Select Committee on Public Accounts Eighth Report


3  The procurement of the Chinook Mk3

20. In July 1995, the Department decided to upgrade eight of the 14 Chinook Mk2 helicopters it was procuring as part of its requirement for a Medium Support Helicopter. The upgrade to an enhanced Mk3 standard would include improvements in range, night vision, and navigation capabilities. The project was scheduled to cost more than £250 million and the forecast in­service date was November 1998. A subsequent change to the requirement led to an avionics upgrade programme being put to contract in 1997, which entailed a hybrid solution, incorporating elements of the existing analogue cockpit and new digital systems and displays. The need to test the airworthiness of the aircraft together with some programme slippage led to the setting of a new In-Service Date of January 2002. When the aircraft were accepted from the contractor in December 2001, the Department found that it was unable to demonstrate that the flight instruments met United Kingdom Defence Standards, as this requirement had not been specified in the contract. Consequently, the aircraft could not be used other than for limited flight trials.[31]

21. The Department said that there were three main reasons why the helicopters remained grounded and were unfit for their operational task. First, without access to the source software codes held by the United States, the safety parameters of the aircraft could not be tested in its current configuration. One of the main contractors has now indicated that it would allow access to some software data. The process of analysis is, however, time consuming and expensive and there is no guarantee of success because the legacy software is not amenable to the techniques required to confirm the robustness of the software design. Secondly, the specialist role envisaged for the aircraft had changed since they were acquired. Finally, the aircraft needed to be fitted with Health and Usage Monitoring Systems, a range of systems that seek to monitor the progressive wear of engines, and better Defensive Aids Suites.[32]

22. Despite the fact that all the aircraft accepted from the contractor met, and in some cases exceeded, the contract, the Department accepted that the taxpayer had not been well served by the procurement of the Chinook Mk3. The contract did not specify fully all of the Department's requirements (paragraph 23). The Department acknowledged that the whole project was flawed from the outset in 1995 and got worse after 1997. Figure 3 illustrates the timescales involved in the project.[33]Figure 3: Timescales on the Chinook Mk3 procurement



23. A key factor in the delay in bringing the Chinook Mk3 into service was the Department's failure to specify in the contract what its requirements were for independently validating the United States manufacturers' safety critical software codes for the avionics systems. The Department had incorrectly assumed that it could rely on a safety case based on the systems' similarity with the avionics systems used in the Royal Netherlands Air Force's Chinooks. The Department acknowledged, however, that, as with the Apache Attack Helicopter, it was not always necessary to have access to source codes to achieve adequate safety assurances. The Department currently operates the C17 aircraft within United States' safety parameters without having independently validated the avionics software codes.[34]

24. In addition, the contract specified delivery of only 45 of 100 "essential elements" outlined in the requirement for the helicopter. In practice the helicopter design met 55 of these requirements. Of the remaining 45 elements not delivered, a number of capabilities could not have been included owing to immature technology, some of which were planned to be fitted later. But, in the majority of cases, the Department had been unable to identify a clear audit trail to explain why the remaining elements of the requirement were not embodied in the contract.[35]

25. The Department had instigated a full review of the procurement, which preceded the introduction of Smart Acquisition, to ensure that mistakes were not repeated. The Department needed to heed three lessons: there should be better risk reduction and more understanding of what was being undertaken before signing a contract; there should be more rigorous project review throughout the period of the procurement; and there needed to be a better understanding of the underlying safety issues, particularly where there was a unique British requirement for the independent validation of source software codes. The need to validate independently the software codes for the Chinook Mk3 had been a British requirement. Other countries, including the United States, were happy to fly the aircraft. The Department was reviewing its management of safety cases to ensure that its procedures were appropriate.[36]

26. The Department accepted that the procurement principles drawn out by the review of the Chinook procurement were not new. For example, during the procurement of the Sea Wolf missile between 1987 and 1990 project management techniques, including regular review meetings, assessments of risk, and measuring safety parameters of the equipment, had all been used.[37]

27. Despite the acknowledgement that the procurement of the Chinook Mk3 had been poor, no one in the Department with responsibility for the project had been disciplined. Decisions had been made collectively rather than any individual being responsible. Faults lay with a range of people including the project team, operational requirements staff and the safety authority. There were also weaknesses in senior staff oversight. The Department's review had suggested that people had acted with the best intentions but had got things wrong.[38]

28. The Department had completed a Combined Operational Effectiveness and Investment Appraisal and identified that to rectify the aircraft's shortcomings was probably the best value for money solution to the Chinook Mk3 problem. The Department were to undertake a £13 million preparation phase to determine the validity of this solution and expected to decide the way forward in Summer 2005. Other options that were open to the Department were to sell the aircraft to a nation that regarded them as acceptable or to use the aircraft as a source of spares for the rest of the Chinook fleet, which was undesirable.[39]

29. The Department had originally estimated that to provide the capability required by mid­2007 would cost around £127 million.[40] It was now, however, unsure of the final cost and the preparation phase for the option to rectify the aircraft's shortcomings would establish a more accurate forecast. This option would comprise three elements: the replacement of the Chinook Mk3's avionics to meet the requirements of the Department's airworthiness standards; the provision of a Health and Usage Monitoring System and a Defensive Aids Suite; and the provision of revised Special Forces' operational requirements. The last two elements would have been additional projects even had the original procurement been successful.[41]

30. Until a final decision on the way forward was made, the Department had taken a prudent accounting measure in writing down the value of the Chinook Mk3s by £205 million in the Departmental Accounts. The value had been written down to reflect that of usable spares only.[42]

31. The Department had considerable experience of identifying lessons from procuring equipment but failed to learn from this experience when acquiring the Chinook Mk3. The Department said that it had now implemented the lessons from this particular procurement project.[43] These included the clear points of failure in the project such as deviations from standard procures, identifying how Smart Acquisition processes could have made a difference and the way in which the need for Military Aircraft Release acted as a constraint. The Department had formulated an action plan based on these lessons and would review progress in mid-2005.[44]


31   C&AG's Report, paras 3.40-3.41 Back

32   Q 2 Back

33   C&AG's Report, para 3.41; Qq 1, 84 Back

34   C&AG's Report, para 3.41; Qq 1, 223 Back

35   C&AG's Report, para 3.42; Qq 20-21 Back

36   Q 1 Back

37   Qq 103-109 Back

38   Qq 42-44, 116-119 Back

39   Qq 149-150; Ev 14 Back

40   C&AG's Report, para 3.43 Back

41   Qq 5, 206  Back

42   Q15; Ev 3 Back

43   Qq 91-92 Back

44   Ev 26 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 18 March 2005