Select Committee on Public Accounts Minutes of Evidence


Supplementary memorandum submitted by Transport for London

Questions 144-147 (Mr Bacon): Whether Transport for London had provided advice to the Department of Transport concerning TfL's recommendations for a public bond financing to support required capital investment in the Tube?

  In fact, beginning in late 2000 TfL had provided its views and detailed recommendations to LUL and DETR/DfT concerning what TfL believed to be a cost effective alternative to the PPP financing scheme. Although some material was formally submitted only to LUL, at all relevant times LUL was acting under the direction of DETR/DfT through London Transport. This record is summarized below, and includes the following attachments:[34]

    —  Outline of a Programme for the Rehabilitation and Management of the London Underground; 13 December 2000. Transport for London, available via the Web at http://www.tfl.gov.uk/tfl/pdfdocs/report02.pdf.

        This piece outlines the use of securitisation, a form of public borrowing, to provide the bulk of the financing to support an alternative approach to the refurbishment of the London Underground. The paper also addresses the in-depth involvement with the private sector, the management of risk between public and private sectors, the need for a full assessment of asset conditions, and the likely levels of Government support required for such a programme.

        While the report was not addressed to DETR, it was provided to DETR and made broadly available to the public. As the next document attests, it was considered in detail by DETR.

    —  Response to Questions Raised by DETR Concerning TfL's Outline of a Programme for the Rehabilitation and Management of the London Underground; 29 December 2000. Confidential correspondence from Robert R. Kiley to Mike Fuhr, Director, London Underground Task Group.

        Regarding TfL's plan of 13 December, DETR tabled various questions on strategic and technical points raised by the paper. The note therefore was direct correspondence from TfL to DETR.

        This paper re-emphasised the role the private sector would play in a TfL plan, the controls that the public sector would require, and the specifics of the proposed financing plan and risk allocation by TfL.

    —  London Underground Public Private Partnership, Emerging Findings; 17 July 2001. Deloitte & Touche Corporation. Executive summary available via the Web at http://www.tfl.gov.uk/tfl/pdfdocs/report02.pdf.

        This report examines a TfL bond plan for works within the Public Sector Comparator with regard to the value for money analysis of the BCV and JNP Infracos. The report notes that the value of public sector bond financing has been largely dismissed by LUL's application of a concept termed "reputational externality". Also, net financing costs for the public alternative were inflated by an inefficient treasury management plan, which raised and held for five years large cash balances from bonds, despite substantially lower investment rates than borrowing costs. Deloittes notes that these costs could be significantly reduced by standard treasury management techniques. In LUL's analysis of VfM, supporting its decision to proceed with preferred bidders, its presentation of these two factors disadvantaged a viable public bond case by £900 million. See paragraphs 3.7.2 and 3.7.3.

        The Deloitte report also notes that selection of preferred bidders too early in the process could lead to a materially adverse impact on VfM. Independent of the benefit of public financing and highly material adjustments to the PSC, the 7.5year bid for the JNP line did not show value for money and the BCV bids show that there was a scenario where the PSC offers better VfM than the preferred bid.

        This report was shared by TfL with LUL's management.

    —  Interim Consultation Response to London Transport on PPP documents provided between 11 February 2002 and 15 March 2002; Chapter VI Value for Money; Transport for London. Available via the Web at http://www.tfl.gov.uk/tfl/report/pdf—05.pdf.

        The chapter describes various criticisms of the value for money analysis, and describes that a TfL bond-funded alternative would project present value cash savings of £1.7 billion against mid-point estimates related to works undertaken in the first contractual period, or £1.2 billion against the highest estimates of the PSC (see page 44). Even when conceding for discussion LUL's questionable estimates of social costs that against the PSC, the savings of the PSC over the bids range from £1.1 billion (against its central estimates of public costs) to £500 million (against the 95% high end of estimated public costs). This chapter notes that TfL's bond plan has never been accurately represented during any stage in the evaluation of the PPP, despite the presentation variously to DfT and LUL of the above materials.

        Also in the chapter are criticisms of the adjustments to the construction of the PSC, in that:

—  Its wide risk ranges were never adjusted to reflect the increasingly narrow risks that ended up being built into the PPP contracts;

—  the VfM ignored contract management costs of the PPP;

—  the 30-year analyses have no substantive value;

—  that the 7.5-year analyses, even when putting aside the debate regarding public sector financing costs, do not show value for money (this has now seemingly been echoed by NAO);

—  the "wider factors" did not include either a full listing of downside risks, or some attempt to give them financial weight or, failing a full analysis, some discussion of commercial significance; and

—  that there was an overall breakdown in the chain of verification of the VfM process.

