Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 60-79)

MINISTRY OF DEFENCE

29 NOVEMBER 2004

  Q60 Mr Jenkins: I was hoping, now they are in a position where they can be used and they comply with health and safety, that we could actually get rid of them to another nation.

  Sir Kevin Tebbit: We are getting rid of them to individuals like mountain rescue teams or adventure training people. They are the sort of people who are buying them.

  Q61 Mr Jenkins: I am back to the Global Positioning System now and, as the General said, we have a piece of equipment here for £4,000, 10 times the cost, that will last 20 years. I do not have a computer that is 20 years old and I do not have a piece of kit that is 20 years old, in fact, if I have got a piece of kit that is five years old, it is normally obsolete. Do you think 20 years is a good lifetime?

  General Fulton: Did I say it would last 20 years?

  Q62 Mr Jenkins: I thought you gave an indication that it might last a lifetime.

  General Fulton: If I did, I apologise, because I do not know what the expected life of the military GPS is.

  Q63 Mr Jenkins: We do tend to buy things which are very well constructed and on occasions I have been in places where they say that a piece of equipment will withstand a bomb blast from 10 metres away. It is a pity the operator will not, but the equipment will last. Are we over-engineering this equipment?

  General Fulton: I think the right approach is to look at the way in which this equipment is going to be used. Clearly there are certain uses on the battlefield, for example in an artillery OP right up in the front line, where we do need firstly, the extremely high precision and secondly, we do need the protection. There may be other uses of Global Positioning Systems, for example in the lines of communication, moving soft-skin vehicles up and down roads, where you neither need the same precision, nor do you need the same level of protection. I think it is a question of matching the requirement to the need and understanding both and not then either over-engineering or paying over the odds.

  Q64 Mr Jenkins: What about need then? The tactical data links for tanker aircraft have been a recurring requirement. We have had them fitted in Kosovo, in Afghanistan and in southern Iraq. If they are so invaluable to air crews, and I do not doubt they are, why are they not fitted permanently into all our tanker fleet?

  Sir Kevin Tebbit: We had a programme in 1996 which was cancelled and that would have done that. That was a programme which was going to cost £97 million in 1997 prices. It was cancelled because at the time it was felt it was not a high enough priority to justify the cost. We then found ourselves operating with the United States in Kosovo, in the air campaign and these things became very important. We bought some through the UOR process for that campaign. After the campaign, we kept them. Then in Afghanistan, again operating with the United States, because the system does link into their system called Link 16, we bought some more. And we bought further enhancements for more tanker aircraft, this time for Telic. This is the one example I am aware of where it has actually been more cost effective to enhance and upgrade the fleet by progressive UOR action than would have been with that original investment of £97 million. It is a bit special, because retiring the Sea Harrier aircraft has meant we have been able to take equipment from them and put them onto the Nimrod and VC10 tanker fleet. But it has actually been quite a useful way forward.

  Q65 Mr Jenkins: I should like to ask you about the impact. When the Department has to deliver these 212 urgent operational requirements, I know it costs only 4% of your budget, but what effect does it have on major programmes with regard to the manpower in the department or the suppliers? Does it actually push any of our programmes back by having this fire-fighting approach, jumping in and saying you want this pretty quickly?

  Sir Kevin Tebbit: It is certainly true that the same staff that do our normal equipment programme did this, as it were, as their night job in addition to their day job and people in industry as well. They seemed to do it with absolute commitment and relish and, as far as I am aware, there were no slippages. These are the sort of people General Fulton actually employs directly and I do not know what he thinks.

  General Fulton: I do not think it has had any effect on the rest of the equipment programme. What I do think it represents is the department going onto a war footing at exactly the time that the rest of the armed forces were and none of my people begrudges one minute of the time they spend doing this because they know that their colleagues, those in the units from which they have just come, or units to which they will go, are also preparing for the most important thing that the country is engaged in at that time. Yes, they do have to work harder, but I think it is exactly what they ought to be doing.

  Mr Jenkins: Excellent. We cannot blame that for the slippage in our legacy programmes then.

  Q66 Mr Williams: I share with the Chairman the agreement with the Report, that it is a good Report as far as the Department is concerned and as far as the people who carried out the necessary emergency arrangements were concerned and would join him in congratulating them. I suppose in a way the switch to small rapid reaction forces increases the risk element: the risk on the one hand of not having what is required and on the other hand having equipment you may hardly ever use. Is this problem that you are trying to address here one which is actually increasing as our strategic concept of defence changes?

