Select Committee on Transport Written Evidence


Memorandum by Serco Integrated Transport (LR 68)

THE FUTURE OF LIGHT RAIL AND MODERN TRAMS

  Serco is an international task management contractor to government and industry, providing comprehensive engineering and support services across a wide range of applications. Around 90% of Serco's business is with government and some 25% comes from outside the UK. The Company's capabilities derive from the extensive knowledge and experience of its 34,000 plus employees on all seven Continents in over 36 countries throughout the World. Today, Serco runs over 500 contracts around the World, spanning the transport, defence, health, science, state and local government sectors and has made a significant investment in a research institute that ensures international best practice is shared throughout the Group's worldwide business. Serco Integrated Transport operates the award winning Docklands Light Railway, Manchester Metrolink and the new Copenhagen Metro.

  If requested to do so, Serco would be happy to be called as witnesses to give evidence to the Transport Sub Committee and to answer any questions and clarify or expand on any of the points raised.

LIGHT RAIL—A SUCCESS OR A FAILURE

1.  INTRODUCTION

  Light Rail Policy in the UK demands that a full Benefit Cost Analysis (BCA) is completed taking into account all factors including, but not limited to, the forecast patronage, modal shift, environmental and commercial benefit, social inclusion and cost of designing, building, operating and maintaining the system. One of the major problems faced is the exuberance of the promoters of many such schemes regarding revenue expectations and the often overly optimistic assumptions when it comes to design, build, operate and maintenance costs. This results in an overestimate of the debt capacity which can be supported which ultimately could manifest itself as a perceived continuous increase in the grant required to support the venture. Recent problems in patronage build up on some systems after opening has exacerbated the problem with the Lenders who are taking a very pessimistic view of forecast revenues that therefore limits the borrowing capacity. This paper therefore attempts to provide suggestions as to how Light Rail systems in the UK can be developed in such a way that both the Public and Private Sector can develop a solution in partnership with risks being managed by those best able to mitigate them and with the requisite incentives for both parties to ensure a successful outcome with no surprises.

2.  BENEFITS OF LIGHT RAIL

2.1  Air Quality

  Though now better than for many years air quality is still a serious problem, particularly in urban areas where there are significant health effects. The use of LRT emitting no pollutants from the vehicle at the point of use goes a long way towards cleaner air. This is valuable in urban areas and traffic corridors where a modal shift to the system would reduce the high concentrations of pollutants generated by motor vehicles.

2.2  Congestion

  The use of LRT helps in a very positive way to reduce congestion.

  A conservative estimate puts the total number of car journeys saved as a direct result of trams at between 10-12 million, in Croydon alone the number is between 3-4 million. If the average car journey is eight miles round trip then this means a saving of over 80 million miles per year and more than three million gallons of fuel. Not only does the motorist save but the environment benefits from a reduction in local pollutants of more than 23,000 tonnes carbon dioxide.

2.3  Comfortable

  Comfortable, quiet and safe; LRT systems reach right into city centre pedestrianised areas; are relatively economical to use, run frequently such that a timetable is unnecessary, and surveys have shown that modal shift from private car is much more likely than with bus.

2.4  Indirect benefits

  For people who don't use LRT but would benefit from its construction for example, an accident associated with driving comprises a significant cost to the economy. Loss of life, personal injury, medical costs, property damage and human suffering represent declines in economic productivity, time away from work.

  There is an accident risk associated with any type of travel, regardless of the mode. However, road vehicles have a greater accident risk than LRT systems and by encouraging modal shift from highways to LRT, the number of accidents would decline and remaining highway users benefit from travel time savings as they become less congested.

2.5  Impact on property values

  Proximity to LRT systems has been shown to improve property values. The average property value increase near stations is in excess of 6% when compared to similar property located further away and vacancy rates are lower for commercial properties near stations.

2.6  In summary

  The year 2004 saw an encouraging increase in the usage of Britain's LRT's systems, 4.9% excluding the newly opened Nottingham Tram system and in particular the number of motorists that abandoned city driving, choosing instead to go by LRT.

