Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 160-179)

DEPARTMENT FOR TRANSPORT, PRICEWATERHOUSECOOPERS AND LONDON UNDERGROUND LIMITED

23 JUNE 2004

  Q160 Mr Curry: Patience Wheatcroft, who writes on financial matters for The Times - and not as far as I know a rabidly left wing journalist—when she read the Audit Office Report she wrote the following: "To paraphrase the carefully crafted prose of Sir John Bourn this looks like a potentially very expensive scheme that may not deliver very much in the way of benefits to travellers but is certainly a bonanza for the private sector. For everyone from consultants and lawyers to engineers and construction companies, the Tube has turned into a gravy train. Gordon Brown is the driver. The Chancellor has determined that Ken Livingstone would not have his way and finance the much needed revamp of the Underground through a bond issue. As far as the Chancellor was concerned it was PPP or nothing and eventually he fought London's Mayor throughout the courts to get his way. Mr Brown's devotion to the PPP was not wasted on those who might put it into practice. They saw a desperate customer coming and as the NAO relates pitched their charges accordingly." If one picked a scale of zero meaning she is absolutely all over the place and ten just about spot on, where would you put that comment?

  Mr Rowlands: One.

  Q161 Mr Curry: Which bit has she got right?

  Mr Rowlands: She has captured the notion of the complexity of the PPP but for the rest she is a journalist, it is good copy but I do not agree with it.

  Q162 Mr Curry: I am a journalist as well. The suggestion that the thing can be defined as being wrong because it is written by a journalist, which seems to be the implication you are making, does seem to me to be one I would be slightly cautious about in general. Has she misinterpreted the National Audit Office Report or is that a criticism you would make of that Report?

  Mr Rowlands: I do not know what her interpretation is apart from the words on the page in The Times with which basically I do not agree. I do not believe this was a gravy train for consultants or advisers and the NAO's own Report says the costs were reasonable in relation to the scale and complexity of the deal. These are £30 billion worth of contracts. The costs though in absolute terms largely represent about 1½% of the total cost of the contract. That is not outrageous or unusual in relation to a contract.

  Q163 Mr Curry: It is true that on this occasion on this deal, which you say is enormous, very long in its timescale and extremely complex one did have two principal political personalities engaged who had opposite views of the way to go forward and neither of whom were inclined to give way, and in the end it had to be fought out on a legal basis. All might be changed now though, we will not comment on that, but would it have been easier, do you think, had there been a greater harmony between those personalities?

  Mr Rowlands: I suspect the answer is yes but that is about as far as I can go really.

  Mr Williams: It is a question of how far the witnesses can go in this direction.

  Mr Curry: No, no, I do not intend to take him any further at all. The Audit Office Report itself made reference to that, which was why I asked the question.

  Mr Williams: It puts him in an embarrassing position as a civil servant.

  Mr Curry: We ought to have the Chancellor here.

  Q164 Jon Cruddas: Just one question that has not been covered in all this. The Committee of Public Accounts in other analysis of PPPs looked at the way the terms and conditions of employment had taken the strain at times. As far as I picked out, when I read these Reports, there are two references to the employment conditions of those workers transferred over which I think amount to some 7,500. It hints that certain understandings were made about the protection of those workers. Could you give some details about that?

  Mr Rowlands: Yes. This is from memory. It was made explicitly clear by the Government at the time the PPP was initially conceived that the terms and conditions of any members of staff transferring into an Infraco would not suffer detriment and that in particular the Infraco's membership would remain in the existing pension scheme and not be placed in another one.

  Q165 Jon Cruddas: Does that include new recruits as well because there has been quite a significant amount of recruitment as well?

  Mr Rowlands: I need to come back on that, if I may, but my recollection is it did not and could not cover new recruits because you could not define the position 25 years out for a new recruit into one of the Infracos.[13]


  Q166 Jon Trickett: Something which has not been addressed and it is very hard to understand from this Report, is this issue of the compensation we pay to bidders. Companies or consortia which were bidding for the contracts were reimbursed the cost of their bid. I think we see reference to it on paragraph 3.16 on page 32. It seems that one company bid for two contracts and was reimbursed £116 million, which was Metronet, and another company called Tube Lines which bid for only one line was reimbursed £134 million, more than the consortium's bid for two lines. When I went to paragraph 3.16 and table 14 on that page there, there is an analysis of the expenditure by Tube Lines on the bid and it appears that most of the expenditure which that company had took place after the contracts had been awarded. First of all, how can you reconcile the fact you paid more to a company which was only bidding for one contract than you paid to a company which was bidding for two contracts? Secondly, can somebody explain this table to me in a way which makes sense? If I have understood it correctly how on earth have we given them the money for bid costs after they have won the bid?

  Mr Rowlands: Can I start with your second question, if I may?

  Q167 Jon Trickett: Sure.

  Mr Rowlands: Can I begin by, I am afraid, repeating myself. All winning bidders recover their bid costs in their contract prices. If winning bidders do not recover their bid costs they go out of business in the end. What this process did was make visible, if you like, what the bid costs were in relation to these particular contracts. To take your second question first, most of the work that both bidders did happened in the latter stages of the process because this was when Metronet were putting into place the contracts that it was supplying its outputs through and Tube Lines was beginning to do due diligence in relation to the contracts it was going to let. This is a heavyweight expenditure on financial and legal advisers in relation to closing out the contracts. So, for example, on the financial side, the Tube Lines' bid costs include tens of millions for the financing fees for debt that was put in place and tens of millions for the insurance with which they wrapped some of the debt to get a better interest rate on it and insure some of it in the market.

