authority and industry stakeholders the opportunity to see first hand the operation of different waste treatment technologies that offer a viable alternative to landfill. The aim is to have five operational pilot plants in place by end-2005, with a further five by end-2006. A separate data centre will bring together current data and research on new and emerging technologies, including the results of the demonstrator projects. A support programme has also been set up to ensure that these results are widely and effectively disseminated to all the relevant stakeholders.

  34.  Work is also underway to improve the effective co-ordination, provision and dissemination of data and research on different waste streams. A 3-year national data strategy will be issued for public consultation in autumn 2004. The aim is to meet the data needs of local authorities (who should be better equipped to develop long-term planning for their waste management activities) and inform investment decisions by the waste industry. Defra plans to publish a new waste R&D strategy in late September, aimed at delivering a sound evidence base for better-informed policy development, implementation, monitoring and evaluation for sustainable waste management at both the national and local levels. This will include effective mechanisms for access to, and dissemination of, research results.

  35.  WRAP is making good progress on waste minimisation with a Home Composting Programme, delivered collaboratively with local authority and community partners. Work is also underway to support the development of a Real Nappies Programme, including research on stakeholder perceptions and assessing different communication and awareness raising options.

  36.  WRAP's major Retailers Initiative is currently underway, seeking to work with the top retail supermarket chains. Retailers and producers can help to reduce waste by eco-design to ensure products are more recyclable and friendlier to the environment. This could reduce the amount of packaging/waste passed on to households. WRAP is currently developing a strategy for engaging retailers at a high level to secure agreement to waste reduction measures. Hand-in-hand with the Retailer Initiative is a Waste Minimisation Innovation Fund, aimed at providing support for retailer-led innovation projects. The fund will provide resources (research, pilot programmes, professional services and capital grants) to retailers wishing to work with WRAP on waste minimisation projects.

  37.  WRAP's separate work on market development for recyclates has progressed well since its establishment in 2001. Over the first three years of it's work programme, WRAP have played a key role in increasing recycling capacity in the UK. Across WRAP's material streams (paper, plastic, glass, wood and aggregates) over 1.3 million tonnes of extra capacity is operational or under construction, with a further 1.8 million tonnes in delivery. WRAP projects have also secured over £120 million investment from the private sector. Through their work WRAP projects have identified new uses for recycled materials such as lightweight lorry panelling, fluxing agents, water filtration media and carpet underlay. The market development programme has developed and launched a number of Publicly Available Specifications for materials, to set recognisable standards and thereby increase certainty in the quality of recycled materials. WRAP have also provided training to many local authorities and voluntary groups, run seminars and events and have developed a number of well received web resources, such as the Aggregain Website.

  38.  WRAP's market development programme is set to continue to at least 2006 and is aiming to build on the results and successes of its original work programme to further increase recycling capacity, turn the results of R&D projects from the first three years into commercially viable projects, deliver further training and advice and encourage further investment in recycling businesses.







FUNDING FOR LOCAL AUTHORITIES

  39.  The delivery of national policy objectives for waste—including the obligations imposed by the EU Landfill Directive—will increase local authority waste management costs and requires significant new investment in collection systems, recycling facilities and waste processing plants.

  40.  The Private Finance Initiative (PFI) is increasingly one of the key mechanisms for funding investment in waste services. Government has increased resources provided for waste PFI projects in recent years. To date, 16 waste PFI projects have been approved, of which nine are operational. The other seven are at procurement stage. Over the next six months another four projects are likely to be approved with combined PFI credits of £207 million. PFI is making a significant contribution to the delivery of key waste management objectives. and these projects help to promote new technology options as Defra's selection criteria places considerable emphasis on recycling and the use of innovative approaches.

  41.  Additional funding support for local authorities is provided through the Waste Minimisation and Recycling Fund ("The Challenge Fund"). In February 2004, Ministers announced over £40 million in additional funding to help local authorities provide improved waste services (particularly kerbside recycling) to around 2 million extra households. These projects will also divert some 300,000 tonnes of waste from landfill each year. A total of £223.8 million has been awarded to local authorities, outside of London, since 2002-03.

  42.  Defra has made available a £20 million targeted recycling grant for local authorities in 2004-05 to address the pressure each authority faces to invest in its waste management services this year—particularly to meet its Statutory Performance Standard for recycling and composting in 2005-06. A formula has been designed to distribute the grant between local authorities according to need to spend on waste management services.

  43.  The consultation on the Government's proposed design for the Waste Performance Reward Grant (£45 million in 2005-06, £105 million 2006-07, £110 million 2007-08) ended on 31 March. Officials are continuing to analyse responses received, many of which expressed legitimate concerns. The Government will make an announcement on the final design in due course.