  Even though some systems are already at close to full capacity, this compares to the 3.9% rise on national rail, 3% on buses and 0.6% on London Underground.

  Where towns and cities have shown the lead in introducing or re-introducing LRT systems, local motoring populations have seen the sense in leaving the car at home or outside the central areas LRT systems are now regarded as the type of public transport most likely to attract motorists out of their cars, the reasons cited being convenience, comfort, security, speed and cost

3.  ALTERNATIVES

3.1  Buses

  Although a necessary form of transport and an important element of any integrated transport solution, there is enough evidence from various cities both in the UK and Europe that car drivers cannot be tempted in large numbers to transfer from their cars to buses. However, a much larger proportion are prepared to use public transport when LRT systems is the main form of transport for all or part of their journey, eg where buses feed into an LRT system. The bus does not offer the same advantages with reducing congestion and air quality in city centres. The bus cannot compete with travel times achieved with most LRT systems. The UK bus market, with the exception of London, is deregulated and therefore has less control from local authorities in route design, headways and times of operations. Should bus operators outside London be asked to operate along major transport corridors at defined headways and operating hours, then most likely a number of operators will ask for operating subsidies.

4.  RECOMMENDATIONS TO ENSURE THE SUCCESS OF LIGHT RAIL

4.1  Revenue

  Patronage forecasting confidence remains low on new systems, despite various methods used and financier assessments and most lenders will take pessimistic forecasts to mitigate the risk of failure to meet debt payments. Lenders are not operators and the ability to "step-in" is a mechanism of last resort since it rarely solves the core problem of lack of revenue unless the Operator is failing so badly. Mitigation of this risk by the Authority, who is best placed to "encourage" use of the system through changes in subsidy and ticketing strategy across the whole Public Transport system in partnership with a suitably incentivised Private Sector operator would give much greater "comfort" to the Lenders and subsequently permit higher levels of borrowing.

4.2  Financing

  Financing new schemes is an important element in ensuring the viability of new LRT systems and the time and process of developing these schemes need to be reviewed and shortened where at all possible. LRT projects in Britain face difficult challenges from their conception, especially getting clear Government support for projects. The drawn out bid process employed under OJEU rules does not facilitate the decision making process, in many cases the project costs continue to rise just due to the length of the bid period. Every effort must be made by the promoter/authority to select a preferred bidder as soon as possible and to work together for a pre-agreed period to reach financial close to mitigate this risk.

4.3  Utility Diversions

  These have become a major cost in building new LRT systems or extensions. Utilities such as water and gas mains are usually dug up and moved when a new LRT system is built on streets in order to facilitate easy access in future. Utility diversions can therefore be a significant capital cost element of LRT systems. In the case of Croydon this was 10% of the £200 million construction cost.

  Constructors of new schemes have to pay 92.5% of the costs of diverting utilities whilst Utility companies pay 7.5% they gain the cost of having new infrastructure and considerably less maintenance costs. There must be a more equitable way of dealing with this but it requires the full support of the Authority who is in a much stronger position to deal with utility providers.

4.4  Involvement of the Private Sector

  Most local authorities employ various consultants to assist in the planning and design of new schemes to allow recommendations to Government on BCA and the estimation of funding required. Only once this is complete and the tender process starts, does the private sector become involved and only then are the full requirements established and a determination of risks and their ownership identified. This has led to the true cost of these schemes being realised after agreement on funding requirements has been reached with Government. Greater ownership from such advisors in the original estimates together with the early involvement of the private sector is required in order that large discrepancies are avoided (ie to ensure that the answer initially provided is not what the Authority want to hear necessarily but what they need to know)

4.5  Involvement of Property Developers

  A number of highly desirable properties are often developed along the LRT corridors as part of regeneration and the Authority should take more advantage of the increase in property values along transit corridors. A number of European schemes have tapped into this market and use funding from developers to help offset the cost of LRT's. There is little or no property developer involvement in the UK schemes and therefore possible links to assist in funding has not been fully explored. A number of new developments have already been built in and around the Manchester Metrolink's Phase 3 corridors, in anticipation of the opening of the new extensions.

