Select Committee on Northern Ireland Affairs Written Evidence


Annex D

Memorandum on PEACE II (HC 653)

  The Committee Clerk has asked for a memorandum updating the Committee on matters covered in its Peace II Report. The following memorandum aims to meet this request and endeavours to answer the various questions posed by the Committee in the order in which they appear in the letter dated 29 November 2004.

Question 1

What progress has been made in applying the nine recommendations set out in paragraph 10 of the Government's response to the Committee's report? (HC 1077, page 3)

Recommendation 1: 60 Day Action Team

  Following receipt of the PWC report on the reviewing of PEACE II implementation systems and processes in July 2003, the Minister established a "60 Day" Action Team to oversee delivery of the nine areas of simplification. The Action Team completed its work in November 2003 and a copy of their final report making 47 recommendations on simplifications was issued to NIAC on 8 December 2003. The Minister asked that implementation of these simplifications is taken forward by the SEUPB in 2004. 45 of the 47 recommendations have been implemented. The two not yet fully implemented were numbers 15 and 40. Number 15 was to create a consultancy call off list and is no longer considered necessary. Number 40 was for a full review of accountability arrangements that is partially completed. A new financial memorandum reflecting this work is expected to be agreed before March 2005.

Recommendation 2: Application Process

  A new registration process, grant application form and small grant application form became operational in December 2003. Application forms were redesigned with the objective of simplification. The new registration process strongly highlights "Distinctiveness criteria" to avoid unnecessary work by applicants and implementing bodies in considering projects which fail to meet these essential criteria. The aim is to ensure that information requested from the applicant is commensurate to the stage achieved in the process. The SEUPB held management workshops in early 2004 to introduce the changes.

Recommendation 3: Assessment Process

  The SEUPB has introduced minimum service delivery standards for project applicants established for all implementing bodies in relation to processing and assessing applications. The establishment of formal complaints and suggestions procedures for project applicants/promoters, with minimum service delivery standards for the SEUPB and implementing bodies.

  SEUPB held workshops for all implementing bodies in early 2004 on guidance to and best practice of Assessment Panels. SEUPB issued a Service Delivery Standards Paper to all implementing bodies in December 2003.

Recommendation 4: Support for Decision Making Process

  SEUPB revised procedures in respect of economic appraisals and issued updated guidance on value for money assessments, also devised step-by-step guidance, proformas and flow charts/checklist to clarify and ensure principles of appraisals are applied with appropriate and proportionate effort. A simple flowchart was developed to provide an overview of the appraisal process. A checklist which standardises the requirements accompanies this. The checklist provides a standard programme-wide pro-forma for use on economic appraisals which has been extended to all the EU funds operating in Northern Ireland.

Recommendation 5: Standardisation on Letters of Offer

  SEUPB issued a standard model Letter of Offer and associated guidance in all implementing bodies in December 2003. A management workshop was held in January 2004.

Recommendation 6: Agreed approach to audit and verification

  SEUPB issued guidance on financial controls for the PEACE II Programme to all implementing bodies. This states clearly the financial control requirements of the EU and represents the minimum financial control requirements for the Programme consistent with EU regulations and proper management of public money. Project organisations with multiple projects (funded from the same EC fund) will not normally receive more than one Article 4 audit check in a 12-month period. Implementing Bodies are now permitted to apply the principle of materiality to expenditure claims. This revised guidance has been incorporated into the EU Structural Funds Manual and is used across all four EU programme funds operational in Northern Ireland.

Recommendation 7: Clarification of Monitoring Requirements

  SEUPB issued guidance on monitoring and reporting requirements in December 2003 and a workshop was held in early 2004. Equality monitoring requirements reduced to one form per year. Monitoring information now collated from projects on a six monthly basis rather than quarterly. Projects not now required making formal return with respect to PEACE II distinctiveness monitoring. Other aspects of monitoring reviewed and clarified.

Recommendation 8: Development of the Interface between SEUPB and Government Departments

  Accountability arrangements between SEUPB and Departments as specified in Terms and Conditions of Payments of Grant documents have been simplified and clarified to allow scope for SEUPB to seek cash from Departments to measures based on projected need rather than solely on the basis of payments to a pre(set limit as previously. Virement procedures have also been put in place. This reduces the number of payment claims from SEUPB to Departments that are necessary and ensures cash balances are minimised.