        This report, as a consultation response, was of course shared with LUL management.

        TfL staff are available to discuss the above reports and correspondence at the Committee's convenience. We believe now, as we believed then, that the public bond alternative would have provided a more prudent and cost-effective approach to financing the modernisation of the Tube.

Robert R Kiley

Commissioner of Transport

7 July 2004

Questions 36-38 (Jon Trickett), Questions 174-182 (Mr Jenkins) and Questions 182-186 (Mr Williams): Summary of position on information provision.

INTRODUCTION

  Paragraph A3.2 of the NAO Report "London Underground: Are the Public Partnerships likely to work successfully? " set forth the position on the exchange of information between LUL and the Infracos as at the end of the fiscal year, March 2004. This note summarises the position as at 13 July but the position is evolving and subject to change.

INFORMATION TO BE PROVIDED BY INFRACOS TO LUL

  The PPP contracts span a wide range of complex activities that are undertaken by Infraco and LUL on the Underground network. The contract sets down the information to be provided to LUL that LUL requires to fulfil its functions, for example to assure itself of the safety of the railway. In some areas, the contractual information sharing provisions are expressed in general terms and do not specify the form and content of submittals. It should be noted that the PPP contracts specifically refer to the Infracos undertaking their obligations on an open book basis. Some of these information requirements are set out below:

Capital Projects

  LUL has the responsibility to co-ordinate the execution of capital works across the Underground network by several different PPP and PFI contractors. This is to ensure both that proposed works do not over-lap in space and time (with consequent risk of interference) and that impacts on the operation of the railway can be managed. To do this, LUL has developed a Master Projects Database (MPD) into which the Infracos—as well as LUL itself and its PFI contractors—are required to feed accurate project plans showing when and where work will be undertaken. MPD is critical to the management of the unprecedented work programme being undertaken on the network.

  LUL has been planning for many months upon the basis that MPD would be capable of being used as a management tool by September 2004. LUL itself is on target to meet this deadline although its PFI contractors have trailed behind the Infracos, given that PFI contractors involve some entities related to Infraco shareholders and discussions did not commence with them until after the Infracos agreed the principles of what they would provide in early 2004.

Asset Management

  The Infracos have to submit an over-arching Asset Management Strategy (AMS) that sets out the management regime they intend to apply to the assets, and an Annual Asset Management Plan (AAMP) that documents the specific steps they will take under that regime for each asset class, forecasting out nine years into the future. Both of these require LUL's approval. These must demonstrate how the Infraco intends to discharge its PPP obligations including the adoption of an efficient and economic whole-life cost approach. Of necessity, this involves the Infraco providing cost information which should facilitate monitoring progress of Infracos' expenditure in relation to the baseline forecast in the PPP contracts which underpinned the level of the Infrastructure Service Charge.

Other Financial Information

  The Underground's assets remain on LUL's balance sheet under the PPP contracts. To accurately account for them, the Infracos are required to provide LUL with detailed information on how their work has increased the value of the assets each period.

  In addition, the Infracos are required to give LUL further information about their cash and revenues so as to allow LUL to monitor the Infracos' overall financial position: this information includes periodic management accounts. In the case of Tube Lines, LUL and Tube Lines have agreed that additional financial information will be provided—this was agreed in the context of the recent refinancing.

Sub-Contracts

  The PPP contracts give LUL "step-in" rights to take over parts of an Infraco's operation in circumstances where the Infraco is in breach of contract. Under these circumstances, LUL would replace the Infraco as the counter-party to the sub-contracts put in place by the Infraco. Each Infraco therefore has to provide LUL with information about its Key Sub-Contracts, to allow LUL to check that the sub-contracts contain the rights LUL may need in the future and the appropriate terms in areas such as audit. Thereafter, LUL signs an explicit agreement (termed a "Direct Agreement") with the sub-contractor formalising the arrangement. The Direct Agreement also serves the purpose of bringing the sub-contract and the assets provided under it under the protective provisions in the Greater London Authority Act 1999 in the event of insolvency or administration of the Infracos.

