Select Committee on Transport Written Evidence


Memorandum by South Hampshire Rapid Transit (LR 86)

PHASE 1:  FAREHAM—GOSPORT—FAREHAM

INTRODUCTION—SCHEME DESCRIPTION AND STATUS

  South Hampshire Rapid Transit Phase 1 (SHRT 1) is a proposal for a 9 mile light rail system between the town centres of Fareham and Gosport and Portsmouth City centre and is being promoted jointly by Hampshire County Council and Portsmouth City Council. It would provide a new permanent link, via a tunnel under Portsmouth Harbour, which enables a seamless journey to be made between the Fareham—Gosport peninsula and Portsea Island. It also utilises a disused railway for two thirds of the route, which provides for swift reliable journey times.

  SHRT 1 has been in development since 1990. It has been through extensive consultation with members of the public and key third parties. In March 2001 approval for £170m (npv) of public sector funding was obtained and in July 2001 the Secretary of State for Transport granted the TWA Order, which meant the negotiated procurement process could be started.

  Procurement followed Treasury guidance for the public private partnership route, with invitations to tender issued to three pre-qualified private sector consortia in June 2002. One bidder dropped out two weeks before the deadline for tender returns but in December 2002 two consortia returned bids for a concession lasting 33 years to design, construct, operate, maintain and part finance the system. The bids exceeded the approved funding limit, which after a protracted project review led to the transport secretary deciding not to approve the additional cost. The Department then revoked the funding agreement for SHRT1 in July 2004.

  Both bidders remain committed to what is a stalled procurement process. In September 2004 DfT officials requested that the promoters review the scope of the scheme and the risk profile to see if substantial savings could be made. This is proceeding with a revised submission planned for March 2005.

THE COSTS AND BENEFITS OF LIGHT RAIL?

  Light rail schemes, like other transport schemes are evaluated in cost benefit terms using the standard methodology required by the DfT (and HM Treasury) for major investment in the transport system. The outcome is a benefit cost ratio (BCR) that enables the performance of a particular scheme to be compared with alternatives as well as other schemes in different locations throughout the UK. The method, however, quantifies benefits which focus on the transport essentials and fails to capture the full potential value that light rail can help to deliver in terms of local regeneration and economic growth. A recent move to quantify economic impact attempts to capture more of the potential benefits that light rail schemes can deliver but the results are still likely to understate the value of light rail in the wider transport, land-use and regeneration context. The point is given further weight by the empirical evidence gathered for the PTEG report, "The Case for Light Rail".

  Typically the performance of light rail in metropolitan areas is considered against the circumstances where it would overlay existing public transport such as an existing underperforming heavy rail line or an over capacity bus route. In these situations the case stands on the added value of light rail over the existing public transport service. As a consequence it is often more challenging for light rail to demonstrate a high BCR. The exception is where a light rail proposal would provide a new link in the public transport network. Such is the case for SHRT 1, which utilises a disused railway formation and provides a new permanent link across Portsmouth Harbour. As a result it has a BCR of 3:1, which places the scheme in the high value for money bracket.

WHAT LIGHT RAIL SYSTEMS NEED TO BE SUCCESSFUL?

  Government and local authorities need to reach a common and thorough understanding of light rail and the circumstances in which it can deliver added value over alternative modes so that these characteristics can be applied effectively to particular situations. Of equal importance is that projects are brought forward inline with established priorities and affordability constraints. Regional economic, transport and spatial strategies should provide the reference framework for setting future investment priorities including light rail schemes. This strategic approach should provide a more stable environment to support the delivery of effective projects.

  Most elements of the delivery process require cross working to achieve objectives. For example, light rail schemes will be more successful serving high-density residential areas where public transport is given priority over other road users. To achieve this requires the collaboration of public transport executives, private sector public transport operators, and highway and planning authorities. Such an arrangement is recognised in South Hampshire and has led to the formation of Solent Transport Partnership. This initiative has established a partnership of transport operators, representative organisations for the private motorist, freight organisations and local businesses, local authorities, and regional and national government organisations. In March 2003 members signed the Solent Transport Charter to assist in achieving sustainable economic growth for South Hampshire. This integrated management approach acts as a delivery device and progress is already manifest with the recent introduction of the Solent Travel Card, which is valid across all bus services and will shortly cover trains and ferries.

HOW EFFECTIVELY IS LIGHT RAIL USED AS PART OF AN INTEGRATED TRANSPORT SYSTEM?

  It is perhaps helpful to consider an integrated transport system from three aspects.

