Select Committee on Transport Written Evidence


Memorandum by D Scott Hellewell (LR 25)

INTEGRATED TRANSPORT:  THE FUTURE OF LIGHT RAIL AND MODERN TRAMS IN BRITAIN

1.  INTRODUCTION:  INTEGRATED TRANSPORT

  1.1  The Transport Committee is undertaking its inquiry into Light Rail as part of an overarching inquiry into Integrated Transport. By way of introduction, and to assist Members in settling the scene, it may be helpful to provide a brief description of Integrated Public Transport.

  1.2  Integrated Public Transport is where all the different types (modes) of public transport—bus, trams, trains, ferries—and all operators work together in some framework, whereby their individual services are operated to complement each other. The integrated public transport network is then marketed as one network with a fares and ticketing system to cover all operators and modes, thus permitting free and easy interchange. Such a network offers a realistic alternative to the private car for many journeys. The 1968 Transport Act and the PTA/PTEs were established for this very purpose, as was TfL.

  1.3  Good examples of integrated transport exist throughout Continental Europe, Scandinavia, Boston, New York and San Francisco and Toronto.

2.  THE COSTS AND BENEFITS OF LIGHT RAIL

2.1  Costs

  2.1.1  These arise under the following headings: Promotional Costs, Bidding Costs, Capital Costs, Operating Costs, Finance, funding & fees.

  2.1.2  Promotional Costs are those incurred by the Promoter, usually a PTE or a Consortium of Local Authorities, eg South Hampshire Transit. They are the costs involved in planning the LRT scheme and the preparation of documents required to make a submission for an Order under the Transport & Works Act (TWA) 1992. Documentation will include alignment plans and cross-sections, a Book of Reference of affected parties and an Environmental Impact Statement. It will mean identifying all the utilities en route. It is a major piece of work which can take between two and five years—depending upon length of alignment and complexity—and cost between £1 and £5 million.

  2.1.3  This process should be simplified so that only the minimum work is necessary to identify quickly the broad cost and impact of the scheme so it can receive, in effect, "Outline Planning Permission". There would then be a second stage, when all the detail would be produced, knowing that the scheme was likely to proceed.

  2.1.4  The Secretary of State is likely to call in the LRT Scheme and to hold a Public Inquiry. Historically there have been delays in establishing the inquiry and further delay (up to two years) before the Secretary of State gave his reply. The length of inquiries has ranged from a few days to many weeks. The cost of this stage, involving Legal Counsel, etc, can be up to £1-2 million.

  2.1.6  Bidding Costs are those involved by companies bidding to design, build, operate and maintain the project, are dependent upon the actual procurement method adopted for the LRT scheme. (The pros and cons of different financing arrangements are considered in Section 6.) The design element can duplicate some of the work done by the Promoter in obtaining Powers. Historically consortia of companies have assembled to bid for LRT projects, because of the wide expertise needed and to spread the risk. Typically bidding costs will be in the range of £3-5 million. Typically four or five consortia will bid, involving expenditure of £12-25 million. Only one can be successful, even then there is no guarantee that the project will go ahead, eg Metrolink Extensions. These costs are taken entirely by the private sector.

  2.1.7  Thus, before the project has started and with no benefit to the travelling public, £17-37 million has been spent, the majority private sector risk. If the project does not proceed, this money has been wasted. The opportunity cost of this expenditure is significant. The inherent risks are substantial. These issues need to be addressed.

  2.1.8  Capital Costs are made up of:

    (a)  Infrastructure Costs: the building and installing of track, power supply, bridge and cutting work, service diversions, traffic management arrangements, stations, depot, control room, offices, etc.

    (b)  Vehicles: supply of light rail vehicles and any other mechanical equipment needed.