  The Infracos have been engaged with LUL since the contracts were signed in discussing how they might deliver their obligations in all these areas. Some information has flowed from both Tube Lines and from Metronet in each of the four areas above, but in all four areas significant difficulties have been encountered. Discussions continue with both companies as to how the provision of necessary information can be improved. In general, problems relate both to the Infracos' development of internal management information systems capable of producing required information and to the reluctance of the Infracos to provide financial information already in their possession. The position with Tube Lines is largely resolved with information flowing or dates for delivery agreed. There are substantive issues remaining with Metronet and this is disappointing, given that Metronet was helpful in resolving an impasse between LUL and Tube Lines/Metronet over the MPD.

CURRENT POSITION

Tube Lines

Capital Projects

  Until Tube Lines and LUL agreed the principles about data to be submitted to the MPD in early 2004, limited capital projects information was passed to LUL. Since then, Tube Lines and LUL have been working jointly to configure the necessary automatic links between Tube Lines' internal project management systems and the MPD. The MPD is not yet a fully functional management tool because the required technical integration and data cleansing has not yet been completed. LUL expects to be provided with a full set of data by Tube Lines by September 2004.

Asset Management

  Tube Lines AAMP for Financial Year 2004 included a financial review of the costs incurred in the year to date. LUL was initially unable to reconcile these costs back to Tube Lines' original bid and the data as initially provided was internally inconsistent. The problems were due, in part, to the introduction of new financial systems but a significant reason was the reallocation of cost and overheads. LUL has given Tube Lines' initial AAMP a conditional approval, limited to the 2004-05 work programme (as opposed to the nine year plan anticipated by the contract). LUL is working with Tube Lines on an improvement programme which the parties expect will lead to submission of a satisfactory 2005-06 AAMP. If Tube Lines meets the commitments made, then LUL considers progress will be in the right direction.

Other Financial Information

  Tube Lines have delivered the accounting information required at a high level and have committed to work with LUL in developing more detailed information.

The management accounting information provided to date by Tube Lines has been aggregated to a high level, limiting its usefulness in understanding the evolving position. The additional information Tube Lines agreed to provide at refinancing is not due until the Autumn.

Sub-Contracts

  LUL has received requests for over twenty Direct Agreements from Tube Lines and, until recently, copies of the sub-contracts were not being provided with these requests. In Spring 2004 LUL exercised audit rights to check compliance with the PPP contract requirements in this area. Tube Lines has now agreed to remedy deficiencies identified in the audit by various dates over the next few months. Since then, Tube Lines have generally submitted copies of the sub-contracts with requests for Direct Agreements but no agreement has been reached on the provision of variations.

Metronet

Capital Projects

  Metronet provided only outline information to LUL about the capital works underway on its lines in 2003. In February 2004, Metronet agreed principles with LUL governing the provision of capital project cost and progress data to the MPD for delivery by late September 2004. Metronet has recently advised LUL that it only intends to deliver data on live projects in late October 2004. LUL has not yet been advised when data on the remaining 600 proposed projects will be provided.

Asset Management

  Metronet agreed, in principle, to provide (in the first year AAMP only) broadly similar information to Tube Lines but this information has not yet been delivered. It is not possible to make informed judgements as to whether Metronet is demonstrating a whole-life cost approach upon the basis of the information submitted. Metronet has recently submitted further proposals which are under review by LUL.

Other Financial Information

  The information being provided by Metronet on changes in asset value is insufficient to meet LUL's accounting needs. LUL's external auditors have stated that unless there is a significant improvement, LUL will not be able to support its fixed asset accounting records which would place LUL in breach of its statutory obligations under the Companies Act 1989. Metronet have subsequently agreed to provide more detailed information has to enable LUL to fulfil its statutory obligations.

  Metronet's management accounts provide more detail than those provided by Tube Lines to date.

Sub-Contracts

  LUL has copies of the initial Metronet sub-contracts put in place before Metronet took over responsibility for the Infracos and continues to receive Key Sub-Contracts from Metronet prior to entering into Direct Agreements. Metronet has recently agreed to copy material variations to LUL on a non-contractual basis but there is no agreement yet over what constitutes "material".

  Metronet has obligations under the contract to make sure that sub-contractors undertake their obligations on an open book basis and contain certain audit rights in favour of LUL. LUL has been requiring Metronet to insert the same provisions that it required Metronet to insert in its initial sub-contracts during the bid process.

  Metronet now claims that it is having difficulties securing these rights from its new sub-contractors and that it is not obliged to do so.

  Metronet has regretfully referred the scope of these obligations to dispute arguing a narrow interpretation of the contractual provisions.