  Sir Kevin Tebbit: That is a very interesting question and it is one I ask myself. In fact, when I was preparing for this hearing, I was trying to get information on what proportion of our force that we took to the Gulf in 1991 was augmented by UORs and indeed what we did at the Falklands, because I did not have that comparator and I thought that would be quite interesting. Sadly, I am still waiting for the information because it seems to be in archives and I am trying to recreate it. I think I will continue doing that, because it is an interesting question.

  Q67 Mr Williams: It would be interesting.

  Sir Kevin Tebbit: In terms of where we are now, the problem is of course that we do have an increased number of relatively small-scale operations, but we also have, in this case, a very big large-scale operation as well, so it is quite hard to give you a specific answer. My sense is that we certainly have to keep agile and fast. We need to do that in our basic infrastructure as well; our basic programme should be geared towards that. We cannot switch that programme onto that more agile footing as fast as I would like because of these very big programmes we have which have existed over a large number of years and we cannot move as quickly in that respect because of contractual obligations. In any case, those big platforms are going to be needed for the future. But we do need to think of how we can do better to respond to fast-moving situations, not necessarily just through the UOR process.

  Q68 Mr Williams: It is clearly a very different situation from when you had the large land mass type operation which was envisaged during the Cold War.

  Sir Kevin Tebbit: We knew where it was, we knew the opponent, everything, the strategy and tactics were exactly clear.

  Q69 Mr Williams: In the case of Iraq and for reasons outside our consideration it was a rather long-drawn out process between the initial decision to start deployment and the eventual decision to go to war. At what stage do you start with your UOR operation? Immediately from the instruction to start deployment, or do you gamble on the fact that it is gunboat diplomacy that may never come to anything? How do you make that decision?

  Sir Kevin Tebbit: I think there are several stages. The very first stage, starting from sort of the spring of 2002, was staffs, informally, simply asking themselves questions about whether, if they had to do anything, the UOR process was viable, was in good shape, sort of internal contingency planning that was not even planning. The actual planning as such, I would have said, began in September 2002 when there were discussions with the Treasury about money, as a first tranche, and the stage at which planning got to the stage where we could go out to industry was, I think, November, I am sure it is in the Report, after the Secretary for Defence made a public statement and we were able then to do that. Through that period, through the autumn, there were difficult judgments as between going quickly to get UORs done and not going in the areas where to do so would signal determination to go to war rather than to pursue a diplomatic route. So there were some sorts of equipment where we could just go ahead, because getting more of the same was not particularly delicate or signalling, as distinct from certain procurements which would be very clearly focused on war fighting. But then, at the final stage of course the plans changed. Until the middle of January, we still were planning for a role in northern Iraq, having gone through Turkey. It was not until the middle of January that that option was closed off and we had to switch very, very short-term indeed, to a southern Iraq option. The real achievement was the UORs which were procured specifically for that; this All-Terrain Mobile Platform was suddenly in the frame at that stage. The mine-sweeping measures and other things for the amphibious forces did not appear until January, because before then we were thinking of a heavily armoured intervention from a different location. What arose at the end was an unusual combination of force packages, so there was a very frantic last phase where things were different from the previously assumed type of build-up.

  Q70 Mr Williams: We are told about the Treasury's role in this, that they manage a special reserve effectively. Is this part of the normal contingency reserve, or is it a separate reserve again for emergency action.

  Mr Glicksman: It is specially identified and the Chancellor of the Exchequer has indicated publicly the size of this reserve in budget announcements and spending review announcements.

  Q71 Mr Williams: What is the size as a matter of academic interest?

  Mr Glicksman: At the moment it stands at £3.8 billion, but the Chancellor of the Exchequer keeps it under review and, if necessary, he will change it.

  Q72 Mr Williams: Mr Bacon has referred to £110 million, but is there an expedited procedure for releasing this money? From the Ministry of Defence's point of view is it a bureaucratic process to go through to get Treasury to release the cash, or is it almost automatic on demand?

  Sir Kevin Tebbit: Within that heading, which is for everything not just equipment of course, for all additional costs, provided the items are scrutinised and agreed with Treasury officials, by and large it goes through. What we have to do is create supplementary estimates in the defence budget coming through at various times of the year to take that money onto our vote with the authorisation of the Treasury.

  Q73 Mr Williams: Take the situation that you have identified as really interesting in January, that you expected to come in through the north with heavy armour and then you are coming up through the south. How long from identifying that this was going to need X million extra—and I know you could not give a final sum—how long from your initial identification of that need would it take you to get the release of the money from the Treasury?

  Sir Kevin Tebbit: Provided the Treasury agreed the basic costs, that was assumed. We could go forward with the programme and then it was a question of parliamentary authorisation to regularise that position.

