Select Committee on Transport Written Evidence


Memorandum by The Chartered Institute of Logistics and Transport (UK) (LR 96)

INTEGRATED TRANSPORT:  THE FUTURE OF LIGHT RAIL AND MODERN TRAMS IN BRITAIN

1.  THE COSTS & BENEFITS OF LIGHT RAIL

1.1  Costs

  1.1.1  Costs of light rail schemes have, quite rightly, come in for a lot of criticism recently. To determine why costs have risen so much it is necessary to identify the principal cost heads, which are: Promotional Costs, Bidding Costs, Construction Costs, Operating and Maintenance Costs, Funding and Fee Costs. Under a number of these headings there is also the pricing in of risk, technical, legal or financial. Contingency allowances and risk are brought in at each stage and thus compound any basic cost increases. In part, this is due to the inappropriate allocation of risk by or to the parties involved. In part, it is due to the methods by which British LRT schemes are procured.

  1.1.2  Promotional Costs are those incurred by the Promoter and include all the pre-planning necessary to determine the route of the scheme, location of stops and depot. It includes details of vertical and horizontal alignment, preparation of Book of Reference and an Environmental Impact Statement, ie all the work necessary to obtain an Order under the Transport & Works Act 1992. Thereafter is likely to follow a Public Inquiry. It also includes appraisal work in order to obtain government funding approval in principle/PFI credits. This is an excessively long and complex process which should be simplified. This would reduce both cost and timescale.

  1.1.3  Bidding Costs are those incurred by the Consortia bidding to design, build, finance, operate and maintain the LRT scheme for the concession period. (Alternative arrangements are considered in Section 5.) Functional system specifications will have been prepared by the Promoter and it is then for each Consortia to prepare designs in sufficient detail for cost-estimates to be prepared. Time is of the essence because of the competitive nature of the process. Accurate costing, based on sufficient information, may be difficult to achieve and therefore be covered by contingency or risk allowances.

  1.1.4  Construction Costs include all the infrastructure works and vehicles to operate the LRT system. Such systems are complex and, particularly where street-running is involved, have many interfaces, eg tram priorities and traffic management. This requires extensive consultations and variations to work done at earlier stages. Costs can easily escalate and construction plans become extended. There are many interfaces and good project management is essential. It is of note that each LRT scheme in Britain has been built by a different Consortium, suggesting that experienced Consortia may have priced-in their experience and thus priced themselves out of the bidding.

  1.1.5  Operating Costs come under two headings: Pre-operational Costs involved in setting up the operational arrangements; recruiting and training staff; testing and commissioning the system and trial running. The second heading is the steady-state costs of operating and maintaining the system, which are principally a function of the Promoter's operating specification. Consortia have some freedom to determine fare levels which influence passenger usage and income. LRT and tram schemes outside Greater London operate in a competitive environment. It is very difficult to assess, with any degree of reliability, the effect of bus competition. Debt financiers will not take risk on revenue forecasts and this has required more equity at higher margins. Conversely, the Promoter will have gone for optimistic passenger forecasts to justify the scheme. Promoters also have regard to the social benefits such a scheme would be expected to generate, but these social benefits do not normally produce a financial benefit for the Consortia.

  1.1.6  Funding and Fee Costs. Funding costs tend to be higher than for public sector borrowing, although capital costs in traditional PFI/PPP are lower than in classic public sector procurements. Fee Costs are a considerable element in all UK LRT schemes because they are undertaken by private sector Consortia who are expected to carry considerable risk. Furthermore, the contractual arrangements between the various members of each consortia and their sub-contractors, require very extensive and complex contractual documentation, all with their own termination and penalty clauses. This is an area where there is potential for simplification and cost reduction.

1.2  Benefits

  1.2.1  LRT and modern tram schemes offer:

    —  safe, fast, reliable, frequent services

    —  overall, environmental benefits

    —  accessible stops and vehicles for easy use by all

    —  improved public transport "offer", at reduced cost compared to any heavy rail service they may replace

    —  electric traction

    —  ability to attract motorists out of their cars

    —  assistance in the regeneration of run-down areas

    —  comprehensive passenger information system

    —  efficient use of road space.

  1.2.2  An LRT "package" would normally include a high level of segregation from other transport by having its own dedicated right-of-way. It would also have priority over other traffic when running on-street. A comprehensive passenger information system also comes as part of the package. Many of these features are "add-ons" to bus systems.

2.  WHAT LIGHT RAIL SYSTEMS NEED TO BE SUCCESSFUL

  2.1  To be successful LRT/modern tram systems need to:

    —  be fully integrated with other public transport

    —  have adequate park and ride provision

    —  be well related to existing and future land-use developments

    —  have a high degree of segregation

    —  offer quick journey times

    —  have reasonable passenger flows upwards of 3,000 pphpd.