  44.  The 2004 Spending Review provided an extra £150 million PFI credits per year by 2007-08, and an extra £35 million over two years (2006-07 and 2007-08) for the new waste management Performance Reward Grant to enable investment in sustainable waste management. This was in addition to increases of £389 million in 2006-07 and £823 million in 2007-08 in local government funding through the Environmental, Protective and Cultural Services (EPCS) block grant, which funds activities including waste management. This increase in EPCS funding includes the recycling of revenues from the Landfill Tax escalator to local authorities.

PLANNING

  45.  Diverting waste away from landfill requires the development of a range of other waste management facilities. The planning system plays a critical role in enabling the delivery of such facilities. Defra is working closely with the ODPM in a revision of the planning policy guidance note (PPG10) that sets out national planning policy on waste management. The revision is part of the Government's drive to streamline planning policy to give greater clarity in terms of the outcomes to be achieved. The ODPM expect to consult on a draft of the new planning policy statement later this year. This will build on the planning reforms already being taken forward by the Deputy Prime Minister following the enactment of the Planning and Compulsory Purchase Act 2004.

  46.  Alongside this work, Defra will be consulting on draft guidance on the preparation of municipal waste management strategies. These will help inform the planning process as well as providing a mechanism for local authorities to plan the future management of municipal waste and associated investment decisions.

  47.  The department has published an independent Review of the Environmental and Health Effects of Waste Management which has been sent to all local authorities. In the foreword to the report the Minister of State, Environment and Agri-Environment, urged local planning authorities to press ahead urgently with the task of approving planning applications for waste management facilities. Mr Morley has also written to all local authorities in England on the importance of having hazardous waste facilities in place.

D.  CONCLUSION

  48.  The Landfill Directive signals a major change in the way the UK deals with its waste. The UK supports the overall aim of the Directive "to prevent or reduce as far as possible the negative effects on the environment from the landfilling of waste". Moreover, the UK also views landfilling as unsustainable as it wastes resources and creates potential environmental problems for generations to come. It therefore also supports the underlying principle of the Directive that wherever possible, alternatives to landfill that have less environmental impact and makes better use of resources should be explored.

  49.  The new Hazardous Waste Regulations will streamline procedures in dealing with hazardous waste from point of production to point of disposal/reuse where possible, while retaining the necessary controls. The overall aim is to ensure that the requirements of the Hazardous Waste Directive are fully implemented in a cost effective way which minimises additional burdens on industry.

  50.  The Government cannot achieve those goals alone. Waste producers, waste managers, regulators, local authorities, representative organisations and consumers must all work with Government and each other if the very real benefits on offer by the Landfill Directive are to be fully realised.

Annex A

WASTE POLICY AND THE LANDFILL DIRECTIVE
Chronological Order of Events

April 1999
Landfill Directive agreed in Council of Ministers
July 1999Landfill Directive published in Official Journal
October 1999Limiting Landfill consultation
August 2000Implementing the Landfill Directive (1st) consultation
June 2001Tradable Landfill Permits consultation
July 2001Transposition deadline for Landfill Directive
October 2001Implementing Landfill Directive (2nd) consultation
June 2002Landfill Regulations come into force
November 2002Waste and Emissions Trading Bill presented to Parliament
December 2002Council Decision on Waste Acceptance Criteria agreed
December 2002Hazardous Waste Forum launched
January 2003Council Decision on Waste Acceptance Criteria published
August 2003Landfill Allowances Trading Scheme (LATS) consultation
September 2003Waste Acceptance Criteria (WAC) consultation
November 2003WET Bill Royal Assent
December 2003Landfill and Hazardous Waste Implementation Prog.
December 2003Publication of Hazardous Waste Forum Action Plan
March 2004WAC consultation outcome
April 2004LATS consultation outcome
June 2004Landfill (Amendment) Regulations [WAC] come into force
July 2004Landfill Scheme Regulations come into force
July 2004Hazardous Waste Regulations consultation


Annex B

WASTE POLICY AND THE LANDFILL DIRECTIVE

HAZARDOUS WASTE FORUM: TERMS OF REFERENCE

  The Forum's terms of reference are:

    (a)  to advise on the way ahead over the next five years for reducing hazardous waste and better managing it;

    (b)  to identify opportunities to reduce the production of hazardous waste and to recover that which is produced;

    (c)  to consider the impacts of existing and forthcoming legislation, and advise on Government/Agency action; and

    (d)  to provide up-to-date and reliable data.





1   Limiting Landfill: A Consultation paper on limiting landfill to meet the EC Landfill Directive's targets for the landfill of biodegradable municipal waste. Back

2   Tradable landfill permits: A consultation paperBack

3   The Landfill (Scheme Year and Maximum Landfill Amount) Regulations 2004 (2004 No 1936). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 18 March 2005