  Capital costs have increased recently, partly as a backlash from capital costs associated with heavy rail. However, it tends to be the risk factors associated with projects, eg scope of service diversions and complexities of traffic management arrangements, that have lead to this increase in costs. The greater the design undertaken initially (however achieved), the less the risk when it comes to pricing the job (and the better quality of work). For many of the elements there are only a relatively limited number of suppliers, unless Continental sources are used, many of whom are reluctant to get involved in the UK LRT market. Also the Regulatory Authorities (HSE, HMRI, Disability Units, etc) have unduly onerous requirements relative to EU Standards. There is also the "uniqueness" of each UK LRT scheme, the lack of standardisation resulting.

  2.1.9  Designs of new and cheaper track forms, eg LR55 and simpler tram designs incorporating automotive and industrial technology, have been privately developed. But progress over these last 10 years has been slow and disappointing, largely because no Promoter or Constructor was prepared to take the risk and no Government Grants were available.

  2.1.10  All these issues must be addressed. However, many of the problems stem from the procurement method adopted in this country, which will be considered in Section 6.

  2.1.11  Operating costs are made up of:

    (a)  Pre-Operational Costs involved during the design, development and building stages, the build-up of the operating team, the preparation of documentation, recruitment, training and examination of staff and test and trial running. These are all incurred before fare-paying service commences.

    (b)  Steady-state Operating Costs are the costs of operating and maintaining the LRT system to provide the service specified by the promoter.

  Provided experienced operators are involved it is not too difficult to make reasonably accurate estimates of these costs. However, the longer the operating concession, the more difficult it is to forecast operating costs.

  2.1.12  LRT schemes are expected to operate without any subsidy. It follows that fares income must exceed operating costs. Fares are usually left to be determined by the Concessionaire, however competition in the market place affects the maximum fares that can be charged. Outside London public transport is deregulated and it is very difficult to assess over the life of an operating concession what degree of competition the LRT scheme will experience. In spite of tight control on operating and maintenance costs, competition can affect fare income and thus operations become loss-making. This is a major risk and leads to lenders assuming the lowest passenger revenues and charging a high risk premium, thus affecting the scheme's viability.

  2.1.13  Financing and Funding Costs. The method by which LRT schemes have been procured in Britain all involve the private sector taking substantial risks at every stage in the development, building and operating the project. Risk is added at every step, the cumulative effect of which is to price up UK LRT schemes. Furthermore, all the relationships: Promoter to Constructor and/or Operator; between the Individual Consortia members: designer-builder-operator/maintainer are subject to complex contractual arrangements, each involving penalty and termination clauses. There is a very high cost of lawyer's and financier's fees involved which could be greatly reduced if a simpler and more traditional approach was adopted.

  2.1.14  Risk: in the foregoing consideration of costs "risk" has been mentioned frequently. The NAO Report(1) made reference to risk and its allocation. By careful work at each stage risk can be greatly reduced and accurately quantified. If the present amount of time spent on financial and legal matters was applied to the reduction and assessment of risk, it would not feature so highly in UK LRT projects. Furthermore, the cost of risk is frequently compounded at each stage of the bid process. In the case of Metrolink extensions "£80 million contingency was built in on top of the 10% contingency that the bidders had included, and the 5-6% contingency included by the sub-contractors"(2). Is there any wonder LRT schemes cost so much in Britain!

2.2  Benefits of Light Rail

  2.2.1  LRT offers safe, quick, reliable transport, accessible to all, using non-polluting power at point-of-use and is sustainable, and kind to the environment. It very nearly combines the best features of trains and buses—the safety and reliability of trains and the frequency and accessibility of the bus. Worldwide it has shown its ability to persuade motorists to leave their cars. Where allowed to do so, it has often been the catalyst in regenerating run-down areas (eg Docklands) or permitted the opening up of remote new housing areas (eg Antwerp).

  2.2.2  Because of its flexibility (compared to heavy rail) it can be fitted into existing city centres, including narrow streets and pedestrian areas. Surface treatments can vary from a variety of pavings to grassed track. Because stops (or stations) are simple they can be located to suit passenger demand and are accessible to all. Light rail can take over run-down or infrequent heavy rail passenger services or freight-only lines or disused alignments (eg Manchester Metrolink). By building new street-running city centre sections, whole new LRT networks can be created.

