Select Committee on Transport Minutes of Evidence


Examination of Witnesses (Questions 200 - 219)

WEDNESDAY 9 MARCH 2005

MR PAUL DAVISON, MR ROGER HARDING, MR PETER HENDY, MR PAT ARMSTRONG AND MR NEIL SCALES

  Q200  Ian Lucas: Mr Davison wants to respond to that.

  Mr Davison: I will respond to a couple of the issues. One is that it was late and over budget. Late it was, by about six months. It did not cost us a penny more than we said we would pay for it and it did not cost the public a penny more than we said we would pay for it. We said we would pay just short of £200 million and that is what we paid the builder. Any costs overrun was absorbed by the builders and they took that on the nose. It was not a massive cost overrun—I do not have the detailed figures but I can probably get them for you—but it was of the order of 10%, which on a first of build for a long while—and certainly for the team who built it—is a reasonably creditable performance, and at £7 million or £8 million a tram route kilometre it is substantially cheaper than the figures I see at the moment, which are at least two and a half times that, and I have to say that I do not understand why they are two and a half times that, having looked very carefully at the build cost for a tram link. In terms of integrating the transport, we have looked at what was proposed and where we are now and if we just look at the number of bus miles that are run around Croydon, on routes that parallel the tram routes there are approaching 30% more bus miles run over the period since 1995-96. I think it is odd that we are running more bus miles along the routes and not running more bus miles to join up with the tram scheme and then use the trams as the way to get into central Croydon. It is not meant to be a claimant's document, I am just trying to make the point that it is crucial to tram schemes in general that you restructure and integrate the buses. It has been done in Nottingham, to good effect. Equally, it is good that we have park and ride. There is no parking at all on Tramlink, and park and ride takes people out of their car and puts them on public transport in circumstances where you can then get high volumes of people into the centre of Croydon or Wimbledon or wherever, fairly economically. It seems to me that we should have done more to try to get this integration since the tram scheme opened in 2000.

  Q201  Mrs Ellman: Is there enough certainty in Government funding for light rail systems?

  Mr Scales: I think on our particular scheme we are very fortunate to have the indicative funding of £170 million. We then had to do a lot of work with our colleagues in the Department of Transport to satisfy in terms of the risk transfer, in terms of all the modelling that we have had to do—and fortunately we built a three-line model for Merseytram before we actually got this far. I think the real risk is our colleagues in the Treasury and the Department have got to go at the Treasury and fight their corner along with everybody else. So I think that is the real issue. The contractors and builders and our colleagues on the operating side like certainty. I think there is enough certainty as long as you have made your case and the Department have enough ammunition to go to the Treasury with.

  Q202  Mrs Ellman: Three lines are planned for Merseytram, how confident are you that three lines will in fact be built?

  Mr Scales: I think I am all right on Line 1. Our colleagues in the Department for Transport have got annex E, the public sector bid for Line 2 and we can evaluate that once we get Line 1 out of the way. Line 3, down to the airport, we could run into difficulty with that only because it is so far in the future and I do not know the exact route because we have not done the work on the route yet. But we have a heavy rail option and we are building a large interchange at Allerton, as you know, which is going to serve the airport as well. Allerton interchange is three kilometres from John Lennon Airport.

  Q203  Mrs Ellman: Mr Armstrong, you referred earlier to getting the nod from the Department. Is a nod good enough?

  Mr Armstrong: It is always very difficult to have that certainty. As I explained earlier, it was a very long time before we got the go ahead for Line 1 and that uncertainty is very difficult, particularly for the private sector, to live with and also to maintain public support locally both politically and from the general public. When I said, "nod", yes, it is something more than that, but it is certainly a very conditioned approval that we are hoping to get for our phase two, and we would like to think fairly quickly. If I can just make the note, Nottingham's Express Transit is exactly one year old today, so it is quite an auspicious time to be down here.

