Select Committee on Transport Written Evidence


Memorandum by the Secretary of State for Transport (RP 21)

M6 TOLL ROAD AND PROPOSED EXPRESSWAY BETWEEN JUNCTIONS 11A AND 19 ON THE M6

  1.  In July 2004, the Department launched the consultation "M6: giving motorists a choice" and published the "M6 Toll Traffic Monitoring Study" looking at the impact of the M6 Toll Road since its opening in December 2003.

  2.  Because of rising traffic, leading to increasing congestion on the M6, the Government announced on 10 December 2002 support for the need to widen the M6 between Birmingham and Manchester. With the consultation "M6: giving motorists a choice", the Government is seeking views on a possible alternative to traditional widening of the existing M6 by the construction of a new Expressway (a toll road) alongside the existing M6 between junctions 11a and 19.

  3.  The "M6 Toll Traffic Monitoring Study" represents an assessment of impacts of the M6 Toll in the first full three months to end of March 2004 since the road opened in the week commencing 8 December 2003. The study compares traffic conditions in November 2003 prior to opening of the M6 Toll with traffic conditions in February/March 2004 (depending on data availability) after opening. Of course it is too early to identify the full and long-term impact of the M6 Toll on the existing M6 and other roads. But the initial findings are important. A detailed one-year "after" report was to be produced to provide greater information on the impact of the M6 Toll; this will now be deferred until Spring 2005 to take account of ongoing roadworks on the existing M6 which will have a significant impact.

How effective has the existing M6 Toll road been in tackling congestion on the M6, on the new toll road itself and on the surrounding area?

  4.  The Monitoring Study reports that journey time delays experienced in peak hour periods on the existing M6 through the West Midlands conurbation on week days have reduced since the opening of the M6 Toll; with the more noticeable effect being during the evening peak period.

  5.  Prior to the opening of the M6 Toll, the existing M6 on Fridays showed an extended afternoon peak period of significant congestion (created by a mix of commuter traffic and longer distance traffic movements). Since the opening of the M6 Toll, this extended afternoon peak is significantly reduced, with delays reduced by up to one hour for northbound traffic and a shortened two hour peak period of traffic delay for southbound movements.

  6.  Sunday journey time delays on the M6 southbound for returning weekend traffic are not experienced since the opening of the M6 Toll. The transfer of a proportion of traffic to the M6 Toll provides sufficient relief, such that journey times are also improved for M6 traffic. There is now little difference in journey times for traffic using the existing M6 or M6 Toll on Sundays.

  7.  These reduced journey times for through movements provide significant benefits for both northbound and southbound movements on both the existing M6 and the M6 Toll. Weekday journey timesavings are on average 12 minutes northbound and seven minutes southbound, with maximum timesavings of around 30 minutes during midweek peak hours and up to 70 minutes on Fridays. On Sundays, southbound journey times are up to 30 minutes faster than the same journey before the M6 Toll opened.

  8.  The M6 Toll has removed a significant amount of traffic away from the M6, such that the M6 itself has improved operating conditions and journey times. This reduction in traffic has meant that through journey times on the M6 have also improved. Weekday journey timesavings are up to 16 minutes and up to an hour on Fridays.

  9.  However, the Monitoring Study does suggest that the changing operating conditions indicates that traffic on the M6 is oscillating, and that the following pattern may be currently happening:

    (a)  the M6 is heavily congested—the M6 Toll opens-traffic decides it is worth paying a toll to save time, achieve reliability etc and diverts to the M6 Toll;

    (b)  conditions on the M6 improve;

    (c)  it becomes known by those using the M6 Toll that the M6 is free-flowing and thus they start diverting back to the M6—resulting in a return to some congestion and delays on the M6; and

    (d)  this process then oscillates until equilibrium is achieved.

  10.  The Monitoring Study shows that, in the short term, a net 10% reduction in traffic has been achieved on the M6 with significant improvements in operating conditions since the opening of the M6 Toll. As traffic volumes oscillate, it is not clear at present how much of a switch back from the M6 Toll to the M6 would cause major congestion on the M6.