Questions 142-149  (Mr Bacon and Mr Williams): Potential refinancings of the PPP Debt

  Why refinance? Refinancings generally occur because the borrower is able to achieve a lower rate of interest than they currently pay.

  Interest payments are split into two components: the base component and the credit spread. The base component is the underlying rate of interest that is paid by high quality borrowers. In the UK for large borrowers, the base component is either Gilts—the fixed rate at which the UK Government borrows—or LIBOR (the London Inter-bank Offered Rate)—the floating rate at which banks borrow from each other. At the time of any debt issuance, Gilts will be quoted at a fixed rate of interest, whereas LIBOR will be floating rate interest for short periods (eg three or six months). Borrowers can enter into interest rate swaps in order to swap payment of LIBOR for payments of fixed rates of interest.

  The credit spread is the premium that the borrower must pay for being a riskier investment than either the UK Government or banks and is quoted as basis points[35] over Gilts or LIBOR.

  A borrower can achieve lower interest rates if either the base component decreases and/or the credit spread decreases.

However, if the base component is at a fixed rate of interest (either Gilts or interest rate swaps) and the borrower wishes to repay the loan in order to refinance, the borrower may be required to pay a prepayment fee to the investor. [36]Because the prepayment penalty will be essentially equivalent to any benefit that the borrower could gain from lower interest rates, the effect of fixed interest rates is that a borrower will not be able to achieve any significant benefit from reduced underlying interest rates.

  With credit spreads, a borrower will be able to achieve a lower rate of interest without prepayment penalty if the borrower can reduce its credit spread. A borrower's credit spread can go down for several reasons:

    (a)  improved credit and therefore becoming a less risky investment,

    (b)  market reductions in credit spreads at that level, and

    (c)  structural enhancements to the debt which reduce its riskiness (although the borrower itself does not become less risky).

Questions 174-181  (Mr Jenkins) and Questions 182-186 (Mr Williams): Can Tube Lines and Metronet refinance?

  In theory, both Tube Lines and Metronet could refinance their debt, as there are no limitations on their ability to refinance in the PPP Service Contract.

  In practice, in the case of Tube Lines, it is unlikely that they will refinance most, if not all, of their debt. Metronet, however, has greater potential for refinancing. The potential for refinancing by both companies is described below.

  Tube Lines: Tube Lines original financing was floating rate bank debt with an interest rate swap, as described above. When Tube Lines refinanced their debt in May 2004, they actually borrowed at a higher underlying interest rate than the original financing, but received payment from the interest rate swap providers for cancelling the swap, thereby achieving the net effect of borrowing at the same interest rate as the original financing.

  Tube Lines achieved the refinancing benefit by being able to reduce the weighted average credit spread on the refinancing from approximately 1.60% in the original financing to 0.686% on the refinancing.

  Because of the significant reduction in the credit spread achieved by Tube Lines in the refinancing, for the majority of the debt, it will be unlikely that Tube Lines will be able to achieve any material benefit—net of fees and expenses—from a further refinancing. However, the credit spread on £172 million of debt will increase significantly starting in 2010. Therefore, Tube Lines may be able to gain some benefit by refinancing this debt before the interest rate margins increase in 2010.

  Metronet: There is a possibility that Metronet could achieve significant refinancing benefit if they are able to further reduce the credit spread paid on their debt. A significant portion of Metronet's current debt are in bonds. Therefore, if Metronet chooses to refinance 100% of the debt, they may need to pay substantial pre-payment penalties to the bondholders. For the floating rate bank debt, we expect that for the majority of this debt, Metronet will enter into interest rate swaps. Metronet may still need to pay a pre-payment penalty to unwind the swaps, but this payment should be less than to the bondholders.

The amount of refinancing benefit for both Metronet and Tube Lines will only be determinable at the time of refinancing as it is impossible to predict what structure would be available at that time, or the underlying interest rates or credit spread.







34   Not printed. Back

35   1 basis point = 0.01%. Back

36   The prepayment fee is paid in order to "make the investor whole" for the returns that the investor will not be earning due to the prepayment. It is calculated by comparing the interest rate on the bond or interest rate swap currently in place against the current base interest rates at the time of refinancing. If interest rates at the time of refinancing are lower than the existing bond or swap, the borrower will need to make a payment to the lender. With interest rate swaps for bank loans, if interest rates at the time of the refinancing are higher, the bank will make a payment to the borrower. With bonds, if interest rates at the time of refinancing are higher, no additional payments from either party will be made. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 31 March 2005