  Q204  Mrs Ellman: Mr Hendy, did you want to add to that?

  Mr Hendy: Yes, I think I should add to the witness in the previous session who mentioned UK Tram. The light rail and tram industry as a whole recognises that one of the criticisms and worries that Government has about these systems is the apparently rapidly inflating cost of building these systems, and a lot of that is around what the previous witness was questioned about, which is the particular procurement of individual systems, the low volume of cars purchased, the experience which appears to be relived in different systems and about difficulties in construction. So one of the practical ways we can help Government feel more comfortable about the quoted costs and the quoted patronage is to do the work under UK Tram, which is about trying to establish better methods of procurement, the most appropriate procurement, reducing the risk premium particularly for construction and the equipment, and other things to get not standard cars, but standardised specifications. I do not think you will find anybody in the wider industry who does not believe that this is a good thing to do, to give Government a bit more confidence than it currently has that the cost of these things will not just spiral out of control either now or in the future.

  Mr Davison: If I could add one feature? I have been involved in major projects certainly through the first part of my career and one of the things that you do get is you get economies of expertise, and the fact is that if we were building tramways at a reasonable rate, as they do in the rest of Europe, we would get this economy of expertise and it would mean that people build higher quality products, they find the quick and easy ways to build it and they find the quick and easy ways to specify it, and you end up with major economies, and they ought not be discounted. They can be very, very high in terms of the way in which a £200 million project might have over three or four iterations declined to be 50% almost of the original process.

  Q205  Mrs Ellman: Do any of you detect any change in Government policy towards light rail? Do you think that Government is less keen than it was?

  Mr Davison: I feel we have actually to some extent prejudiced the future of light rail because everybody sees us as a problem.

  Q206  Chairman: "We" being who?

  Mr Davison: Croydon Tramlink, how we have been seen to be a difficult project at some stage. But I think that the benefits are not sold on the general integrated transport high volume routes, and the fact that if you make the risks predictable and share them properly they can be very good projects and they would be seen as being an advantage in the same way they are in major cities across Europe.

  Q207  Chairman: Mr Scales?

  Mr Scales: I think it is all about minimising risk, Chairman, and what we have tried to do on Merseytram is minimise the risk. We have done topographical surveys along the route, tree surveys, we have been working with the statutory undertakers for five years, we know where all the stats are on the route; we have dug about 1,000 holes to make sure that—

  Q208  Chairman: Do the utilities know where the facilities are along the route?

  Mr Scales: They do now on our route, Chairman; they did not before. It is all about minimising risk. Fortunately we have this three-line model as well, so our economists can talk to the Department's economists and do all sorts of sensitivities. But no plans of first contact with the enemy and the only thing you can guarantee about a business plan it will be wrong! So what we have tried to do with our colleagues in the Department is to get the 95% and just go with it. That is what we want to do. So it is all about minimising risk.

  Q209  Mrs Ellman: But it is possible for the Department to withdraw funding part way through a project; is that correct?

  Mr Hendy: It is very hard for them to do that when people are digging holes in the ground and I think that is one of the difficulties, that when you start on one of these things you do have to finish it. The Department also, and I think with some cause, have been rightly worried about the fact that many of the projects in Britain have failed to achieve the passenger numbers which the promoters claimed in the beginning. We have already discussed some of the reasons for that and I think that it is incumbent on the promoters, both public sector promoters and the consortia that get into these things, to be realistic about passenger generation because there are some spectacular differences between the passenger numbers claimed for the systems before they operate and ones which turn up in practice. That does lead to giving the Department some considerable nervousness.

  Mr Scales: The practice we adopted was to get the operators on board very early—two years before we applied for the Transport and Works Act Order—and it is their numbers that have gone into our model, it is their numbers that have been validated and it is their numbers that are in the business case because at the end of the day we are looking for an operator colleague for 25 years, so they have to make that work for 25 years. So what we have done is not use silly numbers on our patronage figures, but we have had the private sector validate them and the private sector warrant them.