  LRT systems benefit from high density land use, around some stops, particularly housing. Conversely where there is land for development that may remain undeveloped for a long period of time then the building of stops should be delayed to avoid stops being isolated and creating public concern for safety. This can be eliminated with a coordinated development approach and operational efficiency is enhanced in early years in this way.

4.6  Transport Integration

  Both current and future passengers are looking for the seamless journey from home to work with the shortest possible journey and where necessary the shortest connection time. In London the regulated transport market and ticket integration has aided the success of Docklands Light Railway and Croydon Tramlink. However outside London integration with bus services is perceived to be poor and with de-regulation the major bus operators generally compete with LRT's rather than act in harmony as feeders. Due to financial constraints within the bus sector routes and timetables remaining uncoordinated and there is little integration; the only exception to this is Nottingham Express Transit where the local bus operator has a significant role within the LRT operating consortium. However the operators of both bus and LRT have to ensure that competition law enforced by the Office of Fair Trading is not broken.

4.7  Early Operator Involvement

  Some LRT systems have experienced early operational problems. Most problems are due to late and often inadequate integration of various systems and the pressures of competition have often led to inexperienced consortia winning on price by reducing spend on early mobilisation activity and thorough systems integration and testing, at the cost of poor reliability on opening and subsequent lack of revenue and ridership. Whereas the experienced operators may mitigate this risk through more rigorous testing, they could be considered to be over priced. The recognition and insistence of Early Operator Involvement by the authorities could help mitigate this risk.

4.8  Risk

  The private sector is naturally cautious but not necessarily risk averse, so as new LRT schemes are tendered, planners and financiers take cautious and prudent views of ridership and fare revenues. On the other hand the public sector is requiring more risk transfer and as more risk is passed to the private sector, then risk margins increase the overall costs. A more optimum balance of risk transfer needs to be agreed between both the public and private sectors to allow a more realistic approach to costing risk.

4.9  Reliability and service delivery

  A number of issues have occurred in LRT systems due to poor reliability of assets or longer journey times than expected. It is essential for LRT to be able to deliver a safe, reliable a fast form of transport if ridership numbers are to be achieved. This starts at the procurement stage, with consideration given to whether there is one contract for the design, build and operation or whether separate contracts are let for each of the individual elements of the service, the latter introduces more integration risk. Consideration should be given to the industry as a whole as current operators may be able to advise on development of future routes or new schemes and drivers and engineers working on existing fleet of vehicles should be consulted in the design of future vehicles. Operational parameters should, ideally, be fully included in construction contracts to avoid unnecessary operating costs.

  Robust and workable incentives and penalty systems should be imbedded in contracts to insure that a partnership approach is achieved by contractors and clients to find the common objectives eg increasing patronage through ensuring everyone supports actions whilst being clear on costs and funding thereby jointly managing the project to ensure the delivery of a sound and robust LRT system.

5.  ACTIONS REQUIRED


BarriersIssues to be addressed

Transport IntegrationFurther develop Quality Bus Contracts
Review feeder routes and ticket integration
Review integration in the design stage
FinancingLocal authorities to review alternative forms of funding, including economic benefits where schemes increase the value of local trade property and land values
Further review the options to raise funds from the powers given in the Transport Act 2000
Utility DiversionsA review of cost associated with utility diversions should be undertaken
A cost benefit analysis should be undertaken on savings on maintenance once diversion is complete
Is Light Rail subsidising the utility companies on capital expenditure?
Private SectorPrivate sector partnering in the design stage will ensure that best practice and knowledge about what has worked well elsewhere both in this country and abroad. Learn from lessons learnt to avoid the same mistakes
Property DevelopersMore robust working arrangements to be established with developers to aid the funding and community growth along Light Rail corridors
RisksReview of risk transfer between public and private sectors could help reduce costs and attract more private sector investors
ReliabilityUse the private sector and other operators to learn from the lessons learnt from other schemes
Have a robust procurement strategy
Work in partnership with sound incentives and penalties to ensure service delivery and revenue targets are met

John H Taylor
MD Urban Transportation
February 2005






 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 10 August 2005