Select Committee on Public Accounts Twenty-Seventh Report


2  Application of the Gateway Review Process

9. Of all the OGC's initiatives the introduction of mandatory Gateway Reviews in February 2001, for projects classified as high or medium risk, has shown the most promise. The review process provides external scrutiny and oversight of major central civil government programmes and projects.[14] By 31 March 2004 a total of 440 reviews had been conducted on 254 IT-enabled programmes and projects.[15] The process was tightened in June 2002 with the introduction of colour-coding — Red, Amber, Green (Figure 1) — to denote the overall status of projects, and at 31 March 2004 50% of these have been Amber, 28% Red, and 22% Green (Figure 2). Figure 1: RAG assessment criteria for overall status of Gateway projects


Source: Office of Government Commerce
Figure 2: Gateway Reviews of IT enabled projects by Red-Amber-Green status June 2002-March 2004


Between June 2002 and March 2004 50% of projects were designated as Amber, 28% as Red, and 22% as Green.

Source: Office of Government Commerce

The impact of Gateway in departments

10. The issues raised by Gateway Review teams have remained consistent since their introduction in 2001,[16] suggesting that despite a clear body of evidence, departments are failing to foresee obstacles to successful delivery. Moreover, one-fifth of all projects that have undertaken more than one review have got worse as they progressed through the process, and over 40% have not improved their status (Figure 3). Figure 3: Performance of the 67 projects which had undertaken two or more colour-coded Gateway Reviews to end of March 2004


Source: National Audit Office/Office of Government Commerce

11. The OGC's Supervisory Board is chaired by the Chief Secretary to the Treasury and made up of Permanent Secretaries, including the OGC's Chief Executive, and senior external representatives. It currently receives, each quarter, an analysis of Gateway Review results broken down by their Red-Amber-Green status.[17]

12. A red review at an early stage of a project's lifecycle shows that the review process has been successful in identifying risks to successful delivery at an early stage, and as such should be positively interpreted.[18] Successive red reviews, on the other hand, are not acceptable and from April 2003 projects receiving a second consecutive red review have triggered a letter from the Chief Executive of the OGC to the Permanent Secretary of the department responsible. This letter highlights the importance of identifying and addressing risks to successful delivery at the earliest possible stage. Eight IT-enabled projects have since received red gates in consecutive Gateway Reviews. Of these:

  • One has had a subsequent green review, and one an amber
  • One is currently undergoing a further review, and another has requested one; and,
  • The remaining four have not yet requested subsequent reviews.[19]

Late engagement with the Gateway Review process

13. The Gateway Review process examines a project at five critical stages of its lifecycle. In addition there is a Gate 0 to assess the feasibility of programmes at their outset (Figure 4). Half of all Gateway Reviews of IT-enabled programmes and projects across government have been at Gates 2 (Procurement Strategy) and 3 (Investment Decision), and a high proportion of these (63% and 41% respectively) have been first-time reviews.[20] More projects are now coming forward for review earlier and the OGC has made clear to departments that projects can no longer enter the process after Gate 3.[21] Nevertheless 30% of all programmes and projects are still by-passing Gates 0 and 1, and therefore entering the process after the business case has been prepared.[22]Figure 4: The stages of the Gateway Review process
Gateway Stage PurposeDescription
Gateway Review 0
Strategic assessment
Establish business need for programme
Asks how the proposed programme meets the business need that lies behind it. Assesses the capability of those who are responsible for the programme and the support of users and stakeholders.
Gateway Review 1
Business justification
Develop business case Asks whether the end project is feasible, affordable, and likely to achieve value for money. Also whether the high-level plans for establishing it are clear and realistic.
Gateway Review 2
Procurement strategy
Develop procurement strategy Asks whether the tendering strategy sufficiently reflects business requirements, awareness of the market, good practice in procurement, and changes to business need. Asks whether funding is available for the whole project, and with adequate financial controls in place.
Gateway Review 3
Investment decision
Competitive procurement Asks whether the tendering process has met its objectives and followed good practice, and whether the prospective contractor is likely to deliver on time, within budget and achieve value for money. Assesses readiness of the business to implement the contract.
Gateway Review 4
Readiness for service
Award and implement contract Assesses whether project plans are up to date, and adapted to working successfully with the contractor. Asks whether implementation of the project is going to plan, with any lessons for the future being recorded.
Gateway Review 5
Benefits evaluation
(repeated as required)
ClosureAssesses whether expected benefits are being delivered, and what is being done to pursue continued improvements. Asks what contingency plans there are for future changes.


Source: National Audit Office/Office of Government Commerce

Final Reviews

14. Gate 5 Reviews are designed to make an assessment of the overall success of the project or programme, including whether value for money and desired service improvements have been achieved. Sixty-two Reviews have been completed at Gate 4 to date and yet only eight, (13%) have proceeded to Gate 5.[23] From March 2004, departmental Centres of Excellence have been required to investigate those projects which have not requested a Gate 5 review within 12 months of completing Gate 4; seven more projects have subsequently completed a Gate 5 review.[24]

Wider dissemination of Gateway reports

15. As key stakeholders in IT projects, suppliers are keen to be involved in the Gateway Review process, yet review teams do not necessarily canvass the views of suppliers, or indeed tell them when Gateway Reviews are taking place, losing the chance to hear their views.[25] While Gateway reports are increasingly scrutinised at the highest levels within departments there is currently no requirement for findings to be shared with suppliers.[26] There is no evidence that suppliers would object to Gateway Reviews being published,[27] and there is a view among senior stakeholders that at least key parts of Gateway Reviews should be shared with them.[28]

Gateway reports and Freedom of Information

16. At the time of our hearing, the OGC was assessing the implications of the Freedom of Information Act, which came into effect on 1 January 2005, for their policy on the general disclosure of Gateway Review information, including looking closely at exemptions 35 and 36. OGC will assess any requests for sight of Gateway reports on a case by case basis, taking into account all public interest arguments.[29] Ultimately, however, it will be the responsibility of the Information Commissioner to pronounce on their disclosure.


14   Q 42; C&AG's Report, para 1.10 Back

15   C&AG's Report, para 2.5 Back

16   Q 1; C&AG's Report, para 2.15 Back

17   C&AG's Report, Improving Procurement (HC 361-1, Session 2003-04), para 1.6 Back

18   C&AG's Report, para 2.8 Back

19   Ev 14 Back

20   C&AG's Report, para 2.10 Back

21   Qq 20-21 Back

22   Q 20 Back

23   C&AG's Report, para 2.11 Back

24   Qq 21, 56 Back

25   Q 37 Back

26   C&AG's Report, para 2.18 Back

27   Q 69 Back

28   C&AG's Report, para 2.17 Back

29   Q 71 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 5 July 2005