3.  HOW EFFECTIVELY IS LIGHT RAIL USED AS PART OF AN INTEGRATED TRANSPORT SYSTEM?

  3.1  Outside Greater London Britain pursues a unique public transport policy amongst developed nations, particularly our Continental competitors. In these cases (in London, abroad and elsewhere in Britain until about 1985), LRT provides the backbone to an integrated public transport where bus plays a complementary role, rather than a competitive one. This is how Tyne and Wear Metro was conceived and operated very successfully until the 1985 Transport Act deregulated provincial public transport. Dockland Light Railway (DLR), apart from being fully segregated, was fully integrated into—indeed was the catalyst—for the redevelopment of Docklands. It has gone from success to success. Similar comments apply to Croydon Tramlink, although its financial performance has been disappointing to its Concessionaire, where bus services were unsatisfactorily restructured around the new system.

  3.2  Conversely, all other schemes—Manchester Metrolink, Sheffield Supertram, Midland Metro and Nottingham Express Transit—operate in a very competitive environment, which was not the wish of their Promoters. The Competition Act and its interpretation by the Competition Commission and the OFT, also adversely affects the integration of public transport. These issues need to be addressed. Furthermore, there is no formal link between LRT Promoters (usually PTAs/PTEs), land use planning and highway authorities, further hindering the development of LRT schemes.

4.  BARRIERS TO THE DEVELOPMENT OF LIGHT RAIL

  4.1  The barriers to LRT development have been touched upon in Sections 2 and 3 but are summarised here for convenience:

    —  lack of integration with the rest of public transport network

    —  lack of integration with land-use planning

    —  insufficient priority when running on-street

    —  inadequate car parking provision

    —  the Competition Act and its application

    —  cost and timescale of implementation (x-ref Section 1)

    —  the procurement methods adopted more recently (refer to Section 5).

  Most of these were well-identified in the NAO Report (23 April 2004).

5.  THE EFFECT OF DIFFERENT FINANCING ARRANGEMENTS (PUBLIC/ PRIVATE) ON OVERALL COST OF LIGHT RAIL SCHEMES

  5.1  It is generally accepted that the cheapest way of procuring any major investment in public transport is for it to be procured by a public authority and built and operated by the private sector following competitive tender. Public authorities have cheaper access to money and are more able to take some of the risks. Such an approach, of course, has implications on the PSBR and in recent times has been unacceptable to HM Treasury and successive governments. So whilst Tyne and Wear Metro and DLR were publicly procured—the former under "classic" arrangements and the latter by way of a turnkey DBOM contract, and remain in public ownership—Metrolink and subsequent LRT schemes have until now been procured by some PPP/PFI formula. The actual contractual arrangements have varied from: DBOM (Design, Build, Operate & Maintain) to DB:OM; DB Finance DM, DB Transfer Operate. These are highly complex arrangements, difficult and costly to establish, and requiring skilful project management.

  5.2  LRT & modern tram systems are, inevitably, complex projects, calling on many design and building skills. The operational requirements must be input from the start of the process and continually borne in mind. There are many interfaces, all of which must be skilfully managed, if the scheme is to be delivered on-time, on-budget and "fit-for purpose". The British have found this very difficult to achieve, hence the current attitudes to LRT. Furthermore, this approach precludes any degree of standardisation or commonality of equipment or componency—adding further to cost and unreliability. There is no element of transfer-of-knowledge from one scheme to another, although the proposed UKTram umbrella organisation should improve this. This is in marked contrast with Continental developments, particularly in France where 10 schemes have been built, compared to five in Britain—in the same timescale.

6.  THE PRACTICALITY OF ALTERNATIVES TO LIGHT RAIL, SUCH AS INCREASED INVESTMENT IN BUSES

  6.1  The bus has a lot of good features and is often maligned. Buses range from minibuses to megabuses, with midis, single and double-deckers and artics in between. They can be diesel or electrically powered, or hybrid. However, all buses suffer from the same problem. They share their road space with other traffic. Whilst some local authorities have shown a willingness to provide bus priorities, many have been very slow. Continuous lengths of bus lane or busways are virtually non-existent in Britain. The policing of bus lanes is also poor, with regards to keeping them free flowing. Buses are rarely given priority over other traffic at traffic signals. Until these issues are addressed seriously buses will never offer the quality and reliability of service and absence of bunching, which is the accepted norm of LRT or modern tramway operation.

  6.2  By its very nature LRT is a system offering, in one package, the benefits shown in paragraph 1.2.1. Even with bus-only lanes or busways, guided or otherwise, all the basic features of LRT come as extras to bus-based systems. However, well-developed buses can never offer either the commercial or social benefits that can be delivered by LRT. Promoters of LRT systems will have already undertaken comparative studies before even embarking upon their LRT scheme. DfT will have been involved at every stage. There is no point in asking them to "to go back to the drawing board" to revisit a bus-based scheme when they have already carried out the comparative evaluation. If the affordability to public funds is the issue, then in addition to focusing on the causes of cost increases referred to in Q1 and achieving reductions, consideration should be given to rephasing the scheme.

March 2004



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 10 August 2005