  2.2.3  Under the appropriate conditions LRT can run out into the suburbs of a large city region (thereby offering through seamless travel) by sharing track with heavy rail services (eg Karlsruhe). There are really no limits to what LRT can achieve and the benefits it can give.

  2.2.4  LRT scores well under all five categories of the Government's New approach to Appraisal (NATA) to which all transport projects are subjected. The five categories are: environment, safety, economy, accessibility and integration. It should also be noted that in the case of both Metrolink extensions and the Leeds Supertram Scheme, buses cannot achieve sufficient benefits to offer a satisfactory alternative.

3.  WHAT LIGHT RAIL SYSTEMS NEED TO BE SUCCESSFUL

  3.1  To be successful LRT systems need:

  3.1.1  Reasonable passenger flows: a range of 3,000-15,000 pphpd is often quoted. LRT schemes can be justified on lower flows according to circumstances. Higher flows up to 20,000 pphpd can be accommodated, if allowed for (but not built), at the design stage.

  3.1.2  Quick journey times: relative to the circumstances. This implies commercial speeds (origin—destination) of 18-25 mph. This does not mean high speed, it means carefully located stations at approximately 1-1½ mile intervals and vehicles capable of high acceleration and braking.

  3.1.3  Substantial levels of segregation from other transport to ensure quick and reliable journey times. At least 70% of the system should have its own right-of-way. When running on-street LRT should be accorded priority at all junctions over other traffic.

  3.1.4  Integration with:

    —  land-use, existing and future;

    —  the car, through park and ride provision; and

    —  other public transport: buses and trains, supported by a comprehensive fare and ticketing system covering all public transport in the area concerned.

4.  HOW EFFECTIVELY IS LIGHT RAIL USED AS PART OF AN INTEGRATED TRANSPORT SYSTEM?

  4.1  The NAO Report highlighted the lack of integration of LRT schemes into the urban and transport fabric. Little more can be added to this excellent report. Throughout the World LRT forms the backbone of an integrated public transport system. Only in Britain is LRT expected to compete for market share.

  4.2  Tyne & Wear Metro, opened in stages in the early 1980s as the backbone to an integrated transport system for that conurbation, showed how it should be done and what it could achieve. Following the 1986 Transport Act, which deregulated local public transport, it is now no longer possible to develop such a scheme and, indeed, the Metro has suffered. The Competition Act, and its interpretation, has also compounded the problem.

  4.3  Britain continues to pursue a unique policy in the Developed World, failing to understand the nature of competition in the urban transport market. Competition should not be between buses, trains and trams or between red, blue or green buses. Competition is between quality public transport, properly integrated, and the private car. If the line-haul mode is rail-based or a guided busway, ordinary bus services should be organised to complement it, not to compete with it. Purpose-built, quality interchanges should be built—often integrated with suburban-centre development.

  4.4  LRT also needs integrating into existing and future land-use developments, including regeneration proposals and the up-grading of the city-scape. This takes time, effort and money. Present procurement arrangements tend to prevent such an approach.

  4.5  Until the Government addresses the competition issues identified above, and removes the competitive element to any up-graded line-haul mode, significant improvements to provincial public transport will not occur.

5.  BARRIERS TO THE DEVELOPMENT OF LIGHT RAIL

  5.1  The four main impediments to LRT development in the UK at the present time are:

  5.2  Cost has been dealt with extensively in the opening section of this Submission. Simpler methods of procurement could assist in reducing costs by concentrating more effort in design and consultation and preparing better contract documentation. This would help to reduce risk. Risk needs to be allocated where it can best be handled.

  5.3  Timescale of Implementation is grossly extended in Britain and the situation is getting worse. In the time it has taken Britain to build five schemes, the French have built 10. The Lyon LRT Scheme took only four years from conception to implementation. As has been indicated throughout this document, the UK approach must be simplified and rationalised. Time is money and the British approach does not ensure that the money is spent wisely or cost-effectively.

