Select Committee on Public Accounts Twenty-First Report


2  Managing risk on space projects

4. Space based projects are inherently risky. They involve the development and use of advanced technology. Many space missions have life cycles, from development through launch to exploitation, of decades. Many projects involve collaboration with other countries, with multilateral space agencies and companies from other nations, which poses further risks. Effective assessment and management of risk is therefore a crucial determinant of value for money.

5. There are a number of examples where the assessment and management of risk within the UK's civil space programme could have been better. For example, the NAO's analysis of the Department's national space programme showed that many of the business cases supporting the various elements had not addressed factors such as changes in the space market or delays to launches, and they had not developed risk management strategies.[5]

6. The Beagle 2 project which was part of ESA's Mars Express mission to Mars was put together at relatively short notice by ESA to compensate for the failure soon after launch in 1996 of a planned Russian mission to Mars which had incorporated European instruments.[6] The timescale for putting the mission together was constrained because 2003 represented the best opportunity to send a spacecraft to Mars.[7]

7. A number of factors increased the risks to the project, or hindered their assessment or management.

  • ESA originally indicated that a weight allowance of 200kgs would be available for a lander, but subsequently cut that allowance to 60 kg. This necessitated a complete redesign of the lander and took time out of an already short schedule.
  • This tight mass limit constrained the ability of the consortium which developed Beagle 2 to manage identified risks. Although the lander that was launched was overweight ESA had not formally given prior derogation from the mass limits.
  • Public funding for Beagle 2 proceeded in a series of seven increments because the science and space support budgets were already heavily committed. None of the funding appraisals formally assessed the chances of success for the overall project.
  • ESA treated the Mars Express space craft and the Beagle 2 lander as two separate projects. This decision hindered the management of the enterprise not least because ESA undertook no real oversight of the Beagle 2 lander until very late in its development.
  • The lander did not include a means of communicating with the Mars Express orbiter.

8. Because of concerns about the development and the funding of the Beagle 2 lander ESA requested an independent review of Beagle 2—the Casani review—which reported in September 2000. The key findings of this review were that:

  • there was no margin available in the proposed mass of the lander;
  • the contingency in the schedule which the consortium had to meet to fulfil the launch date of June 2003 was inadequate;
  • the management of the consortium arrangement was fragile;
  • although the project had a risk management plan, risk management in the classical sense would continue to be non-existent unless mass and schedule margins were restored;
  • if each of the findings (of the review) were satisfactorily addressed then the design of the lander's systems and sub-systems would be satisfactory - with the exception of the airbags designed to cushion the landing of Beagle 2 on Mars.[8]

9. The Casani report concluded that if its findings were fully addressed the project was "challenging but eminently doable".[9] However, our colleagues on the Science and Technology Committee who have reported on the Beagle 2 project found that having commissioned the Casani review ESA did not take responsibility for implementing all the review's main recommendations.[10] The Science and Technology Committee also reported that the Director of Science Programmes at ESA had very strong doubts about the lander's chances of success but that he did not act upon those concerns.[11] In these circumstances it is not clear to us that Casani's findings had been satisfactorily addressed before final decisions to proceed had been taken.

10. Other projects in the United Kingdom's national space programmes operated by NERC and PPARC also demonstrated the difficulties that can arise on complex projects, particularly those involving partnerships. For example, the project run by NERC known as the High Resolution Dynamics Limb Sounder (HIRDLS), a joint project with NASA designed to measure gases in the earth's atmosphere, suffered a series of technical and other delays which deferred its launch by six years to 2004.[12]


5   C&AG's Report, para 4.4 Back

6   Q 7 Back

7   Q 16 Back

8   C&AG's Report Figure 18, Qq 8, 58 Back

9   Q 8 Back

10   12th Report from the Science and Technology Select Committee, Government support for Beagle 2 (HC 711, Session 2003-04), para 79 Back

11   ibid, para 91 Back

12   C&AG's Report, Figure 20 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 9 June 2005