Select Committee on Home Affairs Written Evidence


41.  Tenth supplementary memorandum submitted by HM Prison Service, Home Office

PRISON SERVICE HQ REVIEW OF INDUSTRIES: PROGRESS UPDATE ON RECOMMENDATIONS AS AT

2 DECEMBER 2004

Introduction

  The review of prison industries was undertaken as part of the wider review of Prison Service headquarters. The Prison Service Management Board accepted all 44 of the reviews recommendations and agreed a detailed implementation plan.

Summary of progress against recommendations

  2.  The target date for implementing all recommendations is 31 March 2005, though many of the actions will continue beyond that date. The attached table (Annex A) indicates the progress that has been made against each recommendation—broken down into 27 separate workstreams.

  3.  Progress has been made against all 44 recommendations. Two recommendations (on splitting the material budget between purchased goods and materials and providing additional clothing and textile workshops) have not been implemented following further examination.

6 December 2004

ANNEX A—CHECKLIST OF PROGRESS AGAINST RECOMMENDATIONS

Statement of Purpose For Prison Industries Recommendation (1)

  To remove confusion over why we have prison industries and to give them clear direction; the objectives of prison industries must be clearly stated. Early action should be taken to promulgate a Statement of Purpose for prison industries against which future activities can be assessed and evaluated. (Page 24)

  Implemented. The statement forms the starting point for all prison industry strategies and policies and has been incorporated into the revised draft performance standard for industries. Signs displaying the statement of purpose have been produced internally and should be on display in all workshops.

Annual material budget Recommendation (2)

  FC&A, in conjunction with Planning Group, should allocate funds to ESS[29] for the materials budget at the beginning of each financial year based on the average predicted prisoner population for that year. (Page 57)

  Implemented—this is continually monitored.

Budget for purchase of finished goods Recommendation (3)

  The raw materials budget and the funds currently retained by ESS for purchasing finished goods should be separated. The method of distributing funds for the latter should be considered by FC&A[30]. (Page 57)

  Not implemented. The proposal to split the material budget between purchased goods and materials was considered to be too restrictive and did not allow for the flexibility required to meet customer supply requirements. ESS continually reviews the material budget ensuring that funding is allocated to meet the central purchase of materials and finished goods. ESS has also moved from a twice a year allocation to establishments of raw materials to a three times a year system. This will lead to improve the allocation of funding for local purchases.

Setting up Hard Charging Recommendations (4, 30, 31, 32)

  Full hard charging based on the cost of materials and a financial incentive for production should be introduced for the internal market, on a phased basis, with clothing and textiles being charged first, followed by the rest in the following year. (Page 55)

  A small range of high consumption goods are being piloted for hard charging this financial year. Evaluation report with recommendations due to be complete early 2005.

Setting up Industries Management Board Recommendation (5)

  An internal Industries Management Board with representatives drawn from the operational line should be established to govern the operation of industries. (Page 28)

  Implemented

Setting up Industries Advisory Group Recommendation (6)

  An Industries Advisory Sub-Group should be set up with membership comprised of non-executive members from private sector industry, and representatives from within prison industries, to ensure that prison industries keep in line with developments in the modern labour market. (Page 28)

  Implemented

Make or Buy Process Recommendations (7, 8)

  The Policy Section of ESS should manage the Make or Buy process taking into consideration:

    —  support of prison industries strategy;

    —  total cost of manufacturing compared to the purchase price; and

    —  the cost of providing alternative occupation for prisoners. (Page 62)

  Implemented and ongoing—process in place using standardised format. All clothing and textile, woodwork and engineering products due to be completed by end of year.

Internal market mandatory purchase Recommendation (9)

  Where a decision is taken for the Service to make a product its purchase by establishments should be mandatory, thereby ensuring that prison workshops have a continuous supply of work. (Page 62)

  Implemented and ongoing. Prison Service Instruction 23/2004 (Hard Charging) has started this process by making the three products currently being piloted mandatory purchases. The report on the hard charging pilot is due to make its recommendations in January 2005, which will confirm whether on not to expand the range of mandatory purchased items.

Stock responsibility & control Recommendation (10, 11)

  The Head of ESS should take responsibility for ensuring that adequate stock levels are maintained at Branston. (Page 73)

  Implemented. On target to reach agreed stock levels. Processes in place to ensure production varied to ensure sufficient stock.