  Q210  Mrs Ellman: What about evaluation of light rail schemes? Do you feel that the criteria used are reasonable and the assessment is reasonable?

  Mr Scales: We used the new approach to transport appraisal, which is environment, safety, economy, accessibility and integration and our benefit cost ratio is really, really low because we are going through some of the poorest areas in the land—six of our pathways areas are areas of multiple deprivation. So our benefit cost ratio is just about over one because we are tying the tram fares to bus fares because the people along the route do not have any time value of money. So having embraced the new approach to transport appraisal, when the Department start loading the rates of 1.5 to one our scheme will necessarily be in difficulty. In Mr Stringer's area, where a metro link is already established, for example, they can easily get benefit costs ratios of two to one because they can do premium fares and we cannot. So I think we are okay as long as we recognise that there is no generic tram system in the UK, they are all different, but they are not all appraised in one single way and I think that is something that needs to be looked at.

  Q211  Chairman: I am going to stop you there. That is fine but you were asked about evaluations. Mr Rowland said to do an evaluation would cost between £10 million and £15 million. Firstly, do you think that is right, do you think it is necessary and do you think those are reasonable costs?

  Mr Scales: I think they are reasonable costs because Mr Rowland is the accounting officer for each of those projects so he has to be satisfied.

  Q212  Chairman: I accept that.

  Mr Scales: Whether they are reasonable costs or not, I do not have the figures, but we spent in Merseytravel something like £15 million on Line 1 just to get it up and running.

  Q213  Chairman: Would you think that to say it would cost £15 million to evaluate whether that was actually worthy and whether the figures were right would be a fairly sensible assessment or an over the top assessment?

  Mr Scales: I think that is excessive, Chairman.

  Q214  Clive Efford: Mr Hendy, why is there no park and ride on the Croydon Tramlink?

  Mr Hendy: I think you will need to ask the London Borough of Croydon that. I think they have declined to give planning permission for any park and ride schemes. You will know that although Transport for London has very great powers it does not have local planning powers. It is not the case that there might not be good sites for it, but they do need to be local authority approved, and bearing in mind the borough were the joint promoters of the original Act they clearly had good reason—admittedly of their own—for not giving planning permission to proposals which had been made.

  Q215  Clive Efford: Is it a missed opportunity for integration?

  Mr Davison: As I understand Croydon's position, they do not want to be a sort of parkway round the edge of south London, so that people park at a park and ride site on the Tramlink and then travel straight into central London, avoiding Croydon. There seems to me to be the opportunity to put park and ride sites to relieve road congestion and then use the relieved road congestion, for instance, for building another tramway. So if you put a park and ride site at Purley to take the cars off the road and then put a tramway Purley to Streatham, and that way you end up with moving people on to public transport rather than them just parking in a particular area when they are coming from the south coast, and you actually get modal shift that way.

  Q216  Clive Efford: Mr Hendy, with the West London tram and the Tramlink extension at Crystal Palace and the Canning Town, Royal Arsenal tram links we can expect better integration of those schemes because you are managing them from the start?

  Mr Hendy: I think you can expect us to seek to exploit park and ride opportunities where they would naturally occur, providing that local authorities are willing to accept park and ride into the local community.

  Q217  Clive Efford: What is the future for the park and ride that is currently taking place at Greenwich North station? There is a car park that takes over 1,000 cars a day that is going to be built on and there will be no park and ride area any more.

  Mr Hendy: I would have to get back to you on that; I have no knowledge of that particular location.

  Q218  Clive Efford: So the income from the car park, does it come into Transport for London?

  Mr Hendy: I think it does not.

  Q219  Clive Efford: It must be phenomenal.

  Mr Hendy: That, if I may say, is a second or third order issue. You are talking about North Greenwich on the Jubilee line? I do not think all the car parking space is going to be built over.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 10 August 2005