9. Of all the OGC's initiatives the introduction
of mandatory Gateway Reviews in February 2001, for projects classified
as high or medium risk, has shown the most promise. The review
process provides external scrutiny and oversight of major central
civil government programmes and projects.[14]
By 31 March 2004 a total of 440 reviews had been conducted on
254 IT-enabled programmes and projects.[15]
The process was tightened in June 2002 with the introduction of
colour-coding Red, Amber, Green (Figure
1) to denote the overall status of projects, and at
31 March 2004 50% of these have been Amber, 28% Red, and 22% Green
(Figure 2). Figure
1: RAG assessment criteria for overall status of Gateway projects
Between June 2002 and March 2004 50% of projects
were designated as Amber, 28% as Red, and 22% as Green.
Gateway Stage |
Purpose | Description
|
Gateway Review 0
Strategic assessment
| Establish business need for programme
| Asks how the proposed programme meets the business need that lies behind it. Assesses the capability of those who are responsible for the programme and the support of users and stakeholders.
|
Gateway Review 1
Business justification
| Develop business case |
Asks whether the end project is feasible, affordable, and likely to achieve value for money. Also whether the high-level plans for establishing it are clear and realistic.
|
Gateway Review 2
Procurement strategy
| Develop procurement strategy
| Asks whether the tendering strategy sufficiently reflects business requirements, awareness of the market, good practice in procurement, and changes to business need. Asks whether funding is available for the whole project, and with adequate financial controls in place.
|
Gateway Review 3
Investment decision
| Competitive procurement
| Asks whether the tendering process has met its objectives and followed good practice, and whether the prospective contractor is likely to deliver on time, within budget and achieve value for money. Assesses readiness of the business to implement the contract.
|
Gateway Review 4
Readiness for service
| Award and implement contract
| Assesses whether project plans are up to date, and adapted to working successfully with the contractor. Asks whether implementation of the project is going to plan, with any lessons for the future being recorded.
|
Gateway Review 5
Benefits evaluation
(repeated as required)
| Closure | Assesses whether expected benefits are being delivered, and what is being done to pursue continued improvements. Asks what contingency plans there are for future changes.
|