Recommendation 9: Communications and Publicity

  A PEACE Programme communication strategy has been put in place which establishes clear and consistent objectives and set of actions to redress the balance between the positive and negative image of the Programme. SEUPB held conferences in December 2003 and December 2004 to communicate the success of the Programme to date via projects and to announce the "60 Day" Action Team changes. The PEACE Programme was presented in Brussels in September as part of a wider Commission/Committee of the Regions event.

Question 2

What further steps have been taken to simplify the application forms? (Government's response, HC 1077, paragraphs 12-18)

  Part A of application form significantly shortened and redesigned to become more user friendly. SEUPB introduced a mandatory registration process for all applicants prior to completing full application form. Registration process strongly highlights "Distinctiveness criteria" to avoid unnecessary work by applicants. The Part B has been shortened and redesigned to simplify completion Additionally a Small Grants application form was shortened and simplified in terms of presentation and language, and on basis of minimum core information necessary to assess an application. In the extension period the reduced number of Measures and Implementing Bodies will allow further simplification of the application process and make it simpler for potential applicants to access relevant Measures.

Question 3

What is the average time currently taken to process application forms? (Government response, HC 1077, paragraph 20)

  On 1 January 2004 the SEUPB introduced minimum service delivery standards for project applicants established for all implementing bodies including minimum processing times for assessing applications. Since this date the average processing time for approved PEACE II applications in Northern Ireland has been reduced from an average of 93 working days to 58 working days. The table below provides a more detailed analysis for both approved and rejected applications is received on or after 1 January 2004.

APPROVED APPLICATIONS
Number of
applications
Total working
days processing
time
Average working
days processing
time
Type of funding bodyNI Govt Dept 40126,02065
NI IFB118 6,66957
LSPs482 25,38453
All NI Ibs1,001 58,07358
Note: Processing time for approved projects is the difference between the date the signed Part B is received and the date the LOO is issued.


REJECTED APPLICATIONS
Number of
applications
Total working
days processing
time
Average working
days processing
time
Type of funding bodyNI Govt Dept 19611,93261
NI IFB36 2,49569
LSPs172 4,81328
All NI IBs404 19,24048
Note: Processing time for approved projects is the difference between the date the signed Part B is received and the date the application is rejected.
Source: CSF Central Database, 10 December 2004 (NB Central Database is reliant on funding bodies to provide information. In addition it is live and dynamic and subject to change.


Question 4

What success has the Government had in pressing for "simplification" of audit procedures in the context of Northern Ireland? (Government response, HC 1077, paragraph 22)

  Following the PEACE II Programme's "60 Day" Action Team simplifications DFP has issued revised guidance on audit and verification. The revised guidance ensures consistent and streamlined procedures are applied by all Departments and Implementing Bodies.

  DFP in consultation with other Departments has provided comments and views to DTI and has attended EU technical seminars to help develop the UK position on audit matters for the post 2006 Structural Funds Regulations. It is hoped that these simplification proposals will be reflected in the new regulations that are expected to be agreed in mid-2005.

Question 5

Progress on N+2 spending targets. How much was spent at 31 December 2003? (Recommendations 18-22; Government response, HC 1077, paragraphs 23, 24)

  At the end of December 2003 the PEACE II Programme met and exceeded all of its N+2 target. In 2004 N+2 targets for the PEACE II Programme in Northern Ireland will be met with total expenditure to the end of November 2004 of

346 million.

Question 6

Peace II Extension (The Committee has asked for an update on the arrangements and timetable for the proposed extension of Peace II and has asked specifically what risk is there that there will be a funding gap between the current and any extension programmes)

  Good progress has been made to secure the necessary National and EU agreements to extend PEACE II but final European Parliamentary Ratification is not expected until mid/late January. Agreement by the European Council on the budget was delayed until early December and is now less than that first proposed and its composition in terms of National and EU money is also different. The proposals that we made to the Commission at the end of September to allocate these resources now need amendment to reflect these changes. It is hoped that these can be finalised by end January 2005 and Commission approval obtained before end March 2005. Contracts to Implementing Bodies can issue after that. We hope that first expenditure allocations can begin before summer 2005. As projects with current offers can claim expenditure until 2006 there is only limited risk of any funding gap period.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 27 January 2005