  11.  The Monitoring Study concludes that it is beneficial to all parties for through traffic to use the M6 Toll, so that the M6 does not revert back to serious congestion and unreliable journey times.

What impact has the M6 Toll had on traffic levels?

  12.  At the time of the Monitoring Study, daily traffic volumes of up to 37,000 vehicles per day (vpd) are shown on the M6 Toll. The Study shows a significant month on month increase on all days and all of the three sections of the M6 Toll for which data is available. These increases have continued since the formal Study and the Concessionaire, Midland Expressway Limited (MEL) is reporting average daily figures for August of over 55,000 vpd.

  13.  The Study shows there have been significant reductions in traffic on the M6 through the conurbation between junctions 4 and 11; a reduction of approximately 10% of traffic on weekdays on the M6; increasing to over 15% on Saturdays and over 20% on Sundays. The reductions in traffic volumes in the peak hours are significantly less.

  14.  There are increases in traffic volumes of approximately 5% on the M6 at either end of the M6 Toll, and on the M42 approaching the M6 Toll.

  15.  The reductions are almost entirely due to reductions in the number of light vehicles, with no change to the number of heavy goods vehicles (HGVs) on the M6. The M6 Toll Concessionaire, in seeking to encourage hauliers to use the new road, has recently introduced a significant discount for HGVs for an extended trial period until 31 December 2004.

  16.  On individual roads within the scope of the Study, significant changes are shown reflecting complex changes in traffic patterns. For example, the A50 at Stoke-on-Trent shows a reduction in daily traffic volumes of approximately 18 %. There have also been reductions in weekday traffic volumes on many other roads in the conurbation totalling about 17,000 vpd (figures exclude the M6). There has, however, been some traffic growth to the south of the M6 Toll tie-in junction during AM and PM peak periods.

Is a new "Expressway" preferable to widening the existing road?

  17.  It is the purpose of the current consultation exercise to seek views, including those of the Committee, on this issue before the Government decides whether to commission a more detailed feasibility study into the Expressway concept. The consultation document "M6: giving motorists a choice" states that, for road users, there could be many potential advantages in constructing the new tolled Expressway linking Birmingham and Manchester including:

    —  Drivers would have the choice of using the M6 or paying for a quicker trip, as is the case with the M6 Toll. Those drivers benefiting from the faster toll road also improve conditions for those choosing the original road. By opting for the Expressway, these drivers free up space on the existing road, contributing to more reliable journeys for everyone.

    —  The Expressway could be constructed mainly without affecting traffic on the existing road. But it should be recognised that it would have to connect to M6 at either end and that this would most likely require some part of the Expressway to cross over M6 in at least two locations. However, widening the existing M6 would involve significantly more disruption and additional congestion during construction work. An M6 Expressway is unlikely to reach a start of works until 2012, but because far less work would affect the existing M6 traffic, compared to the conventional widening option, it would be expected to be constructed faster, possibly of saving to two years off the required six year construction period for conventional widening, and be completed around the same 2016 date as a traditional widening option. In both cases, Government will do everything in its power to complete ahead of 2016.

    —  The Expressway could be designed to cater more for long distance journeys, benefiting a high proportion of current users. For example, about 40% of users travel between junction 19 and junction 11a. A road with fewer and more strategic junctions would give improved traffic flow conditions and hence greater reliability.

  18.  A further consideration is that a widened M6 would continue to suffer incident related congestion and its effects, albeit that a wider carriageway could allow earlier re-opening in some circumstances. However, an Expressway solution would support incident management by: (a) reducing the impact of such incidents on overall traffic and (b) providing added flexibility to manage those incidents, owing to the provision of a ready-made alternative for traffic approaching a blocked section of motorway.

Is this the most cost effective and environmentally effective solution?

  19.  A parallel Expressway, providing two lanes in each direction, would provide more reliable traffic conditions at a lower cost than adding two lanes to the existing road. To widen the existing M6 could cost around £40 million per mile; overall this could be around 10% more than building a new dual two lane Expressway. Widening schemes must allow for rebuilding much wider bridges and for complex traffic management during construction.