  5.4  The lack of integration and the Competitive situation, unique to Britain, has been dealt with.

6.  THE EFFECT OF DIFFERENT FINANCING ARRANGEMENTS (PUBLIC/PRIVATE) ON THE OVERALL COST OF LIGHT RAIL SCHEMES

  6.1  The traditional way of procuring an LRT system would be for the public promoter to design it, obtain the Powers and prepare contract documentation, and to invite tenders for its construction. In undertaking this work it would probably use specialist consultants. When inviting tenders it would probably invite separate tenders for construction, trackwork, power supply, etc and for the provision of vehicles. A turnkey approach may sometimes be adopted. The Promoter would, in all probability, then operate the system. This is how Tyne & Wear Metro was procured and how the Glasgow Underground was rebuilt and modernised. It was the method planned for Manchester. This is the simplest and most cost-effective approach but involves more public finance than the current methods of procurement.

  6.2  The first stage of Docklands Light Railway (DLR) was in effect, procured by a single turnkey contract with a private sector consortium, since it proved a very effective way of procuring the initial, small (17½ miles and 15 stations) self-contained system in Docklands.

  6.3  When authorising Manchester Metrolink in 1988 the Government decided to take the DLR arrangement a step further by requiring it to be built under one contract with one private sector consortium, following competitive tendering. The Manchester contract was for Design, Build, Operate & Maintain (DBOM) for the concession period. The Government's objective was to maximise the private sector's input and thus minimise cost and timescale of the project. Subsequently all LRT schemes in Britain have been procured under some variation of the theme DB & OM; DBFinance OM by way of the PPP or PFI process. One feature of this approach is that the Promoter cannot specify any particular element; it can only be done in performance terms. In turn, this leads to a lack of standardisation between schemes.

  6.4  There can be significant benefits in using the DBOM-type approach—provided that is what the Promoter envisaged from the start, since it can reduce the duplication of time and effort at the design stage and allow contractors to make their input. BUT, a project cannot be accurately costed and risk minimised until sufficient design has been done to ensure constructability and operation. Under any arrangement the construction of an LRT system in a urban area is a very complex matter. There are also the changes that will occur during the design process as a result of public consultations and consultations with the public utilities and highway authorities. These skills were (in 1988-1990) not available from the private sector.

  6.5  Consortia who have subsequently built LRT systems or extensions in the UK have amassed a great deal of hard-won knowledge and experience. This they priced into subsequent LRT schemes for which they bid. However, this usually means that they are under-cut by an inexperienced "new boy". It is significant that every LRT scheme or extension in Britain has been built by a different contractor. There are a number of consequences of this: firstly, there is no transfer of experience from one project to another and the same costly mistakes are repeated. Secondly, there is no standardisation or commonality of large or small elements between the schemes. This leads to inflated costs, a perceived unacceptable degree of risk and hence the current situation. At the very least there must be a re-assessment of the risks involved and a fair allocation of them.

  6.6  An LRT scheme is, essentially, a transport scheme—all the other benefits identified earlier may be considered to be "icing on the cake". It is designed to offer a better level of public transport than currently exists. It follows that the input of an experienced Operator must be available from the start to interpret the service specification of the Promoter. These operational inputs are critical to the capital and operating cost of any LRT system. They determine the infrastructure necessary to provide the required services eg track layout, power supply, supervision and control arrangements and the number of vehicles required to provide the service. In turn, this determines many of the annual operating costs that have to be recovered from the farebox.

  6.7  The degree of integration/competition, and the role of the LRT system in the overall public transport network, are critical inputs to passenger demand. The fares to be charged are also a major determinant in the number of passengers forecast to use the various sections of the network. Various model runs can be undertaken to forecast passenger figures. Sensitivity and SWOT analysis can also be used to produce robust passenger and revenue forecasts.