    (1)  that the physical design of the system provides for accessibility and connections between different travel modes;

    (2)  that integrated services are established involving bus feeder connections and heavy rail services, together with Park and Ride facilities, which together coordinate travel across the local transport system; and

    (3)  that travellers benefit from the convenience of integrated ticketing and co-ordinated real time travel information services.

  By its nature light rail provides connectivity benefits by being able to link directly with principle travel origins and destinations. A well-designed scheme should take full advantage of this potential. Co-ordinating light rail services with buses and heavy rail presents more of a challenge particularly if the system provides scope for commercial competition between travel modes. Ideally the superior level of service offered by light rail should avoid the need for regulating against wasteful competition from other modes, particularly buses. For example the SHRT1 project would enjoy a competitive advantage over other modes, due to the dedicated tunnel under Portsmouth Harbour. A well designed light rail scheme with a clear competitive advantage over car travel can grow the local public transport market and in these circumstances commercial bus operators have a business interest in providing services that feed the light rail corridor instead of competing with it. In most circumstances it will however not be possible to rely on this self regulation and light rail promoters will need to consider how best to moderate commercial freedom through quality bus partnerships and quality contracts.

BARRIERS TO THE DEVELOPMENT OF LIGHT RAIL?

  These can be split into pre and post procurement process.

  Pre-procurement the Transport and Works Act process often leads to the promoters being obliged to undertake protective measures designed to keep third party interests whole, in particular the public utilities and Network Rail. This has commercial significance on later value for money and affordability issues, which is very often not recognised by the promoters during the planning phase. Effective risk management processes need to be put in place earlier to enable risk to be removed or mitigated at the appropriate time. If this is not achieved promoters could be placed in a position where to finalise a contract with the private sector becomes prohibitively expensive. Better value for money could be achieved in striking the right balance of public interest with institutions such as public utilities and Network Rail, where the outcome is agreed at national level.

  During procurement the complex delivery of light rail schemes requires effective project management. The Department's past involvement can be described as being at arms length as it tends to delegate the delivery authority to the light rail promoters. This delegation however comes without investment authority and recent events have shown this approach to be unsustainable leading to the revocation of funding on three light rail schemes. More effective change management control involving the Department directly during procurement development could have avoided this breakdown in trust.

  The light rail programme launched in 2001 introduced a step change in the value and complexity of business to be delivered using Local Transport Plan resources. Local delivery teams were supported by specialist advisers but this expertise was not extended to the local transport team at DfT. Consequently unfamiliarity with the specialist procurement skills required to deliver these complex programmes has prevented the Department from taking an active part during the delivery process. Arrangements to rectify this are now being implemented by the Department.

  Better supply chain management is needed. The light rail programme has not benefited from any effective programme management. There could be considerable benefits from a more reliable deal flow in the light rail sector. Greater consultation with the industry at large is needed.

  At a strategic level DfT need to take ownership of the national light rail programme and to engage with suppliers to raise the confidence over the actual commercial opportunities in the sector. It should be noted that the collapse of light rail procurement has put supplier confidence at an all time low. Industry forums such as UK Tram will be able to support DfT in this leadership role.

  The committee will receive representations from others regarding the benefits of greater consistency of standards and specifications across the industry.

THE EFFECT OF DIFFERENT FINANCING ARRANGEMENTS (PUBLIC/PRIVATE) ON THE OVERALL COST OF LIGHT RAIL SYSTEMS

  The market response to procurement based on PFI principles suggests a more conventional approach would deliver better value for money. It appears that the PFI approach has been destabilised by the stance taken by promoters in passing all revenue risk to the private sector. Splitting the infrastructure provision from the system operation, such as the model used on Docklands Light Railway, may well treat market failure. However, there is a danger that there could be an over reaction as light rail promoters retain more risk. In doing so they need to ensure that they appreciate the type and scale of risk and that they have the competencies in place to manage it.

  The underlying philosophy of applying PFI procurement for light rail remains sound but the delivery has been flawed mainly by transferring full revenue risk.

THE PRACTICALITY OF ALTERNATIVES TO LIGHT RAIL, SUCH AS INCREASED INVESTMENTS IN BUSES?

  Light rail can be the right transport option in certain locations. As with any investment decision, you must be prepared to have confidence in your options appraisal and evaluation methodology, and its conclusions. It should however, also be recognised that affordability pressure can result in decisions that appear perverse in hindsight when systems are designed for 30 to 60 years.

February 2005



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 10 August 2005