  20.  A parallel Expressway would involve greater land take than widening the existing road. Preliminary work suggests the minimum difference might be around 10 metres in width, 35 to 40 metres being needed as opposed to 25 to 30 metres needed for traditional widening assuming the Expressway were built adjacent to the existing motorway. However, the Expressway could move away from running immediately alongside the existing motorway. This could happen where there are distinct advantages and benefits in doing so, that outweigh the environmental impacts of either affecting more land or proposing a new road in a location away from the existing M6, or where there are significant geometric or cost disbenefits for example, to avoid having to demolish some existing bridges over the M6.

  21.  Careful consideration would be given to the extent to which constructing a new route—close but not necessarily adjoining the M6—could provide opportunities for mitigating environmental impact, compared with the constraints of widening the existing route. Opportunities open to investigation could involve: Building sections of Expressway at a lower level than the adjoining M6; introducing modern screening techniques such as mounded areas of new planting; considering where benefit could arise through avoiding established vegetation and habitats by moving Expressway away from the existing M6; and introducing new screening alongside the existing M6 as part of the overall scheme.

  22.  The wider environmental implications, including visual intrusion and the effect on landscape, biodiversity, cultural heritage, local air quality and greenhouse gas emissions would be explored in any feasibility study. There would also be an assessment of what construction of the Expressway might mean for traffic levels overall and in the surrounding area. The investigation would include looking at the scope for high quality measures to combat adverse effects.

  23.  If a decision is taken, following the consultation exercise, to carry out a detailed feasibility study, the full range of potential social, economic and environmental impacts of an Expressway will be assessed—including assessing the scope for minimising any adverse impacts, as well as maximising the benefits. No final decision would be taken on whether to widen the existing motorway or construct an Expressway until a fuller assessment of the Expressway proposal has been completed.

Have there been any unforeseen impacts of the existing M6 Toll?

  24.  It is worthwhile noting the following issues, which are not necessarily related:

    —  It was always recognised that diversions of traffic from the existing M6 to the M6 Toll would hide a complex set of changing traffic patterns. Hence a diversion of through traffic, which represents about one third of M6 traffic, would release capacity on the existing M6 which could then be used by local traffic within the West Midlands, providing significant relief to many local roads within the conurbation. The Monitoring Study shows that the since opening of the M6 Toll, there has been a significant net reduction in traffic using the M6 (around 10% weekdays, over 15% Saturdays and over 20% Sundays).

    —  The Monitoring Study also shows that since the opening of the M6 Toll, there have already been significant changes to traffic patterns to many local roads. However, this initial impact must be tempered with awareness of the oscillation effects referred to in paragraph 9 above. In addition the monitoring results so far obtained are still very short term—and will be affected by, say, the current roadworks. Hence a longer-term view is necessary to verify substantive changes to traffic flow patterns.

    —  The M6 Toll Concessionaire is actively targeting all users and particularly freight to take up the option of utilising their TAG system to improve efficiency at the Toll Booths.

    —  There has been some criticism of the amount of freedom allowed to the M6 Toll Concessionaire in setting toll levels. Under the provisions of the legislation governing tolling at the M6 Toll (the New Roads and Street Works Act 1991), the Concessionaire is responsible for all aspects of the operation of the M6 Toll, including the level of tolls. The view at the time of the making of the legislation being that such undertakings would be wholly privately financed, therefore, it was right that a Concessionaire should be able to recoup their costs through setting toll levels, just as any commercial company sets the price for its products.

    —  The criticisms about lack of state control of toll levels particularly arose from the haulage industry in response to the toll charges announced for HGVs. As a result of those initial toll levels, hauliers have been averse to use the M6 Toll which means, as stated in paragraph 15 above, that reductions on the M6 are almost entirely due to reductions in the number of light vehicles, with no change to the number of HGVs. However, this same lack of state control has allowed the Concessionaire to respond quickly after discussions with hauliers and others in introducing a significant discount for HGVs for an extended trial period.

  25.  If the decision is to taken carry out a detailed feasibility study into the Expressway concept then consideration would be given as part of this exercise whether it would be appropriate to go down the private finance/concession route and what, if any, level of state control should be placed on toll charges.

September 2004





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 2 August 2005