7.  THE PRACTICALITY OF ALTERNATIVES TO LIGHT RAIL, SUCH AS INCREASED INVESTMENT IN BUSES

  7.1  Light rail is only one of many modes of public transport that is available today to the transport planner. The modes vary from minibuses to megabuses via midi, single, double or articulated buses, with Diesel, electric or dual traction. Then come trams, LRT, Metro and heavy rail—the spectrum has never been wider. The skill of the transport planner is to ensure that he uses the right mode for the right job—although if there are more than three modes in a city or four modes in a city-region, passengers can be confused and interchange between them can become a problem. Inevitably it should be "horses-for courses", subject to the above caveat. A pre-feasibility study will, in most cases, reduce the options to three or four different modes or variations of mode. A Feasibility Study will then determine the best value-for-money, using the usual cost-benefit analysis techniques.

  7.2  With the possible exception of Greater London, the bus will always provide the majority of public transport in any town, city or city-region. The bus is a very effective form of public transport, often unjustly maligned. Unfortunately, it has a poor image, although a number of progressive bus operators have worked hard to improve the design and presentation of buses and bus services and have been rewarded by increased passenger numbers and revenues (eg Trent-Barton; Blazefield Group; Brighton & Hove).

  7.3  However, nothing can disguise the fact that the bus shares its "track" with all other road users and thus suffers from traffic congestion. This is exacerbated by inconsiderately parked cars and the problems associated with loading and unloading vehicles at the roadside. Bus lanes can offer a measure of improvement, provided they are continuous and policed. In the UK neither of these conditions often apply (in marked contrast to Dublin's Quality Bus Corridors). Leeds has a number of guided busways but these are in short, detached sections. Pre-emption by buses at traffic signals is virtually non-existent in the UK (although there were trials in Swansea in the 1970s!).

  7.4  Unless local highway authorities are prepared to take the "bull-by-the-horns" and provide extensive and continuous lengths of busway and pre-emption at junctions, the bus will have little attraction to the motorist. The actual banning of car use in city centres is considered to be a non-starter. However widespread introduction of Congestion Charging has already shown its effectiveness.

  7.5  IF, through the adoption of continuous bus lanes and/or guided busways, bus services can become faster and more reliable then the only matter to address is the vehicle itself, its driver and its image. Some progressive operators are already addressing these issues. Much new thought is currently going into bus design. The new "Future" (ftr) bus being developed by First Group, based on a Wright-bodied Volvo artic chassis, offers great prospects and is to be trialled in Yorkshire later this year.

  7.6  Two further points need mentioning. First, in comparable situations buses, even with substantial investment, will not achieve the same level of benefits that LRT could achieve. Bus-based LRT may be cheaper, but benefits are also less. Secondly, whilst substantial lengths of bus priority might be achievable in the suburbs or on a radial road, it is unlikely that they can be achieved in the city centre, because the roads just do not have the necessary capacity. This means that the benefits of speed and reliability achieved on the approach to the city centre are dissipated in the city centre. This is what happens with the otherwise excellent Adelaide Busway in Australia. With LRT you get a whole system including dedicated tracks in the city centre.

  7.7  However, there will always be a case in the larger cities (eg Nottingham) and City-regions (eg Manchester) for LRT networks. These may be created ab-initio from the heaviest used bus corridors (eg Uxbridge Road) where, after evaluation, LRT is shown to be more cost-effective than "ftr" or by the conversion of some existing, heavy rail lines to LRT as has been identified by the SRA recently. The potential for tram-trains as pioneered by Karlsruhe, should also not be forgotten.

  7.8  IF, following detailed analysis of alternative bus-based and LR-based rapid transit schemes, it is concluded that LRT is the best solution that is the solution that should be progressed. If there is a question of affordability (as there currently appears to be) then consideration should be given to re-phasing each scheme to bring annual expenditure in line with government targets, in preference to reconsidering bus options which will not deliver anywhere near the same benefits. Such an approach would also minimise the abortive expenditure with which the promoters and bidders are currently faced.

REFERENCES

  1.  National Audit Office (NAO): Improving public transport in England through light rail, 23 April 2004.

  2.  From Notes of Manchester Metrolink Working Group Third Meeting, Wednesday, 17 November 2004.

D Scott Hellewell, FCILT, FCMI

Independent Transport Consultant

Wakefield

February 2005



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 10 August 2005