Capital and modernisation equipment Recommendation (12, 13)

  ESS should compile and monitor all large industries equipment items, and from this database and other information should constantly plan for a modernisation and replacement programme. (Page 76)

  Implemented and ongoing. A capital review is underway to identify all plant and equipment used in industries. Capital modernisation and strategic plans across all sectors due by end of year.

  When new or replacement equipment is allocated to establishments it should be accompanied by an analysis of the installation and expected maintenance costs. (Page 76)

  Implemented

Management information & Industrial Performance Recommendation (14, 16)

  A balanced or weighted scorecard approach should be developed for monitoring the performance of prison industries. This should be worked up with close involvement of Planning Group, and should include consideration of how management information should be collected, shared and acted upon. (Page 79)

  New approach developed—due to be implemented before end of the year.

Proposal to close prison workshops Recommendation (15)

  With the exception of short-term operational exigencies, proposals to close prison workshops must be submitted to the Industries Management Board for a decision. (Page 28)

  Implemented. Prison Service Instruction 38/2004 (Workshop Closure) was issued on 1 August 2004. This instruction made it mandatory that Governors had to consult and seek agreement before any workshop closure or significant re-designation.

Prisoner Employment in Workshop    Recommendation (17)

  Consideration should be given to using prisoners in a more constructive manner in workshops, eg administrative and statistical tasks, and in warehousing functions such as storekeeping and forklift truck driving. (Page 23)

  Ongoing implementation. There is increased evidence of prisoners being given roles as described in the recommendation. There is however potential to develop this further.

IPP Audit Challenge Recommendation (18)

  An audit should be carried out (by a small team drawn from ESS staff) to establish the accuracy of the FY2002/3 IPP submissions. The IPP submissions should be compared to the outturns both in terms of regime figures as well as the financial figures. If, as the team suspects, the figures are not robust, the instructions on completing IPP9s should be reviewed and the returns for FY2003/4 amended to reflect reality. As these figures are part of the process used in deciding the levels of raw materials budgetary allocations it is essential that they are as accurate as possible, and therefore this is a crucial recommendation. (Page 26)

  Implemented. The review has been completed and resulted in a recommendation to replace the planning system. See recommendations 14 and 16 for subsequent actions.

Quotes for Contract Work Recommendations (19, 34)

  ESS should remind establishments of the need to ensure that quotes for work follow central guidelines. ESS should ensure that the guidance on pricing for work is reviewed and updated. (Page 26)

  Establishments should ensure that Government Accounting rules are followed when manufacturing goods for external sale (Page 66)

  Both implemented. Guidelines for the use of standard conditions of sales and service have been issued to the operational line and HQ staff. The costing and pricing guidelines for prison industries agreed between ESS and FC&A were issued through an ESS bulletin on 13 August 2004.

Setting up Policy Team Recommendations (20, 21)

  A small policy team should be established within ESS (responsibilities are outlined on page 33 of the review).

  The reporting line for the policy team should be reassessed six months after the policy team is in place.

  Both implemented

PS Business Improvement Policy & Status Recommendations (22, 23)

  The proposed Policy Team in ESS should prepare a PS Business Improvement Policy. Each establishment with industrial workshops should be given the opportunity to introduce any relevant parts of the Policy. Any internal auditing of adherence to the Policy should fall to the local audit team. Updating the Policy should fall to the policy team in ESS but any accreditation to ISO standards should be for an establishment to decide. The establishment would then be responsible for providing any resources necessary for such accreditation including the provision of any additional auditing which would have to be provided externally. (Page 35)

  Implemented and ongoing. Prison Service Performance Standard 12 reviewed and refocused on prison industries. A complete evaluation report on business improvement systems is due to be conducted by January 2005.

Evaluate ESS relocation to Branston Recommendation (24)

  The Review Team recommends that a thorough costing exercise be undertaken in conjunction with Estate Management Group immediately with a view to ESS being relocated to Branston at the earliest opportunity. This has the potential for savings of at least c£620k per annum. (Page 39)

  Implemented. A further evaluation found the business case for moving ESS weak and cost prohibitive. The potential claimed savings did not stand up to further scrutiny.