  Q74 Mr Williams: Will the £658 million that you have referred to have any repercussions as far as your major equipment programmes are concerned or is it entirely accommodated? I understand that it says that where there are accelerated availabilities that is taken into account, but where there are new requirements, do these then have to be met in any way out of your major defence programmes, or is it just completely absorbed by Treasury?

  Sir Kevin Tebbit: Other than those programmes which we are taking into our core budget, other than the ones we were already planning for in future years which have to be deducted, the Treasury do not make any deduction on the defence programme as a result of these extra costs. I can speculate as to whether there might have been more money for defence if we had not had these big demands on the reserve, because £3.8 billion is a lot of resource and I sometimes wonder whether some of it might have been available for the normal defence activity had it not been required for this. That apart, basically there is no deduction from the defence programme, but when we want to keep things which we had not previously budgeted for, and I think the Report accurately says we are thinking of keeping something like 44% of the equipment used in the operation and actually we are now going to try to keep about 50%, because it is logical to do so. If we have had equipment that has been hardened or tested in battle conditions and it has worked and been really useful, then we do try to take it into the core programme and clearly then we have to accommodate it and other things would have to be pushed out in order to do that. We would have to reprioritise.

  Q75 Mr Williams: Mr Bacon referred to the £110 million which is being repaid to Treasury. Was this an argued-over figure or was it a fairly easily identifiable figure? How was it arrived at?

  Sir Kevin Tebbit: Quite clearly these were things we had in the full programme. We got money from the Treasury to advance their arrival into the force structure. They were pretty clearly identified and deductions made in the future planning finances. It was sufficiently straightforward for it not to come to my personal attention. Officials sorted out that money.

  Q76 Mr Williams: Someone raised a question earlier on and you referred to IT. Only the other week we had the OGC here talking about the red gateways and yellow gateways and green gateways. I gather you are outside their gateway system. Why is that?

  Sir Kevin Tebbit: Because we have a large programme, not just of IT but of other things, the whole equipment programme, we already had an existing process of scrutiny, gateways and phases of projects. As a result of the strategic defence review we had a specific McKinsey review of defence procurement. They gave us a model for this process which we are using. It is not exactly the same as the OGC one, but we are aligning it, we are part of their process. We do benchmarking exercises and peer reviews of each other's programmes and that sort of thing. It is not a significant difference.

  Q77 Mr Williams: In that respect, do you remember, Sir John, when we were dealing with OGC they agreed that it would be helpful to have your support and our support in terms of monitoring the red gateways and having quarterly reports from you. Is there any benefit in doing something of that sort, or is it already implicit in what you are doing as far as MoD is concerned?

  Sir John Bourn: It does of course lie within the work that we do. I have been discussing with Mr Alton how we set up that system for civil procurement and I will talk to Sir Kevin about the possibility of covering, either as part of that system or separately, the defence project arrangements.

  Sir Kevin Tebbit: We sit on his steering group. The MoD is sitting on the OGC steering group. The differences are probably more of form than of substance.

  Q78 Mr Williams: You will accommodate them within this new quarterly system you are hoping to evolve.

  Sir John Bourn: Yes.

  Q79 Chairman: Following up an earlier line of questioning from Mr Williams, I want to get the chronology right. I am looking at a report in The Guardian dated 19 November 2004 on the publication of this NAO Report. I want to read out the first part of this Report in The Guardian to see whether you believe it is a fair description of what happened because the chronology in the wider aspect of all this is terribly important. It is headed "MoD ordered Iraq supplies `in a rush'". You may wish to comment on that. It says "The Ministry of Defence did not begin to order equipment it needed to invade Iraq until months after it began to consider the implications of war, a report by parliament's financial watchdog discloses today. Detailed operational planning began only after Tony Blair's speech to MPs on September 24 2002, in which he launched the government's controversial dossier on Iraq's banned weapons programme, says the National Audit Office. That speech triggered a frantic search for equipment, including missiles, radars and communication systems, it says. Between then and the invasion six months later, the MoD processed nearly 200 `urgent operational requirements' at a cost of £510 million. Military commanders started to discuss the need to order equipment for an invasion of Iraq back in May 2002". We have that date of May 2002 and then we have the earlier reference to Mr Blair's speech on 24 September 2002. "Senior MoD officials have already admitted that delays in getting vital equipment, including body armour, to British troops in time for the invasion were the result of political considerations. Sir Kevin Tebbit, the ministry's most senior official, told MPs earlier this year: `Clearly there was a political inhibition against action that would make it clear that we would take the military rather than the diplomatic route'. Is that a fair description in The Guardian of what happened?

  Sir Kevin Tebbit: Not entirely and I should not like to be held to newspaper reports.


 
previous page contents next page