  Q168 Jon Trickett: Can we have an analysis of the differences between the two amounts of money?

  Mr Rowlands: Indeed. I have already promised we would send these details.[14]


  Q169 Jon Trickett: It has been a long hearing for you and no doubt for others as well. Secondly, given the fact that competitive tension had gone out of the bidding process once a preferred bidder had been determined, how can we be certain that the bidders who had then been excluded would have spent less money on the post tender bidding process, as you seem to have described it? It seems to me hundreds of millions of pounds here, probably £200 million between the two contractors, after they had been given the tender but still allegedly part of the bidding process. Where was the competitive tension to make sure they got a decent price for those amounts of money?

  Mr Rowlands: I am afraid that once this competition moved to preferred bidder, although there were reserve bidders they were not undertaking this activity, they were not closing out on the deals so they were not spending this kind of money.

  Q170 Jon Trickett: The taxpayer reimbursed that amount of money, although it was part of the bidding process, the bidding had finished, had it not?

  Mr Rowlands: But they had to move from preferred bidder through to financial close and that meant putting in place very large debt facilities and financing costs.

  Q171 Jon Trickett: Why did the bidding process not ask them to put a price in for the post tender so-called bidding, which is not really bidding at all, is it, but the post tender preparatory work?

  Mr Rowlands: They did.

  Q172 Jon Trickett: Can we have a note on it?

  Mr Rowlands: Yes.[15]


  Q173 Jon Trickett: There are tens, possibly hundreds of millions of pounds here.

  Mr Rowlands: We will do that.

  Q174 Mr Jenkins: I want to get something clear in my mind, I want to revisit the financing deals. I am not sure I have got this perfectly clear. The example we have got here on page five is one of Tube Lines. They refinanced and they disclosed a gain of £84 million and so 60% was the share to the public sector which will rise to 70%. Now that 70%, where does it come from?

  Mr Rowlands: This refinancing happened after the transfer to TfL was negotiated by TfL with, in this case, Tube Lines. If I can help you. What was generated was cash, up front, of which TfL, through their 60% share, got 60% of £84 million, about £42 million from memory. That is cash that has gone to TfL.

  Q175 Mr Jenkins: Since the taxpayer is funding this package they must have been in on the contract, the arrangement would be to pay TfL rather than pay it back to the Treasury, yes?

  Mr Rowlands: The arrangement in the contract provided for TfL and the Infracos to share any refinancing gains, though this particular split was negotiated by TfL after transfer, 60:40 split.

  Q176 Mr Jenkins: Since we are well aware—and this Committee has highlighted the refinancing arrangements in this area—and since we have spent so much time and very, very heavy costs on lawyers knitting these views together, why was it left to somebody else after we handed it over? Surely we should have handed over a complete package which included any refinancing gains coming back to the Treasury?

  Mr Rowlands: I cannot speak for TfL but they might have been reluctant to accept such a package. What it means, certainly, is that if TfL do not get any share of the gain you have removed one part of the contract's interest in what is going on. I am not clear, you will be at the mercy of the Infraco to conclude whatever arrangements it wanted if you were not careful on refinancing. This was policed by TfL.

  Q177 Mr Jenkins: The private sector, when they are going to refinance a deal, refinance the deal because they make quite a heavy profit, a windfall gain. They are not loath to passing some back if we negotiate in the contract they must pass back 50/60/70%.

  Mr Rowlands: Yes.

  Q178 Mr Jenkins: I understood this deal was all sewn up, all knitted together before it was handed over?

  Mr Rowlands: The refinancing was done after the event and it was not worked up before transfer.

  Mr Jenkins: That is appalling.

  Q179 Mr Williams: Hold on. To the Treasury: you gave us an indication that some guidelines had been agreed some months ago on the minimum share that should come to the public sector in the case of refinancing. Would that have been relevant at the time of this?

  Mr Glicksman: Yes. The guidance was 50:50. TfL negotiated a better deal than that, they negotiated 60:40, 60% to the public sector, so they did better than the Treasury guidance.

  Mr Rowlands: They negotiated—I may have this wrong—in effect 70% over time because some gains come later. If all the gains from a refinancing were to go to the Treasury, why would the infrastructure company bother to refinance because it gets no benefit from it, it simply goes to the Treasury?

  Mr Callaghan: If I may help, Mr Jenkins, I think you asked two questions. One was were there refinancing provisions in the contract? The answer to that is yes. In general the Treasury follow the Treasury guidance and in relation to this specific refinancing, which was in contemplation when the contracts were finalised, it was 60:40. In the negotiations that happened subsequent to the contract, TfL and LUL did a better deal than that. The answer to your second question, which is why is it TfL and not the Treasury, is that the contract is between London Underground and the private sector so the money went to London Underground and ultimately to whoever owned London Underground at the time it was done, which is why it was TfL.


13   Ev 26 Back

14   Ev 25, 35¸39 Back

15   Ev 26 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 31 March 2005