Implement ESS Organisation structure Recommendation (25, 29, 35)

  The central support to industries (ESS) should be redrawn along functional lines. This should improve efficiency both at the centre and in the operational line and allow ESS to look at business opportunities on a "whole Service" basis. Cost savings of £600k are envisaged following its full implementation. (Page 40)

  Implemented. The central support to industries has been redrawn along functional lines. All teams are now established with job specifications, business plans completed and incorporated into the business plan for Regime Services. There was a staff cost saving for ESS to year end March 2005 of £281K—further savings of £230k are due to be delivered in 2005-06.

Improving Feedback of Good Practices Recommendation (26)

  Consideration should be given to improving feedback to the field and HQ and in generally promoting examples of good practice, be it at establishment or ESS level. (Page 41)

  Implemented—ongoing.

Review Engineering Section    Recommendation (27)

  Further work should be undertaken to assess the value of splitting the Engineering team from the remainder of ESS. Subject to the outcome of that review the Engineering team that provides work to the Property Services Group and to Establishment Works Departments could be transferred, along with their workshops and their staffing and material budget to Property Services Group. In this way essential security related work could be given the priority it deserves. (Page 42)

  Implemented. Further review completed. Engineering Production Team remains within ESS.

Review Workshop Activity Logistical Difficulties Recommendation (28, 41)

  There should be a comprehensive review of stores and logistics.

  The Head of ESS should examine workshop activity where there are particular logistical difficulties. (Page 83)

  Implementation started and ongoing. This work has been largely subsumed into the much wider review of logistics within the Prison Service. However steps have been taken to reduce logistic costs where possible—for example introducing flat pack furniture products.

Additional Clothing and Textile Workshops    Recommendation (33)

  The Service should invest in additional workshops (and machinery) for clothing and textiles in order that a greater proportion of the needs of the Service can be met. If agreed, ESS should take this forward as a matter of priority. (Page 64)

  Not implemented. This recommendation was re-evaluated after the implementation of a number of other key recommendations—such as the impact of the stock reduction strategy and the hard charging pilot—resulting in there being insufficient work to warrant opening more clothing and textile workshops.

Review Stationery & Catalogue Book 340    Recommendations (36, 37, 38)

  A review of Book 340 should be conducted to ensure that all stationery items within the document are still used by the Prison Service, all items are "owned" by part of the organisation, and that the minimum order levels are appropriate. (Page 71)

  Implemented—ongoing. Over 25% of stock items have been reduced with the review process continuing until the end of the year.

Reintroduction of the Manufacturing clerk's courses Recommendation (39)

  The manufacturing clerk's course should be reintroduced, especially if hard charging is introduced. (Page 75)

  Training requirements have been identified. Course curriculum will be identified in the new year. A meeting has been arranged for the 11 January to begin designing the course curriculum with a view to being piloted in the new year.

Reintroduction of Industries Managers Workshop    Recommendation (40)

  The reintroduction of an Industrial Managers' Conference on at least an 18 monthly basis should be considered—attendance by representatives from appropriate outside industries would be advantageous. The Head of ESS should chair the conference. (Page 75)

  Implemented. The first Industries Workshop was held in March 2004 and was well received. Future conferences are likely to be held every two years.

Prisoner Skills Progression Activities Recommendation (42, 43, 44)

  The new Policy Team in ESS should be tasked with devising a system of progression designed to provide all prisoners with the skills that will allow them to progress within a workshop whilst addressing their needs. (Page 84)

  Implemented and ongoing. Regular meetings are now taking place with prison based Heads of Learning & Skills to promote formal training activities in the workshops for all groups of prisoners. A strategy has been developed to formalise the learning and skills training that takes place in prison workshops. The strategic reviews of all industry sectors—due to be completed by the end of the year—will include a focus on short-term prisoners and what might be possible with prisoners who do not stay long in prison. We are also piloting how we can better link resettlemnt outcomes and training to workshop activities.

  Where Governors set up a workshop that employs prisoners in an activity that meets the restorative justice agenda they should recognise that whilst the work may not cover all the costs there is an added value that should be accepted.

  Implemented—this view appears to be widely accepted.





29   ESS stands for Enterprise and Supply Services-the central Prison Service Unit responsible for prison industries. Back

30   FC&A stands for Financial Control and Accountancy Unit. Back


 